Feature #4974: Ensamble de Prototipo
Feature #4974: Ensamble de Prototipo
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 11/14/2025 Assignee: Priority: High
Feature #5439: Ensamble de Receptores de b...
Feature #5439: Ensamble de Receptores de bloques.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Camilo Geraldo Priority: Normal
Feature #5440: Ensamble del motor del prot...
Feature #5440: Ensamble del motor del prototipo.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Ignacio Cuevas Priority: Normal
Feature #5442: Ensamble y Modificación de ...
Feature #5442: Ensamble y Modificación de Brazos Giratorios.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Maximiliano Burgos Priority: Normal
Feature #5443: Modificación y Ensamble de ...
Feature #5443: Modificación y Ensamble de pistón giratorio.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Jose Quispe Priority: Normal
Feature #5646: Bitácora semana 2
Feature #5646: Bitácora semana 2
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Priority: Normal
Feature #5942: Planificar primer diseño ba...
Feature #5942: Planificar primer diseño base del robot
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Priority: Normal |
30 |
1
Feature #5439: Ensamble de Receptores de b...
Feature #5439: Ensamble de Receptores de bloques.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Camilo Geraldo Priority: Normal
Feature #5440: Ensamble del motor del prot...
Feature #5440: Ensamble del motor del prototipo.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Ignacio Cuevas Priority: Normal
Feature #5442: Ensamble y Modificación de ...
Feature #5442: Ensamble y Modificación de Brazos Giratorios.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Maximiliano Burgos Priority: Normal
Feature #5941: Introducir y Explorar en el...
Feature #5941: Introducir y Explorar en el set de LEGO Spike Prime
Project: GRUPO 3 Status: New Start date: 09/27/2025 Due date: 10/01/2025 Assignee: Priority: Normal
Feature #5004: Ajustes a diseño del protot...
Feature #5004: Ajustes a diseño del prototipo.
Project: GRUPO 3 Status: Resolved Start date: 10/01/2025 Due date: 10/10/2025 Assignee: Maximiliano Burgos Priority: Normal |
2 |
3
Feature #5443: Modificación y Ensamble de ...
Feature #5443: Modificación y Ensamble de pistón giratorio.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Jose Quispe Priority: Normal
Feature #5646: Bitácora semana 2
Feature #5646: Bitácora semana 2
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Priority: Normal
Feature #5942: Planificar primer diseño ba...
Feature #5942: Planificar primer diseño base del robot
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Priority: Normal
Feature #4851: Revisión y prueba de mecani...
Feature #4851: Revisión y prueba de mecanismo de empuje de bloques.
Project: GRUPO 3 Status: Feedback Start date: 10/03/2025 Due date: 10/06/2025 Assignee: Camilo Geraldo Priority: High |
4 |
| 41 |
5 |
6
Feature #4851: Revisión y prueba de mecani...
Feature #4851: Revisión y prueba de mecanismo de empuje de bloques.
Project: GRUPO 3 Status: Feedback Start date: 10/03/2025 Due date: 10/06/2025 Assignee: Camilo Geraldo Priority: High
Feature #5647: Bitácora semana 3
Feature #5647: Bitácora semana 3
Project: GRUPO 3 Status: Resolved Start date: 10/06/2025 Due date: 10/10/2025 Assignee: Priority: Normal |
7 |
8
Feature #4970: Primer avance del Informe
Feature #4970: Primer avance del Informe
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/17/2025 Assignee: Priority: High
Feature #4976: Avance 1ra Parte Informe
Feature #4976: Avance 1ra Parte Informe
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/16/2025 Assignee: Camilo Geraldo Priority: High
Feature #4977: Carta Gantt
Feature #4977: Carta Gantt
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/16/2025 Assignee: Matias Sagredo Priority: High |
9 |
10
Feature #5004: Ajustes a diseño del protot...
Feature #5004: Ajustes a diseño del prototipo.
Project: GRUPO 3 Status: Resolved Start date: 10/01/2025 Due date: 10/10/2025 Assignee: Maximiliano Burgos Priority: Normal
Feature #5647: Bitácora semana 3
Feature #5647: Bitácora semana 3
Project: GRUPO 3 Status: Resolved Start date: 10/06/2025 Due date: 10/10/2025 Assignee: Priority: Normal |
11 |
| 42 |
12 |
13
Feature #5648: Bitácora semana 4
Feature #5648: Bitácora semana 4
Project: GRUPO 3 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Priority: Normal |
14 |
15
Feature #5005: Documentación de la planifi...
Feature #5005: Documentación de la planificación del proyecto
Project: GRUPO 3 Status: Resolved Start date: 10/15/2025 Due date: 10/17/2025 Assignee: Ignacio Cuevas Priority: Normal
Feature #5642: Github
Feature #5642: Github
Project: GRUPO 3 Status: Feedback Start date: 10/15/2025 Due date: 10/17/2025 Assignee: Priority: Normal
Feature #5643: Creación de repositorio
Feature #5643: Creación de repositorio
Project: GRUPO 3 Status: Feedback Start date: 10/15/2025 Due date: 10/17/2025 Assignee: Priority: Normal |
16
Feature #4976: Avance 1ra Parte Informe
Feature #4976: Avance 1ra Parte Informe
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/16/2025 Assignee: Camilo Geraldo Priority: High
Feature #4977: Carta Gantt
Feature #4977: Carta Gantt
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/16/2025 Assignee: Matias Sagredo Priority: High |
17
Feature #4970: Primer avance del Informe
Feature #4970: Primer avance del Informe
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/17/2025 Assignee: Priority: High
Feature #5005: Documentación de la planifi...
Feature #5005: Documentación de la planificación del proyecto
Project: GRUPO 3 Status: Resolved Start date: 10/15/2025 Due date: 10/17/2025 Assignee: Ignacio Cuevas Priority: Normal
Feature #5642: Github
Feature #5642: Github
Project: GRUPO 3 Status: Feedback Start date: 10/15/2025 Due date: 10/17/2025 Assignee: Priority: Normal
Feature #5643: Creación de repositorio
Feature #5643: Creación de repositorio
Project: GRUPO 3 Status: Feedback Start date: 10/15/2025 Due date: 10/17/2025 Assignee: Priority: Normal
Feature #5648: Bitácora semana 4
Feature #5648: Bitácora semana 4
Project: GRUPO 3 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Priority: Normal |
18 |
| 43 |
19 |
20
Feature #5438: Revisión/Corrección del Código
Feature #5438: Revisión/Corrección del Código
Project: GRUPO 3 Status: Resolved Start date: 10/20/2025 Due date: 10/27/2025 Assignee: Jose Quispe Priority: High
Feature #5639: Optimización del sensor de ...
Feature #5639: Optimización del sensor de color
Project: GRUPO 3 Status: Resolved Start date: 10/20/2025 Due date: 10/22/2025 Assignee: Priority: Normal
Feature #5649: Bitácora semana 5
Feature #5649: Bitácora semana 5
Project: GRUPO 3 Status: Resolved Start date: 10/20/2025 Due date: 10/24/2025 Assignee: Priority: Normal |
21 |
22
Feature #5639: Optimización del sensor de ...
Feature #5639: Optimización del sensor de color
Project: GRUPO 3 Status: Resolved Start date: 10/20/2025 Due date: 10/22/2025 Assignee: Priority: Normal
Feature #5636: Reorganización de la Secuen...
Feature #5636: Reorganización de la Secuencia de Ejecución
Project: GRUPO 3 Status: Resolved Start date: 10/22/2025 Due date: 10/27/2025 Assignee: Priority: High |
23 |
24
Feature #5649: Bitácora semana 5
Feature #5649: Bitácora semana 5
Project: GRUPO 3 Status: Resolved Start date: 10/20/2025 Due date: 10/24/2025 Assignee: Priority: Normal |
25 |
| 44 |
26 |
27
Feature #5438: Revisión/Corrección del Código
Feature #5438: Revisión/Corrección del Código
Project: GRUPO 3 Status: Resolved Start date: 10/20/2025 Due date: 10/27/2025 Assignee: Jose Quispe Priority: High
Feature #5636: Reorganización de la Secuen...
Feature #5636: Reorganización de la Secuencia de Ejecución
Project: GRUPO 3 Status: Resolved Start date: 10/22/2025 Due date: 10/27/2025 Assignee: Priority: High
Feature #5637: Calibración e Implementació...
Feature #5637: Calibración e Implementación de Control Remoto para Operación Manual
Project: GRUPO 3 Status: Resolved Start date: 10/27/2025 Due date: 10/29/2025 Assignee: Camilo Geraldo Priority: Normal
Feature #5650: Bitácora semana 6
Feature #5650: Bitácora semana 6
Project: GRUPO 3 Status: Resolved Start date: 10/27/2025 Due date: 10/31/2025 Assignee: Priority: Normal |
28 |
29
Feature #5637: Calibración e Implementació...
Feature #5637: Calibración e Implementación de Control Remoto para Operación Manual
Project: GRUPO 3 Status: Resolved Start date: 10/27/2025 Due date: 10/29/2025 Assignee: Camilo Geraldo Priority: Normal
Feature #5638: Ampliación de la estructura...
Feature #5638: Ampliación de la estructura receptora de bloques
Project: GRUPO 3 Status: Resolved Start date: 10/29/2025 Due date: 11/05/2025 Assignee: Matias Sagredo Priority: High
Feature #5640: Revisión de conexiones
Feature #5640: Revisión de conexiones
Project: GRUPO 3 Status: Resolved Start date: 10/29/2025 Due date: Assignee: Priority: Normal |
30 |
31
Feature #5650: Bitácora semana 6
Feature #5650: Bitácora semana 6
Project: GRUPO 3 Status: Resolved Start date: 10/27/2025 Due date: 10/31/2025 Assignee: Priority: Normal |