Grupo 5A 2025 - Feature #4811: Etapa 1 Feature #4811: Etapa 1

Project: Grupo 5A 2025
Status: New
Start date: 09/02/2025
Due date: 10/29/2025
Assignee:
Priority: Normal
Grupo 5A 2025 - Feature #4812: Ideas de Proyectos Feature #4812: Ideas de Proyectos

Project: Grupo 5A 2025
Status: New
Start date: 09/02/2025
Due date: 09/08/2025
Assignee:
Priority: Normal

3

Grupo 2A 2025 - Feature #4799: Fase 1: Investigación y Pro... Feature #4799: Fase 1: Investigación y Prototipo Inicial

Project: Grupo 2A 2025
Status: New
Start date: 09/03/2025
Due date: 10/14/2025
Assignee:
Priority: Normal
Grupo 2A 2025 - Feature #4800: Investigación de ideas Feature #4800: Investigación de ideas

Project: Grupo 2A 2025
Status: Resolved
Start date: 09/03/2025
Due date: 09/09/2025
Assignee:
Priority: Normal

4

Grupo 3B 2025 - Feature #4984: Definición del problema y s... Feature #4984: Definición del problema y solución

Project: Grupo 3B 2025
Status: New
Start date: 09/04/2025
Due date: 09/09/2025
Assignee:
Priority: High
GRUPO 10 - Feature #5970: INICIO Y PLANIFICACIÓN Feature #5970: INICIO Y PLANIFICACIÓN

Project: GRUPO 10
Status: New
Start date: 09/04/2025
Due date: 12/19/2025
Assignee:
Priority: Normal

5

EPA-2025 - Feature #5417: Creación de Requisitos de A... Feature #5417: Creación de Requisitos de Alto Nivel

Project: EPA-2025
Status: New
Start date: 08/25/2025
Due date: 09/05/2025
Assignee:
Priority: Normal

6

37

7

8

Grupo 5A 2025 - Feature #4812: Ideas de Proyectos Feature #4812: Ideas de Proyectos

Project: Grupo 5A 2025
Status: New
Start date: 09/02/2025
Due date: 09/08/2025
Assignee:
Priority: Normal
GRUPO 2 - Feature #4865: 1ra reunion de planificacio... Feature #4865: 1ra reunion de planificacion sobre roles y proyecto

Project: GRUPO 2
Status: New
Start date: 09/08/2025
Due date: 09/08/2025
Assignee:
Priority: Normal
Grupo 4B 2025 - Feature #4854: Fase I - Planificación del ... Feature #4854: Fase I - Planificación del Proyecto

Project: Grupo 4B 2025
Status: New
Start date: 09/08/2025
Due date: 10/27/2025
Assignee:
Priority: Normal
Grupo 4B 2025 - Feature #4855: Lluvia de Ideas Feature #4855: Lluvia de Ideas

Project: Grupo 4B 2025
Status: New
Start date: 09/08/2025
Due date: 09/14/2025
Assignee:
Priority: Normal
GRUPO 2 - Feature #5669: fase 1 Feature #5669: fase 1

Project: GRUPO 2
Status: New
Start date: 09/08/2025
Due date: 10/31/2025
Assignee:
Priority: Normal
EPA-2025 - Feature #5418: Modelado del Sistema Feature #5418: Modelado del Sistema

Project: EPA-2025
Status: New
Start date: 09/08/2025
Due date: 10/03/2025
Assignee:
Priority: Normal

9

Grupo 3B 2025 - Feature #4984: Definición del problema y s... Feature #4984: Definición del problema y solución

Project: Grupo 3B 2025
Status: New
Start date: 09/04/2025
Due date: 09/09/2025
Assignee:
Priority: High
Grupo 2A 2025 - Feature #4800: Investigación de ideas Feature #4800: Investigación de ideas

Project: Grupo 2A 2025
Status: Resolved
Start date: 09/03/2025
Due date: 09/09/2025
Assignee:
Priority: Normal
Grupo 2A 2025 - Feature #4801: Lluvia de ideas Feature #4801: Lluvia de ideas

Project: Grupo 2A 2025
Status: Resolved
Start date: 09/09/2025
Due date: 09/09/2025
Assignee:
Priority: Normal
Grupo 1B 2025 - Feature #5488: Elección de proyecto a real... Feature #5488: Elección de proyecto a realizar

Project: Grupo 1B 2025
Status: New
Start date: 09/09/2025
Due date: 09/11/2025
Assignee:
Priority: Normal
Grupo 1B 2025 - Feature #5490: Fase 1: Diseño Feature #5490: Fase 1: Diseño

Project: Grupo 1B 2025
Status: New
Start date: 09/09/2025
Due date: 10/21/2025
Assignee:
Priority: Normal
Grupo 1B 2025 - Feature #5494: Redacción de bitácoras Feature #5494: Redacción de bitácoras

Project: Grupo 1B 2025
Status: New
Start date: 09/09/2025
Due date: 12/18/2025
Assignee:
Priority: Normal
Grupo 3B 2025 - Feature #4986: Creación de la maqueta Feature #4986: Creación de la maqueta

Project: Grupo 3B 2025
Status: New
Start date: 09/09/2025
Due date: 10/09/2025
Assignee:
Priority: High
Grupo 3B 2025 - Feature #4987: Creación de un boceto Feature #4987: Creación de un boceto

Project: Grupo 3B 2025
Status: New
Start date: 09/09/2025
Due date: 09/11/2025
Assignee: Tomás Carvajal
Priority: High
Grupo 5B 2025 - Feature #5025: Fase I Feature #5025: Fase I

Project: Grupo 5B 2025
Status: New
Start date: 09/09/2025
Due date: 10/25/2025
Assignee:
Priority: High
Grupo 5B 2025 - Feature #5026: Lluvia de Ideas Feature #5026: Lluvia de Ideas

Project: Grupo 5B 2025
Status: New
Start date: 09/09/2025
Due date: 09/13/2025
Assignee:
Priority: High
Grupo 6B 2025 - Feature #5566: Eleccion del proyecto Feature #5566: Eleccion del proyecto

Project: Grupo 6B 2025
Status: New
Start date: 09/09/2025
Due date: 09/13/2025
Assignee:
Priority: Normal
Grupo 2A 2025 - Feature #4802: Selección de la idea defini... Feature #4802: Selección de la idea definitiva

Project: Grupo 2A 2025
Status: Resolved
Start date: 09/09/2025
Due date: 09/10/2025
Assignee:
Priority: Normal
Grupo 4A 2025 - Feature #5497: Fase 1- Familiarización con... Feature #5497: Fase 1- Familiarización con el proyecto

Project: Grupo 4A 2025
Status: In Progress
Start date: 09/09/2025
Due date: 11/18/2025
Assignee: rene ayca
Priority: High
Grupo 4A 2025 - Feature #5512: Análisis Feature #5512: Análisis

Project: Grupo 4A 2025
Status: In Progress
Start date: 09/09/2025
Due date: 10/20/2025
Assignee: rene ayca
Priority: Normal
Grupo 5A 2025 - Feature #4813: Planteamiento Problemática Feature #4813: Planteamiento Problemática

Project: Grupo 5A 2025
Status: New
Start date: 09/09/2025
Due date: 09/10/2025
Assignee:
Priority: Normal

10

Grupo 2A 2025 - Feature #4802: Selección de la idea defini... Feature #4802: Selección de la idea definitiva

Project: Grupo 2A 2025
Status: Resolved
Start date: 09/09/2025
Due date: 09/10/2025
Assignee:
Priority: Normal
Grupo 5A 2025 - Feature #4813: Planteamiento Problemática Feature #4813: Planteamiento Problemática

Project: Grupo 5A 2025
Status: New
Start date: 09/09/2025
Due date: 09/10/2025
Assignee:
Priority: Normal
Grupo 2A 2025 - Feature #4803: Búsqueda de información com... Feature #4803: Búsqueda de información complementaria

Project: Grupo 2A 2025
Status: Resolved
Start date: 09/10/2025
Due date: 09/23/2025
Assignee:
Priority: Normal
Cibersegurity - Feature #5445: Análisis del proyecto Feature #5445: Análisis del proyecto

Project: Cibersegurity
Status: New
Start date: 09/10/2025
Due date: 09/19/2025
Assignee:
Priority: Normal

11

Grupo 1B 2025 - Feature #5488: Elección de proyecto a real... Feature #5488: Elección de proyecto a realizar

Project: Grupo 1B 2025
Status: New
Start date: 09/09/2025
Due date: 09/11/2025
Assignee:
Priority: Normal
Grupo 3B 2025 - Feature #4987: Creación de un boceto Feature #4987: Creación de un boceto

Project: Grupo 3B 2025
Status: New
Start date: 09/09/2025
Due date: 09/11/2025
Assignee: Tomás Carvajal
Priority: High
GRUPO 10 - Feature #4831: Planificación del Proyecto Feature #4831: Planificación del Proyecto

Project: GRUPO 10
Status: New
Start date: 09/11/2025
Due date: 09/11/2025
Assignee:
Priority: Normal
Grupo 3B 2025 - Feature #4988: Modelado digital Feature #4988: Modelado digital

Project: Grupo 3B 2025
Status: New
Start date: 09/11/2025
Due date: 10/07/2025
Assignee: Tiara Canepa
Priority: High
Grupo 5B 2025 - Feature #5484: Selección y definición del ... Feature #5484: Selección y definición del proyecto

Project: Grupo 5B 2025
Status: New
Start date: 09/11/2025
Due date: 09/13/2025
Assignee:
Priority: High
Grupo 5A 2025 - Feature #5603: Propuesta Solución Feature #5603: Propuesta Solución

Project: Grupo 5A 2025
Status: New
Start date: 09/11/2025
Due date: 09/15/2025
Assignee:
Priority: Normal
GRUPO 10 - Feature #4947: Asignacion de roles Feature #4947: Asignacion de roles

Project: GRUPO 10
Status: New
Start date: 09/11/2025
Due date: 09/12/2025
Assignee:
Priority: Normal

12

GRUPO 10 - Feature #4947: Asignacion de roles Feature #4947: Asignacion de roles

Project: GRUPO 10
Status: New
Start date: 09/11/2025
Due date: 09/12/2025
Assignee:
Priority: Normal
GRUPO 10 - Feature #4948: Eleccion diseño del robot Feature #4948: Eleccion diseño del robot

Project: GRUPO 10
Status: New
Start date: 09/12/2025
Due date: 09/25/2025
Assignee:
Priority: Normal

13

Grupo 5B 2025 - Feature #5026: Lluvia de Ideas Feature #5026: Lluvia de Ideas

Project: Grupo 5B 2025
Status: New
Start date: 09/09/2025
Due date: 09/13/2025
Assignee:
Priority: High
Grupo 5B 2025 - Feature #5484: Selección y definición del ... Feature #5484: Selección y definición del proyecto

Project: Grupo 5B 2025
Status: New
Start date: 09/11/2025
Due date: 09/13/2025
Assignee:
Priority: High
Grupo 6B 2025 - Feature #5566: Eleccion del proyecto Feature #5566: Eleccion del proyecto

Project: Grupo 6B 2025
Status: New
Start date: 09/09/2025
Due date: 09/13/2025
Assignee:
Priority: Normal
38

14

Grupo 4B 2025 - Feature #4855: Lluvia de Ideas Feature #4855: Lluvia de Ideas

Project: Grupo 4B 2025
Status: New
Start date: 09/08/2025
Due date: 09/14/2025
Assignee:
Priority: Normal

15

Grupo 5A 2025 - Feature #5603: Propuesta Solución Feature #5603: Propuesta Solución

Project: Grupo 5A 2025
Status: New
Start date: 09/11/2025
Due date: 09/15/2025
Assignee:
Priority: Normal
Tiro-Arco - Support #5010: Contextualización del Proyecto Support #5010: Contextualización del Proyecto

Project: Tiro-Arco
Status: New
Start date: 09/15/2025
Due date: 09/15/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4789: Etapa l Planificación y Aná... Feature #4789: Etapa l Planificación y Análisis del Proyecto

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/15/2025
Due date: 10/26/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4790: Lluvia de ideas y selección... Feature #4790: Lluvia de ideas y selección del proyecto

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/15/2025
Due date: 09/19/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4791: Análisis de la problemática Feature #4791: Análisis de la problemática

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/15/2025
Due date: 09/19/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4792: Definición de objetivos y r... Feature #4792: Definición de objetivos y roles

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/15/2025
Due date: 09/26/2025
Assignee:
Priority: Normal

16

Grupo 6B 2025 - Feature #5567: Capacitacion Meta Quest Feature #5567: Capacitacion Meta Quest

Project: Grupo 6B 2025
Status: New
Start date: 09/16/2025
Due date: 09/16/2025
Assignee:
Priority: Normal
Grupo 6B 2025 - Feature #5568: Modelado Maqueta 3D Feature #5568: Modelado Maqueta 3D

Project: Grupo 6B 2025
Status: New
Start date: 09/16/2025
Due date: 10/14/2025
Assignee:
Priority: Normal
Tiro-Arco - Support #5011: Desarrollo de Requerimientos Support #5011: Desarrollo de Requerimientos

Project: Tiro-Arco
Status: New
Start date: 09/16/2025
Due date: 09/19/2025
Assignee:
Priority: Normal

17

Grupo 5A 2025 - Feature #4814: Investigación Previa Feature #4814: Investigación Previa

Project: Grupo 5A 2025
Status: New
Start date: 09/17/2025
Due date: 09/23/2025
Assignee:
Priority: Normal

18

19

Grupo 1A 2025 - Feature #4790: Lluvia de ideas y selección... Feature #4790: Lluvia de ideas y selección del proyecto

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/15/2025
Due date: 09/19/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4791: Análisis de la problemática Feature #4791: Análisis de la problemática

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/15/2025
Due date: 09/19/2025
Assignee:
Priority: Normal
Cibersegurity - Feature #5445: Análisis del proyecto Feature #5445: Análisis del proyecto

Project: Cibersegurity
Status: New
Start date: 09/10/2025
Due date: 09/19/2025
Assignee:
Priority: Normal
Tiro-Arco - Support #5011: Desarrollo de Requerimientos Support #5011: Desarrollo de Requerimientos

Project: Tiro-Arco
Status: New
Start date: 09/16/2025
Due date: 09/19/2025
Assignee:
Priority: Normal

20

Grupo 5B 2025 - Feature #5486: Investigacion Feature #5486: Investigacion

Project: Grupo 5B 2025
Status: New
Start date: 09/20/2025
Due date: 09/27/2025
Assignee:
Priority: High
39

21

22

GRUPO 5 - Feature #5175: Asignación de roles Feature #5175: Asignación de roles

Project: GRUPO 5
Status: Resolved
Start date: 09/22/2025
Due date: 09/22/2025
Assignee:
Priority: High
Grupo 4B 2025 - Feature #4857: Establecer alcance del proy... Feature #4857: Establecer alcance del proyecto

Project: Grupo 4B 2025
Status: New
Start date: 09/22/2025
Due date: 09/24/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4793: Diseño y modelado 3D en Unity Feature #4793: Diseño y modelado 3D en Unity

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/22/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4794: Creación de la maqueta 3D. Feature #4794: Creación de la maqueta 3D.

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/22/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4795: Pruebas con lentes Meta Que... Feature #4795: Pruebas con lentes Meta Quest 3

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
Ventanilla Única - Feature #5456: Definir problema y solución... Feature #5456: Definir problema y solución en base al proyecto presentado

Project: Ventanilla Única
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee: Eduardo Apata Tito
Priority: Normal
Recintos Deportivos - Feature #4880: Documento De requisito Feature #4880: Documento De requisito

Project: Recintos Deportivos
Status: Resolved
Start date: 09/22/2025
Due date: 10/06/2025
Assignee:
Priority: Normal
Lukia-APR - Feature #5515: Fase I Feature #5515: Fase I

Project: Lukia-APR
Status: New
Start date: 09/22/2025
Due date: 10/20/2025
Assignee:
Priority: High
Lukia-APR - Feature #5519: Requerimientos Feature #5519: Requerimientos

Project: Lukia-APR
Status: New
Start date: 09/22/2025
Due date: 10/08/2025
Assignee:
Priority: Normal
Cibersegurity - Feature #5446: Tabla de requerimientos Feature #5446: Tabla de requerimientos

Project: Cibersegurity
Status: New
Start date: 09/22/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 1 - Feature #4850: Fase 1 Feature #4850: Fase 1

Project: GRUPO 1
Status: New
Start date: 09/22/2025
Due date: 11/10/2025
Assignee: Bastian Hernandez
Priority: High
GRUPO 1 - Feature #5111: Asignación de roles Feature #5111: Asignación de roles

Project: GRUPO 1
Status: New
Start date: 09/22/2025
Due date: 09/24/2025
Assignee: Bastian Hernandez
Priority: High
GRUPO 2 - Feature #4870: Investigar opciones de codi... Feature #4870: Investigar opciones de codigo del software spike

Project: GRUPO 2
Status: New
Start date: 09/22/2025
Due date: 09/24/2025
Assignee:
Priority: Normal
GRUPO 2 - Feature #4872: contruir un prototipo inicial Feature #4872: contruir un prototipo inicial

Project: GRUPO 2
Status: New
Start date: 09/22/2025
Due date: 09/24/2025
Assignee:
Priority: Normal
GRUPO 3 - Feature #5644: Bitácoras Feature #5644: Bitácoras

Project: GRUPO 3
Status: New
Start date: 09/22/2025
Due date: 12/12/2025
Assignee:
Priority: Normal
GRUPO 3 - Feature #5645: Bitacora semana 1 Feature #5645: Bitacora semana 1

Project: GRUPO 3
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5174: I. INICIO Y PLANIFICACIÓN Feature #5174: I. INICIO Y PLANIFICACIÓN

Project: GRUPO 9
Status: New
Start date: 09/22/2025
Due date: 11/10/2025
Assignee: Eduardo Suaña
Priority: Normal
GRUPO 9 - Feature #5176: Formar el equipo de trabajo Feature #5176: Formar el equipo de trabajo

Project: GRUPO 9
Status: New
Start date: 09/22/2025
Due date: 11/10/2025
Assignee: Eduardo Suaña
Priority: Normal
GRUPO 9 - Feature #5181: Analizar la problemática Feature #5181: Analizar la problemática

Project: GRUPO 9
Status: New
Start date: 09/22/2025
Due date: 09/23/2025
Assignee: Benjamin Sucso
Priority: Normal
GRUPO 4 - Feature #4890: Fase 1 Feature #4890: Fase 1

Project: GRUPO 4
Status: New
Start date: 09/22/2025
Due date: 10/31/2025
Assignee: Guillermo Contreras
Priority: Urgent
GRUPO 4 - Feature #4891: Construcción del Robot Feature #4891: Construcción del Robot

Project: GRUPO 4
Status: New
Start date: 09/22/2025
Due date: 10/03/2025
Assignee: Daniel Flores
Priority: High
GRUPO 4 - Feature #4892: Documentacion Feature #4892: Documentacion

Project: GRUPO 4
Status: New
Start date: 09/22/2025
Due date: 10/31/2025
Assignee: Guillermo Contreras
Priority: Urgent
GRUPO 4 - Feature #4959: Informe Feature #4959: Informe

Project: GRUPO 4
Status: New
Start date: 09/22/2025
Due date: 10/31/2025
Assignee: Jhilmar Solares
Priority: Urgent
GRUPO 4 - Feature #4961: Bitácoras Feature #4961: Bitácoras

Project: GRUPO 4
Status: New
Start date: 09/22/2025
Due date: 10/31/2025
Assignee: Guillermo Contreras
Priority: Low
GRUPO 4 - Feature #4965: Prototipo del robot Feature #4965: Prototipo del robot

Project: GRUPO 4
Status: New
Start date: 09/22/2025
Due date: 09/26/2025
Assignee: Daniel Flores
Priority: High
GRUPO 5 - Feature #4903: Investigación Feature #4903: Investigación

Project: GRUPO 5
Status: Resolved
Start date: 09/22/2025
Due date: 09/27/2025
Assignee:
Priority: High
GRUPO 5 - Feature #5130: Análisis de modelos previos... Feature #5130: Análisis de modelos previos del Brazo Robótico

Project: GRUPO 5
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee:
Priority: High
GRUPO 5 - Feature #5169: Fase 1 Feature #5169: Fase 1

Project: GRUPO 5
Status: In Progress
Start date: 09/22/2025
Due date: 10/24/2025
Assignee:
Priority: High
GRUPO 6 - Feature #4896: Administrar el grupo Feature #4896: Administrar el grupo

Project: GRUPO 6
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee: Cristofer Lazaro
Priority: Normal
GRUPO 6 - Feature #4897: Definición del contrato de ... Feature #4897: Definición del contrato de trabajo

Project: GRUPO 6
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee: Cristofer Lazaro
Priority: Normal
EPA-2025 - Feature #5419: Diseño de Interfaces de Usu... Feature #5419: Diseño de Interfaces de Usuario (Mockups)

Project: EPA-2025
Status: New
Start date: 09/22/2025
Due date: 10/17/2025
Assignee:
Priority: Normal
Tiro-Arco - Support #5012: Desarrollo de Mockups Support #5012: Desarrollo de Mockups

Project: Tiro-Arco
Status: New
Start date: 09/22/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
Tiro-Arco - Support #5016: Desarrollo Carta Gantt Support #5016: Desarrollo Carta Gantt

Project: Tiro-Arco
Status: New
Start date: 09/22/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
Ventanilla Única - Support #5469: Primer Avance - Análisis In... Support #5469: Primer Avance - Análisis Inicial del proyecto

Project: Ventanilla Única
Status: New
Start date: 09/22/2025
Due date: 10/24/2025
Assignee:
Priority: Normal

23

Grupo 2A 2025 - Feature #4803: Búsqueda de información com... Feature #4803: Búsqueda de información complementaria

Project: Grupo 2A 2025
Status: Resolved
Start date: 09/10/2025
Due date: 09/23/2025
Assignee:
Priority: Normal
Grupo 5A 2025 - Feature #4814: Investigación Previa Feature #4814: Investigación Previa

Project: Grupo 5A 2025
Status: New
Start date: 09/17/2025
Due date: 09/23/2025
Assignee:
Priority: Normal
Grupo 6A 2025 - Feature #5865: Lluvia de ideas para escoge... Feature #5865: Lluvia de ideas para escoger una problematica

Project: Grupo 6A 2025
Status: Resolved
Start date: 09/23/2025
Due date: 09/23/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5181: Analizar la problemática Feature #5181: Analizar la problemática

Project: GRUPO 9
Status: New
Start date: 09/22/2025
Due date: 09/23/2025
Assignee: Benjamin Sucso
Priority: Normal
Grupo 3A 2025 - Feature #4784: Fase 1 Feature #4784: Fase 1

Project: Grupo 3A 2025
Status: New
Start date: 09/23/2025
Due date: 10/29/2025
Assignee: Guillermo Pino
Priority: High
Grupo 3A 2025 - Feature #5617: Caso del proyecto Feature #5617: Caso del proyecto

Project: Grupo 3A 2025
Status: New
Start date: 09/23/2025
Due date: 09/24/2025
Assignee: giorgio rojas
Priority: High
Grupo 6A 2025 - Feature #4820: Fase 1 Feature #4820: Fase 1

Project: Grupo 6A 2025
Status: Resolved
Start date: 09/23/2025
Due date: 10/15/2025
Assignee:
Priority: Normal
Grupo 6A 2025 - Feature #4821: Bitácoras Feature #4821: Bitácoras

Project: Grupo 6A 2025
Status: Resolved
Start date: 09/23/2025
Due date: 10/14/2025
Assignee: bastian cruz
Priority: Normal
Grupo 6A 2025 - Feature #5799: Propuesta de proyecto Feature #5799: Propuesta de proyecto

Project: Grupo 6A 2025
Status: Resolved
Start date: 09/23/2025
Due date: 09/24/2025
Assignee:
Priority: Normal
Grupo 6A 2025 - Feature #5801: Informe 1 Feature #5801: Informe 1

Project: Grupo 6A 2025
Status: Resolved
Start date: 09/23/2025
Due date: 10/14/2025
Assignee:
Priority: Normal

24

Grupo 4B 2025 - Feature #4857: Establecer alcance del proy... Feature #4857: Establecer alcance del proyecto

Project: Grupo 4B 2025
Status: New
Start date: 09/22/2025
Due date: 09/24/2025
Assignee:
Priority: Normal
Grupo 3A 2025 - Feature #5617: Caso del proyecto Feature #5617: Caso del proyecto

Project: Grupo 3A 2025
Status: New
Start date: 09/23/2025
Due date: 09/24/2025
Assignee: giorgio rojas
Priority: High
Grupo 6A 2025 - Feature #5799: Propuesta de proyecto Feature #5799: Propuesta de proyecto

Project: Grupo 6A 2025
Status: Resolved
Start date: 09/23/2025
Due date: 09/24/2025
Assignee:
Priority: Normal
Grupo 6A 2025 - Feature #5866: Busqueda de una solución Feature #5866: Busqueda de una solución

Project: Grupo 6A 2025
Status: Resolved
Start date: 09/24/2025
Due date: 09/24/2025
Assignee:
Priority: Normal
GRUPO 1 - Feature #5111: Asignación de roles Feature #5111: Asignación de roles

Project: GRUPO 1
Status: New
Start date: 09/22/2025
Due date: 09/24/2025
Assignee: Bastian Hernandez
Priority: High
GRUPO 2 - Feature #4870: Investigar opciones de codi... Feature #4870: Investigar opciones de codigo del software spike

Project: GRUPO 2
Status: New
Start date: 09/22/2025
Due date: 09/24/2025
Assignee:
Priority: Normal
GRUPO 2 - Feature #4872: contruir un prototipo inicial Feature #4872: contruir un prototipo inicial

Project: GRUPO 2
Status: New
Start date: 09/22/2025
Due date: 09/24/2025
Assignee:
Priority: Normal
Grupo 4B 2025 - Feature #4856: Bosquejo de Maqueta Feature #4856: Bosquejo de Maqueta

Project: Grupo 4B 2025
Status: New
Start date: 09/24/2025
Due date: 09/28/2025
Assignee:
Priority: Normal
Grupo 3A 2025 - Feature #4785: Maqueta Feature #4785: Maqueta

Project: Grupo 3A 2025
Status: New
Start date: 09/24/2025
Due date: 10/07/2025
Assignee: Iván Collao
Priority: Normal
Grupo 5A 2025 - Feature #4815: Elaboración Boceto Maqueta Feature #4815: Elaboración Boceto Maqueta

Project: Grupo 5A 2025
Status: New
Start date: 09/24/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
Grupo 5A 2025 - Feature #4817: Confección de la Maqueta VR Feature #4817: Confección de la Maqueta VR

Project: Grupo 5A 2025
Status: New
Start date: 09/24/2025
Due date: 10/06/2025
Assignee:
Priority: Normal
GRUPO 1 - Feature #4960: Pre-codificacion Feature #4960: Pre-codificacion

Project: GRUPO 1
Status: Resolved
Start date: 09/24/2025
Due date: 10/03/2025
Assignee: Saoud Ahmed
Priority: Normal
GRUPO 1 - Feature #5043: Codificación Feature #5043: Codificación

Project: GRUPO 1
Status: New
Start date: 09/24/2025
Due date: 11/10/2025
Assignee: Marcos Caldas
Priority: Normal

25

Recintos Deportivos - Feature #5559: Reunion 1 Feature #5559: Reunion 1

Project: Recintos Deportivos
Status: Resolved
Start date: 09/25/2025
Due date: 09/25/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5192: Diseñar el robot Feature #5192: Diseñar el robot

Project: GRUPO 9
Status: New
Start date: 09/25/2025
Due date: 09/25/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5195: Profundizar en el funcionam... Feature #5195: Profundizar en el funcionamiento del Set

Project: GRUPO 9
Status: New
Start date: 09/25/2025
Due date: 09/25/2025
Assignee: Matias Agriano
Priority: Normal
GRUPO 10 - Feature #4948: Eleccion diseño del robot Feature #4948: Eleccion diseño del robot

Project: GRUPO 10
Status: New
Start date: 09/12/2025
Due date: 09/25/2025
Assignee:
Priority: Normal
Grupo 1B 2025 - Feature #5491: Creación del boceto del pro... Feature #5491: Creación del boceto del proyecto

Project: Grupo 1B 2025
Status: New
Start date: 09/25/2025
Due date: 09/30/2025
Assignee:
Priority: Normal
Recintos Deportivos - Feature #5558: Reuniones Feature #5558: Reuniones

Project: Recintos Deportivos
Status: New
Start date: 09/25/2025
Due date: 11/18/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5185: Redactar el informe inicial Feature #5185: Redactar el informe inicial

Project: GRUPO 9
Status: New
Start date: 09/25/2025
Due date: 10/17/2025
Assignee: Matias Agriano
Priority: Normal
GRUPO 9 - Feature #5189: Elaborar la bitácoras seman... Feature #5189: Elaborar la bitácoras semanales (Continua)

Project: GRUPO 9
Status: New
Start date: 09/25/2025
Due date: 12/12/2025
Assignee: Dylan Calderon
Priority: Normal
GRUPO 9 - Feature #5191: II. DISEÑO Y CONSTRUCCIÓN Feature #5191: II. DISEÑO Y CONSTRUCCIÓN

Project: GRUPO 9
Status: New
Start date: 09/25/2025
Due date: 10/16/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5203: IV. DOCUMENTACIÓN Y CIERRE Feature #5203: IV. DOCUMENTACIÓN Y CIERRE

Project: GRUPO 9
Status: New
Start date: 09/25/2025
Due date: 12/19/2025
Assignee: Dylan Calderon
Priority: Normal
GRUPO 10 - Feature #4949: Construccion del robot Feature #4949: Construccion del robot

Project: GRUPO 10
Status: New
Start date: 09/25/2025
Due date: 10/02/2025
Assignee:
Priority: Normal
GRUPO 10 - Feature #4950: Exploracion de bibliotecas ... Feature #4950: Exploracion de bibliotecas de Python para el control del robot

Project: GRUPO 10
Status: New
Start date: 09/25/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
GRUPO 10 - Feature #4957: Conteo de set LEGO spike Pr... Feature #4957: Conteo de set LEGO spike Prime.

Project: GRUPO 10
Status: New
Start date: 09/25/2025
Due date: 10/03/2025
Assignee:
Priority: Normal

26

Grupo 1A 2025 - Feature #4792: Definición de objetivos y r... Feature #4792: Definición de objetivos y roles

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/15/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4795: Pruebas con lentes Meta Que... Feature #4795: Pruebas con lentes Meta Quest 3

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
Grupo 5A 2025 - Feature #4815: Elaboración Boceto Maqueta Feature #4815: Elaboración Boceto Maqueta

Project: Grupo 5A 2025
Status: New
Start date: 09/24/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
Ventanilla Única - Feature #5456: Definir problema y solución... Feature #5456: Definir problema y solución en base al proyecto presentado

Project: Ventanilla Única
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee: Eduardo Apata Tito
Priority: Normal
GRUPO 3 - Feature #5645: Bitacora semana 1 Feature #5645: Bitacora semana 1

Project: GRUPO 3
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
GRUPO 10 - Feature #4950: Exploracion de bibliotecas ... Feature #4950: Exploracion de bibliotecas de Python para el control del robot

Project: GRUPO 10
Status: New
Start date: 09/25/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
GRUPO 10 - Feature #4951: BItacora semana 1 Feature #4951: BItacora semana 1

Project: GRUPO 10
Status: New
Start date: 09/26/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
GRUPO 4 - Feature #4965: Prototipo del robot Feature #4965: Prototipo del robot

Project: GRUPO 4
Status: New
Start date: 09/22/2025
Due date: 09/26/2025
Assignee: Daniel Flores
Priority: High
GRUPO 5 - Feature #5130: Análisis de modelos previos... Feature #5130: Análisis de modelos previos del Brazo Robótico

Project: GRUPO 5
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee:
Priority: High
GRUPO 5 - Feature #5131: Verificación de compatibili... Feature #5131: Verificación de compatibilidad de piezas

Project: GRUPO 5
Status: Resolved
Start date: 09/26/2025
Due date: 09/26/2025
Assignee:
Priority: High
GRUPO 6 - Feature #4863: Plantear el objetivo general Feature #4863: Plantear el objetivo general

Project: GRUPO 6
Status: Resolved
Start date: 09/26/2025
Due date: 09/26/2025
Assignee: Abraham Canaviri
Priority: Normal
GRUPO 6 - Feature #4896: Administrar el grupo Feature #4896: Administrar el grupo

Project: GRUPO 6
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee: Cristofer Lazaro
Priority: Normal
GRUPO 6 - Feature #4897: Definición del contrato de ... Feature #4897: Definición del contrato de trabajo

Project: GRUPO 6
Status: Resolved
Start date: 09/22/2025
Due date: 09/26/2025
Assignee: Cristofer Lazaro
Priority: Normal
GRUPO 6 - Feature #4898: Inventario Feature #4898: Inventario

Project: GRUPO 6
Status: Resolved
Start date: 09/26/2025
Due date: 09/26/2025
Assignee: Cristofer Lazaro
Priority: Normal
GRUPO 6 - Feature #4899: Cuantificación de las piezas Feature #4899: Cuantificación de las piezas

Project: GRUPO 6
Status: Resolved
Start date: 09/26/2025
Due date: 09/26/2025
Assignee: Cristofer Lazaro
Priority: Normal
GRUPO 6 - Feature #4901: Completar bitácora N° 1 Feature #4901: Completar bitácora N° 1

Project: GRUPO 6
Status: Resolved
Start date: 09/26/2025
Due date: 09/26/2025
Assignee: Ruth Huanca
Priority: Normal
Tiro-Arco - Support #5012: Desarrollo de Mockups Support #5012: Desarrollo de Mockups

Project: Tiro-Arco
Status: New
Start date: 09/22/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
Tiro-Arco - Support #5016: Desarrollo Carta Gantt Support #5016: Desarrollo Carta Gantt

Project: Tiro-Arco
Status: New
Start date: 09/22/2025
Due date: 09/26/2025
Assignee:
Priority: Normal
Recintos Deportivos - Feature #5075: Desarrollo Carta Gantt Feature #5075: Desarrollo Carta Gantt

Project: Recintos Deportivos
Status: New
Start date: 09/26/2025
Due date: 12/26/2025
Assignee:
Priority: High
GRUPO 1 - Feature #4963: Primer ensamblaje del robot... Feature #4963: Primer ensamblaje del robot prototipo

Project: GRUPO 1
Status: Resolved
Start date: 09/26/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
GRUPO 1 - Feature #4968: Ensamblaje Feature #4968: Ensamblaje

Project: GRUPO 1
Status: New
Start date: 09/26/2025
Due date: 10/31/2025
Assignee: Enzo Llancabure
Priority: High
GRUPO 1 - Feature #5129: Estudio de diferentes robot... Feature #5129: Estudio de diferentes robots en la web.

Project: GRUPO 1
Status: New
Start date: 09/26/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
GRUPO 8 - Feature #4834: Preparación para el proyecto Feature #4834: Preparación para el proyecto

Project: GRUPO 8
Status: New
Start date: 09/26/2025
Due date: 10/03/2025
Assignee: Gabriel Delgado
Priority: Normal
GRUPO 8 - Feature #4909: Ordenamiento de los cables ... Feature #4909: Ordenamiento de los cables para el funcionamiento correcto del robot

Project: GRUPO 8
Status: New
Start date: 09/26/2025
Due date: 10/10/2025
Assignee: Gabriel Delgado
Priority: Normal
GRUPO 8 - Feature #5019: Asignacion de cargos Feature #5019: Asignacion de cargos

Project: GRUPO 8
Status: New
Start date: 09/26/2025
Due date: 09/29/2025
Assignee: Victor Breems
Priority: High
GRUPO 9 - Feature #5184: Redactar la Carta Gantt Feature #5184: Redactar la Carta Gantt

Project: GRUPO 9
Status: New
Start date: 09/26/2025
Due date: 10/17/2025
Assignee: Eduardo Suaña
Priority: Normal
GRUPO 5 - Feature #5133: Registro de bitácoras Feature #5133: Registro de bitácoras

Project: GRUPO 5
Status: Resolved
Start date: 09/26/2025
Due date: 10/24/2025
Assignee:
Priority: High
GRUPO 5 - Feature #5198: Documentación Feature #5198: Documentación

Project: GRUPO 5
Status: Resolved
Start date: 09/26/2025
Due date: 10/24/2025
Assignee:
Priority: High
GRUPO 5 - Feature #5222: Avance del Informe Feature #5222: Avance del Informe

Project: GRUPO 5
Status: Resolved
Start date: 09/26/2025
Due date: 10/09/2025
Assignee: Franco Churata
Priority: Normal
GRUPO 5 - Feature #5227: Informe 1 Feature #5227: Informe 1

Project: GRUPO 5
Status: Resolved
Start date: 09/26/2025
Due date: 10/17/2025
Assignee:
Priority: High
GRUPO 5 - Feature #5237: Elección del Modelo Final Feature #5237: Elección del Modelo Final

Project: GRUPO 5
Status: Resolved
Start date: 09/26/2025
Due date: 09/27/2025
Assignee:
Priority: Normal
GRUPO 6 - Feature #4862: Definir objetivos Feature #4862: Definir objetivos

Project: GRUPO 6
Status: Resolved
Start date: 09/26/2025
Due date: 10/03/2025
Assignee: Abraham Canaviri
Priority: Normal
GRUPO 6 - Feature #4900: Completar bitácora Feature #4900: Completar bitácora

Project: GRUPO 6
Status: In Progress
Start date: 09/26/2025
Due date: 12/12/2025
Assignee: Ruth Huanca
Priority: Normal
GRUPO 11 - Feature #5149: Prototipo del robot Feature #5149: Prototipo del robot

Project: GRUPO 11
Status: Resolved
Start date: 09/26/2025
Due date: 10/12/2025
Assignee: José Terrazas
Priority: High
GRUPO 11 - Feature #5150: Investigación y familiariza... Feature #5150: Investigación y familiarización con el Kit de LEGO

Project: GRUPO 11
Status: Resolved
Start date: 09/26/2025
Due date: 10/03/2025
Assignee: José Terrazas
Priority: High
GRUPO 11 - Feature #5154: Software Feature #5154: Software

Project: GRUPO 11
Status: Resolved
Start date: 09/26/2025
Due date: 10/20/2025
Assignee: Javier Echeverria
Priority: High
GRUPO 11 - Feature #5156: Investigación bibliotecas Feature #5156: Investigación bibliotecas

Project: GRUPO 11
Status: Resolved
Start date: 09/26/2025
Due date: 10/01/2025
Assignee: Javier Echeverria
Priority: High

27

Grupo 5B 2025 - Feature #5486: Investigacion Feature #5486: Investigacion

Project: Grupo 5B 2025
Status: New
Start date: 09/20/2025
Due date: 09/27/2025
Assignee:
Priority: High
GRUPO 5 - Feature #4903: Investigación Feature #4903: Investigación

Project: GRUPO 5
Status: Resolved
Start date: 09/22/2025
Due date: 09/27/2025
Assignee:
Priority: High
GRUPO 5 - Feature #5237: Elección del Modelo Final Feature #5237: Elección del Modelo Final

Project: GRUPO 5
Status: Resolved
Start date: 09/26/2025
Due date: 09/27/2025
Assignee:
Priority: Normal
GRUPO 3 - Feature #5941: Introducir y Explorar en el... Feature #5941: Introducir y Explorar en el set de LEGO Spike Prime

Project: GRUPO 3
Status: New
Start date: 09/27/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
GRUPO 8 - Feature #5047: Prototipo del robot Feature #5047: Prototipo del robot

Project: GRUPO 8
Status: New
Start date: 09/27/2025
Due date: 10/03/2025
Assignee: Gabriel Delgado
Priority: High
40

28

Grupo 4B 2025 - Feature #4856: Bosquejo de Maqueta Feature #4856: Bosquejo de Maqueta

Project: Grupo 4B 2025
Status: New
Start date: 09/24/2025
Due date: 09/28/2025
Assignee:
Priority: Normal
Grupo 5B 2025 - Feature #5487: Justificación y desarrollo ... Feature #5487: Justificación y desarrollo del diseño

Project: Grupo 5B 2025
Status: New
Start date: 09/28/2025
Due date: 10/04/2025
Assignee:
Priority: High

29

GRUPO 8 - Feature #5019: Asignacion de cargos Feature #5019: Asignacion de cargos

Project: GRUPO 8
Status: New
Start date: 09/26/2025
Due date: 09/29/2025
Assignee: Victor Breems
Priority: High
Proyecto IV 2025 - Bug #5287: Fase 1: Planificación y Def... Bug #5287: Fase 1: Planificación y Definición

Project: Proyecto IV 2025
Status: New
Start date: 09/29/2025
Due date: 10/20/2025
Assignee:
Priority: Normal
Grupo 4B 2025 - Feature #4858: Estudio de Software a utilizar Feature #4858: Estudio de Software a utilizar

Project: Grupo 4B 2025
Status: New
Start date: 09/29/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
Grupo 4A 2025 - Feature #5496: Maqueta Feature #5496: Maqueta

Project: Grupo 4A 2025
Status: Resolved
Start date: 09/29/2025
Due date: 10/15/2025
Assignee: yazuska castillo
Priority: High
Grupo 4A 2025 - Feature #5503: Unity Feature #5503: Unity

Project: Grupo 4A 2025
Status: Resolved
Start date: 09/29/2025
Due date: 10/15/2025
Assignee: yazuska castillo
Priority: High
FOUCH-Investigación - Feature #5292: Fase 1: Planificación y Def... Feature #5292: Fase 1: Planificación y Definición

Project: FOUCH-Investigación
Status: New
Start date: 09/29/2025
Due date: 10/20/2025
Assignee:
Priority: Normal
FOUCH-Investigación - Feature #5294: Definición de proyecto (pro... Feature #5294: Definición de proyecto (problema, alcance y objetivos)

Project: FOUCH-Investigación
Status: New
Start date: 09/29/2025
Due date: 10/06/2025
Assignee:
Priority: Normal
Ventanilla Única - Feature #5459: Establecer la reunion con e... Feature #5459: Establecer la reunion con el cliente para definir los requerimientos del proyecto

Project: Ventanilla Única
Status: New
Start date: 09/29/2025
Due date: 10/23/2025
Assignee: Eduardo Apata Tito
Priority: Normal
Ventanilla Única - Feature #5462: Revisar el documentado firm... Feature #5462: Revisar el documentado firmado por el cliente

Project: Ventanilla Única
Status: Resolved
Start date: 09/29/2025
Due date: 10/07/2025
Assignee: Eduardo Apata Tito
Priority: Normal
Ventanilla Única - Feature #5464: Definir los requisitos del ... Feature #5464: Definir los requisitos del sistema del proyecto

Project: Ventanilla Única
Status: Resolved
Start date: 09/29/2025
Due date: 10/23/2025
Assignee: Eduardo Apata Tito
Priority: Normal
Ventanilla Única - Feature #5465: Documentar los requisitos d... Feature #5465: Documentar los requisitos del sistema y presentarla al profesor y cliente

Project: Ventanilla Única
Status: New
Start date: 09/29/2025
Due date: 10/23/2025
Assignee: Fabian Flores
Priority: Normal
Lukia-APR - Feature #5528: Bitacoras Fase I Feature #5528: Bitacoras Fase I

Project: Lukia-APR
Status: New
Start date: 09/29/2025
Due date: 10/20/2025
Assignee:
Priority: Normal
Lukia-APR - Feature #5529: Bitacora I Feature #5529: Bitacora I

Project: Lukia-APR
Status: New
Start date: 09/29/2025
Due date: 10/06/2025
Assignee:
Priority: Normal
GRUPO 1 - Feature #5114: Pruebas de codigo. Feature #5114: Pruebas de codigo.

Project: GRUPO 1
Status: New
Start date: 09/29/2025
Due date: 10/17/2025
Assignee: Saoud Ahmed
Priority: Normal
GRUPO 3 - Feature #4974: Ensamble de Prototipo Feature #4974: Ensamble de Prototipo

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 11/14/2025
Assignee:
Priority: High
GRUPO 3 - Feature #5439: Ensamble de Receptores de b... Feature #5439: Ensamble de Receptores de bloques.

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/01/2025
Assignee: Camilo Geraldo
Priority: Normal
GRUPO 3 - Feature #5440: Ensamble del motor del prot... Feature #5440: Ensamble del motor del prototipo.

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/01/2025
Assignee: Ignacio Cuevas
Priority: Normal
GRUPO 3 - Feature #5442: Ensamble y Modificación de ... Feature #5442: Ensamble y Modificación de Brazos Giratorios.

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/01/2025
Assignee: Maximiliano Burgos
Priority: Normal
GRUPO 3 - Feature #5443: Modificación y Ensamble de ... Feature #5443: Modificación y Ensamble de pistón giratorio.

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/03/2025
Assignee: Jose Quispe
Priority: Normal
GRUPO 3 - Feature #5646: Bitácora semana 2 Feature #5646: Bitácora semana 2

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 3 - Feature #5942: Planificar primer diseño ba... Feature #5942: Planificar primer diseño base del robot

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 4 - Feature #4966: Construcción versión 1 Feature #4966: Construcción versión 1

Project: GRUPO 4
Status: New
Start date: 09/29/2025
Due date: 10/03/2025
Assignee: Daniel Flores
Priority: High
GRUPO 5 - Feature #5136: Montaje de la base estructu... Feature #5136: Montaje de la base estructural

Project: GRUPO 5
Status: Resolved
Start date: 09/29/2025
Due date: 10/01/2025
Assignee: Franco Churata
Priority: Normal
GRUPO 5 - Feature #5204: Ensamblaje Feature #5204: Ensamblaje

Project: GRUPO 5
Status: Resolved
Start date: 09/29/2025
Due date: 10/06/2025
Assignee: Brayan Palacios
Priority: Normal
GRUPO 5 - Feature #5238: Montaje del brazo Feature #5238: Montaje del brazo

Project: GRUPO 5
Status: Resolved
Start date: 09/29/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
GRUPO 6 - Feature #4902: Construcción del robot Feature #4902: Construcción del robot

Project: GRUPO 6
Status: Resolved
Start date: 09/29/2025
Due date: 10/17/2025
Assignee: Cristofer Lazaro
Priority: Normal
GRUPO 6 - Feature #4904: Prueba de diseño del robot Feature #4904: Prueba de diseño del robot

Project: GRUPO 6
Status: Resolved
Start date: 09/29/2025
Due date: 10/03/2025
Assignee: Cristofer Lazaro
Priority: Normal
GRUPO 6 - Feature #5036: Completar bitácora N° 2 Feature #5036: Completar bitácora N° 2

Project: GRUPO 6
Status: Resolved
Start date: 09/29/2025
Due date: 10/03/2025
Assignee: Ruth Huanca
Priority: Normal
Tiro-Arco - Support #5013: Firma y Conformidad de Requ... Support #5013: Firma y Conformidad de Requerimientos

Project: Tiro-Arco
Status: New
Start date: 09/29/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
Cibersegurity - Support #4877: Instalación de Sistema Oper... Support #4877: Instalación de Sistema Operativo

Project: Cibersegurity
Status: New
Start date: 09/29/2025
Due date: 10/03/2025
Assignee:
Priority: Urgent

30

Grupo 1B 2025 - Feature #5491: Creación del boceto del pro... Feature #5491: Creación del boceto del proyecto

Project: Grupo 1B 2025
Status: New
Start date: 09/25/2025
Due date: 09/30/2025
Assignee:
Priority: Normal
Grupo 2B-2025 - Bug #4983: Problema de rendimiento con... Bug #4983: Problema de rendimiento con el modelado

Project: Grupo 2B-2025
Status: New
Start date: 09/30/2025
Due date: 10/14/2025
Assignee: bairon núñez
Priority: Normal
Grupo 2A 2025 - Feature #5502: Modelo 3D(Unity) Feature #5502: Modelo 3D(Unity)

Project: Grupo 2A 2025
Status: Resolved
Start date: 09/30/2025
Due date: 10/07/2025
Assignee:
Priority: Normal

1

Grupo 4B 2025 - Feature #4858: Estudio de Software a utilizar Feature #4858: Estudio de Software a utilizar

Project: Grupo 4B 2025
Status: New
Start date: 09/29/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4793: Diseño y modelado 3D en Unity Feature #4793: Diseño y modelado 3D en Unity

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/22/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
Grupo 1A 2025 - Feature #4794: Creación de la maqueta 3D. Feature #4794: Creación de la maqueta 3D.

Project: Grupo 1A 2025
Status: Resolved
Start date: 09/22/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
GRUPO 1 - Feature #4963: Primer ensamblaje del robot... Feature #4963: Primer ensamblaje del robot prototipo

Project: GRUPO 1
Status: Resolved
Start date: 09/26/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
GRUPO 1 - Feature #5129: Estudio de diferentes robot... Feature #5129: Estudio de diferentes robots en la web.

Project: GRUPO 1
Status: New
Start date: 09/26/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
GRUPO 3 - Feature #5439: Ensamble de Receptores de b... Feature #5439: Ensamble de Receptores de bloques.

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/01/2025
Assignee: Camilo Geraldo
Priority: Normal
GRUPO 3 - Feature #5440: Ensamble del motor del prot... Feature #5440: Ensamble del motor del prototipo.

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/01/2025
Assignee: Ignacio Cuevas
Priority: Normal
GRUPO 3 - Feature #5442: Ensamble y Modificación de ... Feature #5442: Ensamble y Modificación de Brazos Giratorios.

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/01/2025
Assignee: Maximiliano Burgos
Priority: Normal
GRUPO 3 - Feature #5941: Introducir y Explorar en el... Feature #5941: Introducir y Explorar en el set de LEGO Spike Prime

Project: GRUPO 3
Status: New
Start date: 09/27/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
GRUPO 5 - Feature #5136: Montaje de la base estructu... Feature #5136: Montaje de la base estructural

Project: GRUPO 5
Status: Resolved
Start date: 09/29/2025
Due date: 10/01/2025
Assignee: Franco Churata
Priority: Normal
GRUPO 5 - Feature #5238: Montaje del brazo Feature #5238: Montaje del brazo

Project: GRUPO 5
Status: Resolved
Start date: 09/29/2025
Due date: 10/01/2025
Assignee:
Priority: Normal
GRUPO 11 - Feature #5156: Investigación bibliotecas Feature #5156: Investigación bibliotecas

Project: GRUPO 11
Status: Resolved
Start date: 09/26/2025
Due date: 10/01/2025
Assignee: Javier Echeverria
Priority: High
Grupo 6A 2025 - Feature #5800: Maqueta de la solución prop... Feature #5800: Maqueta de la solución propuesta

Project: Grupo 6A 2025
Status: Resolved
Start date: 10/01/2025
Due date: 10/14/2025
Assignee:
Priority: Normal
Grupo 6A 2025 - Feature #5868: Dibujar boceto de la maqueta Feature #5868: Dibujar boceto de la maqueta

Project: Grupo 6A 2025
Status: Resolved
Start date: 10/01/2025
Due date: 10/07/2025
Assignee:
Priority: Normal
Grupo 6A 2025 - Feature #5869: Investigación sobre Unity Feature #5869: Investigación sobre Unity

Project: Grupo 6A 2025
Status: Resolved
Start date: 10/01/2025
Due date: 10/07/2025
Assignee:
Priority: Normal
GRUPO 1 - Feature #5109: Optimización del Prototipo Feature #5109: Optimización del Prototipo

Project: GRUPO 1
Status: Resolved
Start date: 10/01/2025
Due date: 10/22/2025
Assignee: Alex Campillay
Priority: Normal
GRUPO 1 - Feature #5121: Ensamblaje del 2do Prototipo Feature #5121: Ensamblaje del 2do Prototipo

Project: GRUPO 1
Status: New
Start date: 10/01/2025
Due date: 10/31/2025
Assignee: Alex Campillay
Priority: High
GRUPO 3 - Feature #5004: Ajustes a diseño del protot... Feature #5004: Ajustes a diseño del prototipo.

Project: GRUPO 3
Status: Resolved
Start date: 10/01/2025
Due date: 10/10/2025
Assignee: Maximiliano Burgos
Priority: Normal
GRUPO 5 - Feature #5008: Codificación Feature #5008: Codificación

Project: GRUPO 5
Status: Resolved
Start date: 10/01/2025
Due date: 10/20/2025
Assignee: Joaquin Quezada
Priority: High
GRUPO 5 - Feature #5137: Conexión de cables y compon... Feature #5137: Conexión de cables y componentes eléctricos.

Project: GRUPO 5
Status: Resolved
Start date: 10/01/2025
Due date: 10/02/2025
Assignee:
Priority: Normal
GRUPO 5 - Feature #5141: Familiarización con el Soft... Feature #5141: Familiarización con el Software

Project: GRUPO 5
Status: Resolved
Start date: 10/01/2025
Due date: 10/02/2025
Assignee:
Priority: Normal
GRUPO 6 - Feature #4864: Definir objetivos específicos Feature #4864: Definir objetivos específicos

Project: GRUPO 6
Status: Resolved
Start date: 10/01/2025
Due date: 10/03/2025
Assignee: Cristofer Lazaro
Priority: Normal
GRUPO 11 - Feature #5157: Familiarización con el código Feature #5157: Familiarización con el código

Project: GRUPO 11
Status: Resolved
Start date: 10/01/2025
Due date: 10/05/2025
Assignee: Javier Echeverria
Priority: High

2

GRUPO 7 - Feature #5946: Reunión inicial y definició... Feature #5946: Reunión inicial y definición del proyecto

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date: 10/02/2025
Assignee:
Priority: Normal
GRUPO 7 - Feature #5948: Asignación de roles del equipo Feature #5948: Asignación de roles del equipo

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date: 10/02/2025
Assignee:
Priority: Normal
GRUPO 10 - Feature #4949: Construccion del robot Feature #4949: Construccion del robot

Project: GRUPO 10
Status: New
Start date: 09/25/2025
Due date: 10/02/2025
Assignee:
Priority: Normal
GRUPO 5 - Feature #5137: Conexión de cables y compon... Feature #5137: Conexión de cables y componentes eléctricos.

Project: GRUPO 5
Status: Resolved
Start date: 10/01/2025
Due date: 10/02/2025
Assignee:
Priority: Normal
GRUPO 5 - Feature #5141: Familiarización con el Soft... Feature #5141: Familiarización con el Software

Project: GRUPO 5
Status: Resolved
Start date: 10/01/2025
Due date: 10/02/2025
Assignee:
Priority: Normal
Grupo 1B 2025 - Feature #5492: Desarrollo maqueta virtual Feature #5492: Desarrollo maqueta virtual

Project: Grupo 1B 2025
Status: New
Start date: 10/02/2025
Due date: 10/09/2025
Assignee:
Priority: Normal
Grupo 4B 2025 - Feature #4859: Modelado de maqueta Feature #4859: Modelado de maqueta

Project: Grupo 4B 2025
Status: New
Start date: 10/02/2025
Due date: 10/07/2025
Assignee:
Priority: Normal
Recintos Deportivos - Feature #5097: Seleccion De Herramientas Web Feature #5097: Seleccion De Herramientas Web

Project: Recintos Deportivos
Status: Resolved
Start date: 10/02/2025
Due date: 10/13/2025
Assignee:
Priority: Normal
GRUPO 7 - Feature #5945: FASE 1: PLANIFICACIÓN INICIAL Feature #5945: FASE 1: PLANIFICACIÓN INICIAL

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date: 10/31/2025
Assignee:
Priority: Normal
GRUPO 7 - Feature #5947: Investigación del kit Lego ... Feature #5947: Investigación del kit Lego Spike Prime

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date: 10/31/2025
Assignee:
Priority: Normal
GRUPO 7 - Feature #5950: FASE 3: CONSTRUCCIÓN Feature #5950: FASE 3: CONSTRUCCIÓN

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date: 10/23/2025
Assignee:
Priority: Normal
GRUPO 7 - Feature #5963: FASE 6: DOCUMENTACIÓN Y ENT... Feature #5963: FASE 6: DOCUMENTACIÓN Y ENTREGA

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date:
Assignee:
Priority: Normal
GRUPO 7 - Feature #5964: Desarrollo de bitácoras sem... Feature #5964: Desarrollo de bitácoras semanales

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date:
Assignee:
Priority: Normal
GRUPO 7 - Feature #5969: Construcción de la base del... Feature #5969: Construcción de la base del robot

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 8 - Feature #4835: Primer modelo del robot Feature #4835: Primer modelo del robot

Project: GRUPO 8
Status: New
Start date: 10/02/2025
Due date: 10/03/2025
Assignee: Nicolas Olivares
Priority: Normal
GRUPO 8 - Feature #4838: Avance del primer modelo Feature #4838: Avance del primer modelo

Project: GRUPO 8
Status: New
Start date: 10/02/2025
Due date: 10/03/2025
Assignee: Gabriel Delgado
Priority: Normal
GRUPO 8 - Feature #4846: Término del primer modelo d... Feature #4846: Término del primer modelo del robot

Project: GRUPO 8
Status: New
Start date: 10/02/2025
Due date: 10/03/2025
Assignee: Sebastian Cahuachia
Priority: Normal
GRUPO 9 - Feature #5243: Construir brazo del robot Feature #5243: Construir brazo del robot

Project: GRUPO 9
Status: New
Start date: 10/02/2025
Due date: 10/16/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5244: Construir garra del robot Feature #5244: Construir garra del robot

Project: GRUPO 9
Status: New
Start date: 10/02/2025
Due date: 10/16/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5245: Ensamblar motores y sensore... Feature #5245: Ensamblar motores y sensores en el robot

Project: GRUPO 9
Status: New
Start date: 10/02/2025
Due date: 10/16/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5247: Ensamblar: Estructura Base Feature #5247: Ensamblar: Estructura Base

Project: GRUPO 9
Status: New
Start date: 10/02/2025
Due date: 10/16/2025
Assignee: Benjamin Sucso
Priority: Normal
GRUPO 9 - Feature #5248: Probar giro de 360° Feature #5248: Probar giro de 360°

Project: GRUPO 9
Status: New
Start date: 10/02/2025
Due date: 10/16/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5249: Probar movimiento vertical ... Feature #5249: Probar movimiento vertical del brazo robótico

Project: GRUPO 9
Status: New
Start date: 10/02/2025
Due date: 10/16/2025
Assignee: Matias Agriano
Priority: Normal
GRUPO 9 - Feature #5250: Probar el agarre y liberaci... Feature #5250: Probar el agarre y liberación de la garra

Project: GRUPO 9
Status: New
Start date: 10/02/2025
Due date: 10/16/2025
Assignee:
Priority: Normal
GRUPO 9 - Feature #5251: Redactar el Informe 1 Feature #5251: Redactar el Informe 1

Project: GRUPO 9
Status: New
Start date: 10/02/2025
Due date: 10/17/2025
Assignee: Dylan Calderon
Priority: Normal
GRUPO 10 - Feature #4884: Testeando y creando funcion... Feature #4884: Testeando y creando funciones para el robot

Project: GRUPO 10
Status: New
Start date: 10/02/2025
Due date: 10/09/2025
Assignee:
Priority: High
GRUPO 10 - Feature #4956: Desarrollo en libreria Pybrick Feature #4956: Desarrollo en libreria Pybrick

Project: GRUPO 10
Status: New
Start date: 10/02/2025
Due date: 10/17/2025
Assignee:
Priority: Normal
GRUPO 10 - Feature #4958: Desarrollo de la estructura... Feature #4958: Desarrollo de la estructura funcional y algortimica

Project: GRUPO 10
Status: New
Start date: 10/02/2025
Due date: 10/10/2025
Assignee:
Priority: Normal
GRUPO 5 - Feature #5140: Programación de movimientos... Feature #5140: Programación de movimientos simples con el entorno de LEGO

Project: GRUPO 5
Status: Resolved
Start date: 10/02/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 5 - Feature #5233: Pruebas de agarre con el Robot Feature #5233: Pruebas de agarre con el Robot

Project: GRUPO 5
Status: Resolved
Start date: 10/02/2025
Due date: 10/06/2025
Assignee:
Priority: Normal

3

Lukia-APR - Feature #5517: Reunion I Feature #5517: Reunion I

Project: Lukia-APR
Status: New
Start date: 10/03/2025
Due date: 10/03/2025
Assignee:
Priority: High
Cibersegurity - Feature #5446: Tabla de requerimientos Feature #5446: Tabla de requerimientos

Project: Cibersegurity
Status: New
Start date: 09/22/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 1 - Feature #4960: Pre-codificacion Feature #4960: Pre-codificacion

Project: GRUPO 1
Status: Resolved
Start date: 09/24/2025
Due date: 10/03/2025
Assignee: Saoud Ahmed
Priority: Normal
GRUPO 3 - Feature #5443: Modificación y Ensamble de ... Feature #5443: Modificación y Ensamble de pistón giratorio.

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/03/2025
Assignee: Jose Quispe
Priority: Normal
GRUPO 3 - Feature #5646: Bitácora semana 2 Feature #5646: Bitácora semana 2

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 3 - Feature #5942: Planificar primer diseño ba... Feature #5942: Planificar primer diseño base del robot

Project: GRUPO 3
Status: Resolved
Start date: 09/29/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 7 - Feature #5955: Diseño conceptual del robot Feature #5955: Diseño conceptual del robot

Project: GRUPO 7
Status: New
Start date: 10/03/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 7 - Feature #5969: Construcción de la base del... Feature #5969: Construcción de la base del robot

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 8 - Feature #4834: Preparación para el proyecto Feature #4834: Preparación para el proyecto

Project: GRUPO 8
Status: New
Start date: 09/26/2025
Due date: 10/03/2025
Assignee: Gabriel Delgado
Priority: Normal
GRUPO 8 - Feature #4835: Primer modelo del robot Feature #4835: Primer modelo del robot

Project: GRUPO 8
Status: New
Start date: 10/02/2025
Due date: 10/03/2025
Assignee: Nicolas Olivares
Priority: Normal
GRUPO 8 - Feature #4838: Avance del primer modelo Feature #4838: Avance del primer modelo

Project: GRUPO 8
Status: New
Start date: 10/02/2025
Due date: 10/03/2025
Assignee: Gabriel Delgado
Priority: Normal
GRUPO 8 - Feature #4840: Interfaz del robot Feature #4840: Interfaz del robot

Project: GRUPO 8
Status: New
Start date: 10/03/2025
Due date: 10/03/2025
Assignee: Willy Cruz
Priority: Normal
GRUPO 8 - Feature #4841: Avance Informe Feature #4841: Avance Informe

Project: GRUPO 8
Status: New
Start date: 10/03/2025
Due date: 10/03/2025
Assignee: Nicolas Olivares
Priority: Normal
GRUPO 8 - Feature #4846: Término del primer modelo d... Feature #4846: Término del primer modelo del robot

Project: GRUPO 8
Status: New
Start date: 10/02/2025
Due date: 10/03/2025
Assignee: Sebastian Cahuachia
Priority: Normal
GRUPO 8 - Feature #5047: Prototipo del robot Feature #5047: Prototipo del robot

Project: GRUPO 8
Status: New
Start date: 09/27/2025
Due date: 10/03/2025
Assignee: Gabriel Delgado
Priority: High
GRUPO 10 - Feature #4952: BItacora semana 2 Feature #4952: BItacora semana 2

Project: GRUPO 10
Status: New
Start date: 10/03/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 10 - Feature #4957: Conteo de set LEGO spike Pr... Feature #4957: Conteo de set LEGO spike Prime.

Project: GRUPO 10
Status: New
Start date: 09/25/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 4 - Feature #4891: Construcción del Robot Feature #4891: Construcción del Robot

Project: GRUPO 4
Status: New
Start date: 09/22/2025
Due date: 10/03/2025
Assignee: Daniel Flores
Priority: High
GRUPO 4 - Feature #4966: Construcción versión 1 Feature #4966: Construcción versión 1

Project: GRUPO 4
Status: New
Start date: 09/29/2025
Due date: 10/03/2025
Assignee: Daniel Flores
Priority: High
GRUPO 5 - Feature #5140: Programación de movimientos... Feature #5140: Programación de movimientos simples con el entorno de LEGO

Project: GRUPO 5
Status: Resolved
Start date: 10/02/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
GRUPO 6 - Feature #4862: Definir objetivos Feature #4862: Definir objetivos

Project: GRUPO 6
Status: Resolved
Start date: 09/26/2025
Due date: 10/03/2025
Assignee: Abraham Canaviri
Priority: Normal
GRUPO 6 - Feature #4864: Definir objetivos específicos Feature #4864: Definir objetivos específicos

Project: GRUPO 6
Status: Resolved
Start date: 10/01/2025
Due date: 10/03/2025
Assignee: Cristofer Lazaro
Priority: Normal
GRUPO 6 - Feature #4904: Prueba de diseño del robot Feature #4904: Prueba de diseño del robot

Project: GRUPO 6
Status: Resolved
Start date: 09/29/2025
Due date: 10/03/2025
Assignee: Cristofer Lazaro
Priority: Normal
GRUPO 6 - Feature #5036: Completar bitácora N° 2 Feature #5036: Completar bitácora N° 2

Project: GRUPO 6
Status: Resolved
Start date: 09/29/2025
Due date: 10/03/2025
Assignee: Ruth Huanca
Priority: Normal
GRUPO 11 - Feature #5150: Investigación y familiariza... Feature #5150: Investigación y familiarización con el Kit de LEGO

Project: GRUPO 11
Status: Resolved
Start date: 09/26/2025
Due date: 10/03/2025
Assignee: José Terrazas
Priority: High
EPA-2025 - Feature #5418: Modelado del Sistema Feature #5418: Modelado del Sistema

Project: EPA-2025
Status: New
Start date: 09/08/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
Tiro-Arco - Support #5013: Firma y Conformidad de Requ... Support #5013: Firma y Conformidad de Requerimientos

Project: Tiro-Arco
Status: New
Start date: 09/29/2025
Due date: 10/03/2025
Assignee:
Priority: Normal
Cibersegurity - Support #4877: Instalación de Sistema Oper... Support #4877: Instalación de Sistema Operativo

Project: Cibersegurity
Status: New
Start date: 09/29/2025
Due date: 10/03/2025
Assignee:
Priority: Urgent
Lukia-APR - Feature #5516: Reunion Feature #5516: Reunion

Project: Lukia-APR
Status: New
Start date: 10/03/2025
Due date: 10/09/2025
Assignee:
Priority: High
Cibersegurity - Feature #4853: Investigación Feature #4853: Investigación

Project: Cibersegurity
Status: New
Start date: 10/03/2025
Due date: 11/19/2025
Assignee:
Priority: Urgent
GRUPO 1 - Feature #5110: Bitácoras Feature #5110: Bitácoras

Project: GRUPO 1
Status: New
Start date: 10/03/2025
Due date: 11/28/2025
Assignee: Marcos Caldas
Priority: Normal
GRUPO 3 - Feature #4851: Revisión y prueba de mecani... Feature #4851: Revisión y prueba de mecanismo de empuje de bloques.

Project: GRUPO 3
Status: Feedback
Start date: 10/03/2025
Due date: 10/06/2025
Assignee: Camilo Geraldo
Priority: High
GRUPO 7 - Feature #5949: FASE 2: DISEÑO Feature #5949: FASE 2: DISEÑO

Project: GRUPO 7
Status: New
Start date: 10/03/2025
Due date: 11/13/2025
Assignee:
Priority: Normal
GRUPO 11 - Feature #5151: Construcción base del Robot Feature #5151: Construcción base del Robot

Project: GRUPO 11
Status: Resolved
Start date: 10/03/2025
Due date: 10/09/2025
Assignee: José Terrazas
Priority: High
GRUPO 11 - Feature #5152: Construcción brazo del robot Feature #5152: Construcción brazo del robot

Project: GRUPO 11
Status: Resolved
Start date: 10/03/2025
Due date: 10/09/2025
Assignee: Alexander Pinto
Priority: Normal
GRUPO 11 - Feature #5153: Construcción garra del robot Feature #5153: Construcción garra del robot

Project: GRUPO 11
Status: Resolved
Start date: 10/03/2025
Due date: 10/10/2025
Assignee: Alexander Pinto
Priority: Normal
GRUPO 11 - Feature #5159: Actualización de software d... Feature #5159: Actualización de software del controlador LEGO

Project: GRUPO 11
Status: Resolved
Start date: 10/03/2025
Due date: 10/04/2025
Assignee: Javier Echeverria
Priority: Normal

4

Grupo 5B 2025 - Feature #5487: Justificación y desarrollo ... Feature #5487: Justificación y desarrollo del diseño

Project: Grupo 5B 2025
Status: New
Start date: 09/28/2025
Due date: 10/04/2025
Assignee:
Priority: High
GRUPO 11 - Feature #5159: Actualización de software d... Feature #5159: Actualización de software del controlador LEGO

Project: GRUPO 11
Status: Resolved
Start date: 10/03/2025
Due date: 10/04/2025
Assignee: Javier Echeverria
Priority: Normal
GRUPO 5 - Feature #5220: Codificación con Bloques Feature #5220: Codificación con Bloques

Project: GRUPO 5
Status: Resolved
Start date: 10/04/2025
Due date: 10/10/2025
Assignee: Joaquin Quezada
Priority: Normal