Calendar
Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday | |
---|---|---|---|---|---|---|---|
40 |
28 |
29
Feature #4902: Construcción del robot
Feature #4902: Construcción del robot
Project: GRUPO 6 Status: Resolved Start date: 09/29/2025 Due date: 10/17/2025 Assignee: Cristofer Lazaro Priority: Normal
Feature #4904: Prueba de diseño del robot
Feature #4904: Prueba de diseño del robot
Project: GRUPO 6 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Cristofer Lazaro Priority: Normal
Feature #5036: Completación bitácora N° 2
Feature #5036: Completación bitácora N° 2
Project: GRUPO 6 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Ruth Huanca Priority: Normal |
30 |
1
Feature #4864: Definir objetivos específicos
Feature #4864: Definir objetivos específicos
Project: GRUPO 6 Status: Resolved Start date: 10/01/2025 Due date: 10/03/2025 Assignee: Cristofer Lazaro Priority: Normal |
2 |
3
Feature #4862: Definir objetivos
Feature #4862: Definir objetivos
Project: GRUPO 6 Status: Resolved Start date: 09/26/2025 Due date: 10/03/2025 Assignee: Abraham Canaviri Priority: Normal
Feature #4864: Definir objetivos específicos
Feature #4864: Definir objetivos específicos
Project: GRUPO 6 Status: Resolved Start date: 10/01/2025 Due date: 10/03/2025 Assignee: Cristofer Lazaro Priority: Normal
Feature #4904: Prueba de diseño del robot
Feature #4904: Prueba de diseño del robot
Project: GRUPO 6 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Cristofer Lazaro Priority: Normal
Feature #5036: Completación bitácora N° 2
Feature #5036: Completación bitácora N° 2
Project: GRUPO 6 Status: Resolved Start date: 09/29/2025 Due date: 10/03/2025 Assignee: Ruth Huanca Priority: Normal |
4 |
41 |
5 |
6
Feature #4874: Trabajar en el informe
Feature #4874: Trabajar en el informe
Project: GRUPO 6 Status: In Progress Start date: 10/06/2025 Due date: 10/17/2025 Assignee: Ruth Huanca Priority: Normal
Feature #4875: Definir actividades
Feature #4875: Definir actividades
Project: GRUPO 6 Status: Resolved Start date: 10/06/2025 Due date: 10/10/2025 Assignee: Abraham Canaviri Priority: Normal
Feature #5037: Completación bitácora N° 3
Feature #5037: Completación bitácora N° 3
Project: GRUPO 6 Status: Resolved Start date: 10/06/2025 Due date: 10/10/2025 Assignee: Ruth Huanca Priority: Normal |
7 |
8
Feature #4876: Realizar la carta gantt
Feature #4876: Realizar la carta gantt
Project: GRUPO 6 Status: Resolved Start date: 10/08/2025 Due date: 10/13/2025 Assignee: Brayan Cahuachia Priority: Normal |
9 |
10
Feature #4875: Definir actividades
Feature #4875: Definir actividades
Project: GRUPO 6 Status: Resolved Start date: 10/06/2025 Due date: 10/10/2025 Assignee: Abraham Canaviri Priority: Normal
Feature #5037: Completación bitácora N° 3
Feature #5037: Completación bitácora N° 3
Project: GRUPO 6 Status: Resolved Start date: 10/06/2025 Due date: 10/10/2025 Assignee: Ruth Huanca Priority: Normal
Feature #4962: Explorar formas de manejar ...
Feature #4962: Explorar formas de manejar el Spike de manera remota
Project: GRUPO 6 Status: Resolved Start date: 10/10/2025 Due date: 10/17/2025 Assignee: Brayan Cahuachia Priority: Normal |
11 |
42 |
12 |
13
Feature #4876: Realizar la carta gantt
Feature #4876: Realizar la carta gantt
Project: GRUPO 6 Status: Resolved Start date: 10/08/2025 Due date: 10/13/2025 Assignee: Brayan Cahuachia Priority: Normal
Feature #5029: Ítem carta Gantt
Feature #5029: Ítem carta Gantt
Project: GRUPO 6 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Ruth Huanca Priority: Normal
Feature #5030: Ítem estimación de costos
Feature #5030: Ítem estimación de costos
Project: GRUPO 6 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Ruth Huanca Priority: Normal
Feature #5031: Ítem conclusión
Feature #5031: Ítem conclusión
Project: GRUPO 6 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Ruth Huanca Priority: Normal
Feature #5032: Revisión del Informe
Feature #5032: Revisión del Informe
Project: GRUPO 6 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Abraham Canaviri Priority: Normal
Feature #5038: Completación bitácora N° 4
Feature #5038: Completación bitácora N° 4
Project: GRUPO 6 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Ruth Huanca Priority: Normal |
14 |
15 |
16 |
17
Feature #4874: Trabajar en el informe
Feature #4874: Trabajar en el informe
Project: GRUPO 6 Status: In Progress Start date: 10/06/2025 Due date: 10/17/2025 Assignee: Ruth Huanca Priority: Normal
Feature #4902: Construcción del robot
Feature #4902: Construcción del robot
Project: GRUPO 6 Status: Resolved Start date: 09/29/2025 Due date: 10/17/2025 Assignee: Cristofer Lazaro Priority: Normal
Feature #4962: Explorar formas de manejar ...
Feature #4962: Explorar formas de manejar el Spike de manera remota
Project: GRUPO 6 Status: Resolved Start date: 10/10/2025 Due date: 10/17/2025 Assignee: Brayan Cahuachia Priority: Normal
Feature #5029: Ítem carta Gantt
Feature #5029: Ítem carta Gantt
Project: GRUPO 6 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Ruth Huanca Priority: Normal
Feature #5030: Ítem estimación de costos
Feature #5030: Ítem estimación de costos
Project: GRUPO 6 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Ruth Huanca Priority: Normal
Feature #5031: Ítem conclusión
Feature #5031: Ítem conclusión
Project: GRUPO 6 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Ruth Huanca Priority: Normal
Feature #5032: Revisión del Informe
Feature #5032: Revisión del Informe
Project: GRUPO 6 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Abraham Canaviri Priority: Normal
Feature #5038: Completación bitácora N° 4
Feature #5038: Completación bitácora N° 4
Project: GRUPO 6 Status: Resolved Start date: 10/13/2025 Due date: 10/17/2025 Assignee: Ruth Huanca Priority: Normal |
18 |
43 |
19 |
20
Feature #5158: Trabajar en el informe 2
Feature #5158: Trabajar en el informe 2
Project: GRUPO 6 Status: New Start date: 10/20/2025 Due date: 11/17/2025 Assignee: Ruth Huanca Priority: Normal
Feature #5241: Control inalámbrico del robot
Feature #5241: Control inalámbrico del robot
Project: GRUPO 6 Status: New Start date: 10/20/2025 Due date: 10/24/2025 Assignee: Brayan Cahuachia Priority: Normal
Feature #5242: Diseñar la interfaz de con...
Feature #5242: Diseñar la interfaz de control
Project: GRUPO 6 Status: New Start date: 10/20/2025 Due date: 10/24/2025 Assignee: Brayan Cahuachia Priority: Normal
Feature #5437: Completación bitácora N° 5
Feature #5437: Completación bitácora N° 5
Project: GRUPO 6 Status: New Start date: 10/20/2025 Due date: 10/24/2025 Assignee: Ruth Huanca Priority: Normal |
21 |
22 |
23 |
24
Feature #4900: Completar bitácora
Feature #4900: Completar bitácora
Project: GRUPO 6 Status: In Progress Start date: 09/26/2025 Due date: 10/24/2025 Assignee: Ruth Huanca Priority: Normal
Feature #5241: Control inalámbrico del robot
Feature #5241: Control inalámbrico del robot
Project: GRUPO 6 Status: New Start date: 10/20/2025 Due date: 10/24/2025 Assignee: Brayan Cahuachia Priority: Normal
Feature #5242: Diseñar la interfaz de con...
Feature #5242: Diseñar la interfaz de control
Project: GRUPO 6 Status: New Start date: 10/20/2025 Due date: 10/24/2025 Assignee: Brayan Cahuachia Priority: Normal
Feature #5437: Completación bitácora N° 5
Feature #5437: Completación bitácora N° 5
Project: GRUPO 6 Status: New Start date: 10/20/2025 Due date: 10/24/2025 Assignee: Ruth Huanca Priority: Normal |
25 |
44 |
26 |
27
Feature #5186: Manual de usuario
Feature #5186: Manual de usuario
Project: GRUPO 6 Status: New Start date: 10/27/2025 Due date: 10/31/2025 Assignee: Francisca Albornoz Priority: Normal
Feature #5190: Planificación
Feature #5190: Planificación
Project: GRUPO 6 Status: New Start date: 10/27/2025 Due date: 10/31/2025 Assignee: Abraham Canaviri Priority: Normal |
28 |
29 |
30 |
31
Feature #5186: Manual de usuario
Feature #5186: Manual de usuario
Project: GRUPO 6 Status: New Start date: 10/27/2025 Due date: 10/31/2025 Assignee: Francisca Albornoz Priority: Normal
Feature #5190: Planificación
Feature #5190: Planificación
Project: GRUPO 6 Status: New Start date: 10/27/2025 Due date: 10/31/2025 Assignee: Abraham Canaviri Priority: Normal |
1 |
issue beginning this day issue ending this day issue beginning and ending this day