Calendar
Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday | |
---|---|---|---|---|---|---|---|
40 |
28 |
29
Feature #4974: Ensamble de Prototipo
Feature #4974: Ensamble de Prototipo
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Priority: Normal
Feature #5439: Ensamble de Receptores de b...
Feature #5439: Ensamble de Receptores de bloques.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Camilo Geraldo Priority: Normal
Feature #5440: Ensamble del motor del prot...
Feature #5440: Ensamble del motor del prototipo.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Ignacio Cuevas Priority: Normal
Feature #5442: Ensamble y Modificación de ...
Feature #5442: Ensamble y Modificación de Brazos Giratorios.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Maximiliano Burgos Priority: Normal
Feature #5443: Modificación y Ensamble de ...
Feature #5443: Modificación y Ensamble de pistón giratorio.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Jose Quispe Priority: Normal |
30 |
1
Feature #5439: Ensamble de Receptores de b...
Feature #5439: Ensamble de Receptores de bloques.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Camilo Geraldo Priority: Normal
Feature #5440: Ensamble del motor del prot...
Feature #5440: Ensamble del motor del prototipo.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Ignacio Cuevas Priority: Normal
Feature #5442: Ensamble y Modificación de ...
Feature #5442: Ensamble y Modificación de Brazos Giratorios.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/01/2025 Assignee: Maximiliano Burgos Priority: Normal
Feature #5004: Ajustes a diseño del protot...
Feature #5004: Ajustes a diseño del prototipo.
Project: GRUPO 3 Status: Resolved Start date: 10/01/2025 Due date: 10/10/2025 Assignee: Maximiliano Burgos Priority: Normal |
2 |
3
Feature #4974: Ensamble de Prototipo
Feature #4974: Ensamble de Prototipo
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Priority: Normal
Feature #5443: Modificación y Ensamble de ...
Feature #5443: Modificación y Ensamble de pistón giratorio.
Project: GRUPO 3 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Jose Quispe Priority: Normal
Feature #4851: Revisión y prueba de mecani...
Feature #4851: Revisión y prueba de mecanismo de empuje de bloques.
Project: GRUPO 3 Status: Feedback Start date: 10/03/2025 Due date: 10/06/2025 Assignee: Camilo Geraldo Priority: High
Feature #4964: Codificación
Feature #4964: Codificación
Project: GRUPO 3 Status: In Progress Start date: 10/03/2025 Due date: 10/16/2025 Assignee: Camilo Geraldo Priority: Normal |
4 |
41 |
5 |
6
Feature #4851: Revisión y prueba de mecani...
Feature #4851: Revisión y prueba de mecanismo de empuje de bloques.
Project: GRUPO 3 Status: Feedback Start date: 10/03/2025 Due date: 10/06/2025 Assignee: Camilo Geraldo Priority: High |
7 |
8
Feature #4970: Informe Final
Feature #4970: Informe Final
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/17/2025 Assignee: Priority: High
Feature #4976: Avance 1ra Parte Informe
Feature #4976: Avance 1ra Parte Informe
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/16/2025 Assignee: Camilo Geraldo Priority: High
Feature #4977: Carta Gantt
Feature #4977: Carta Gantt
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/16/2025 Assignee: Matias Sagredo Priority: High |
9 |
10
Feature #5004: Ajustes a diseño del protot...
Feature #5004: Ajustes a diseño del prototipo.
Project: GRUPO 3 Status: Resolved Start date: 10/01/2025 Due date: 10/10/2025 Assignee: Maximiliano Burgos Priority: Normal |
11 |
42 |
12 |
13 |
14 |
15
Feature #5005: Documentación de la planifi...
Feature #5005: Documentación de la planificación del proyecto
Project: GRUPO 3 Status: Resolved Start date: 10/15/2025 Due date: 10/17/2025 Assignee: Ignacio Cuevas Priority: Normal |
16
Feature #4964: Codificación
Feature #4964: Codificación
Project: GRUPO 3 Status: In Progress Start date: 10/03/2025 Due date: 10/16/2025 Assignee: Camilo Geraldo Priority: Normal
Feature #4976: Avance 1ra Parte Informe
Feature #4976: Avance 1ra Parte Informe
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/16/2025 Assignee: Camilo Geraldo Priority: High
Feature #4977: Carta Gantt
Feature #4977: Carta Gantt
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/16/2025 Assignee: Matias Sagredo Priority: High |
17
Feature #4970: Informe Final
Feature #4970: Informe Final
Project: GRUPO 3 Status: Resolved Start date: 10/08/2025 Due date: 10/17/2025 Assignee: Priority: High
Feature #5005: Documentación de la planifi...
Feature #5005: Documentación de la planificación del proyecto
Project: GRUPO 3 Status: Resolved Start date: 10/15/2025 Due date: 10/17/2025 Assignee: Ignacio Cuevas Priority: Normal |
18 |
43 |
19 |
20
Feature #5438: Revisión/Corrección del Código
Feature #5438: Revisión/Corrección del Código
Project: GRUPO 3 Status: Resolved Start date: 10/20/2025 Due date: 10/26/2025 Assignee: Jose Quispe Priority: Normal |
21 |
22 |
23 |
24 |
25 |
44 |
26
Feature #5438: Revisión/Corrección del Código
Feature #5438: Revisión/Corrección del Código
Project: GRUPO 3 Status: Resolved Start date: 10/20/2025 Due date: 10/26/2025 Assignee: Jose Quispe Priority: Normal |
27 |
28 |
29 |
30 |
31 |
1 |
issue beginning this day issue ending this day issue beginning and ending this day