Project

General

Profile

Calendar

Filters

« July | September »

Apply Clear

SundayMondayTuesdayWednesdayThursdayFridaySaturday
31

29

30

31

1

2

3

4

32

5

6

7

8

9

Grupo 3 2018 - Feature #399: Construcción del Robot EV3 Feature #399: Construcción del Robot EV3

Project: Grupo 3 2018
Status: Resolved
Start date: 08/09/2018
Due date: 08/30/2018
Assignee: Esteban Ovando
Priority: Normal
Grupo 3 2018 - Feature #400: Designar el modelo del robot Feature #400: Designar el modelo del robot

Project: Grupo 3 2018
Status: Resolved
Start date: 08/09/2018
Due date: 08/14/2018
Assignee: Esteban Ovando
Priority: Normal

10

11

33

12

13

Grupo 3 2018 - Feature #401: Verificación de piezas a usar Feature #401: Verificación de piezas a usar

Project: Grupo 3 2018
Status: Resolved
Start date: 08/13/2018
Due date: 08/21/2018
Assignee: Esteban Ovando
Priority: Normal

14

Grupo 3 2018 - Feature #400: Designar el modelo del robot Feature #400: Designar el modelo del robot

Project: Grupo 3 2018
Status: Resolved
Start date: 08/09/2018
Due date: 08/14/2018
Assignee: Esteban Ovando
Priority: Normal
Grupo 4 2018 - Feature #416: Formulación del Proyecto Feature #416: Formulación del Proyecto

Project: Grupo 4 2018
Status: New
Start date: 08/14/2018
Due date: 09/25/2018
Assignee:
Priority: Normal
Grupo 4 2018 - Feature #417: Avance Carta Gantt Feature #417: Avance Carta Gantt

Project: Grupo 4 2018
Status: New
Start date: 08/14/2018
Due date: 09/25/2018
Assignee:
Priority: Normal
Grupo 4 2018 - Feature #418: Avance del robot EV3 Feature #418: Avance del robot EV3

Project: Grupo 4 2018
Status: New
Start date: 08/14/2018
Due date: 12/06/2018
Assignee:
Priority: High
Grupo 4 2018 - Feature #425: Diseño del Robot Feature #425: Diseño del Robot

Project: Grupo 4 2018
Status: New
Start date: 08/14/2018
Due date: 08/16/2018
Assignee: Cristian Baustista
Priority: High
Grupo 4 2018 - Feature #426: Documentación Parte I Feature #426: Documentación Parte I

Project: Grupo 4 2018
Status: New
Start date: 08/14/2018
Due date: 11/29/2018
Assignee:
Priority: Normal
Grupo 4 2018 - Feature #427: Bitácoras Feature #427: Bitácoras

Project: Grupo 4 2018
Status: New
Start date: 08/14/2018
Due date: 11/29/2018
Assignee:
Priority: Normal
Grupo 4 2018 - Feature #433: Gestión de Riesgos Feature #433: Gestión de Riesgos

Project: Grupo 4 2018
Status: New
Start date: 08/14/2018
Due date: 08/30/2018
Assignee:
Priority: Normal

15

16

Grupo 2 2018 - Feature #206: Organización Proyecto Feature #206: Organización Proyecto

Project: Grupo 2 2018
Status: Resolved
Start date: 08/16/2018
Due date: 08/16/2018
Assignee: Matias Sandoval
Priority: Normal
Grupo 4 2018 - Feature #425: Diseño del Robot Feature #425: Diseño del Robot

Project: Grupo 4 2018
Status: New
Start date: 08/14/2018
Due date: 08/16/2018
Assignee: Cristian Baustista
Priority: High
Grupo 1 2018 - Feature #201: Formulación del Proyecto pa... Feature #201: Formulación del Proyecto parte I

Project: Grupo 1 2018
Status: New
Start date: 08/16/2018
Due date: 09/06/2018
Assignee:
Priority: Normal
Grupo 1 2018 - Feature #214: Documentación del Proyecto Feature #214: Documentación del Proyecto

Project: Grupo 1 2018
Status: New
Start date: 08/16/2018
Due date: 11/29/2018
Assignee: Scarlett Oswald
Priority: Normal
Grupo 1 2018 - Feature #215: Bitacoras Feature #215: Bitacoras

Project: Grupo 1 2018
Status: New
Start date: 08/16/2018
Due date: 11/29/2018
Assignee:
Priority: Normal
Grupo 1 2018 - Feature #266: Informe I Feature #266: Informe I

Project: Grupo 1 2018
Status: New
Start date: 08/16/2018
Due date: 09/06/2018
Assignee:
Priority: Normal
Grupo 2 2018 - Feature #205: Desarrollo Del Proyecto Feature #205: Desarrollo Del Proyecto

Project: Grupo 2 2018
Status: In Progress
Start date: 08/16/2018
Due date: 12/07/2018
Assignee: Matias Sandoval
Priority: Normal
Grupo 3 2018 - Feature #378: Administración del Sitio de... Feature #378: Administración del Sitio de RedMine

Project: Grupo 3 2018
Status: In Progress
Start date: 08/16/2018
Due date: 12/06/2018
Assignee: Gabriel Echeverria
Priority: Normal
Grupo 3 2018 - Feature #380: Bitácora (semanal) Feature #380: Bitácora (semanal)

Project: Grupo 3 2018
Status: In Progress
Start date: 08/16/2018
Due date: 11/29/2018
Assignee: Gabriel Echeverria
Priority: Normal
Grupo 3 2018 - Feature #382: Formulación del proyecto Feature #382: Formulación del proyecto

Project: Grupo 3 2018
Status: Resolved
Start date: 08/16/2018
Due date: 09/11/2018
Assignee: Gabriel Echeverria
Priority: Normal
Grupo 4 2018 - Feature #428: Informe Plan de Proyecto Feature #428: Informe Plan de Proyecto

Project: Grupo 4 2018
Status: New
Start date: 08/16/2018
Due date: 08/28/2018
Assignee:
Priority: Normal

17

18

34

19

20

21

Grupo 2 2018 - Feature #208: Contabilizar Piezas Del Robot Feature #208: Contabilizar Piezas Del Robot

Project: Grupo 2 2018
Status: Resolved
Start date: 08/21/2018
Due date: 08/21/2018
Assignee: Luis Soto
Priority: Normal
Grupo 3 2018 - Feature #401: Verificación de piezas a usar Feature #401: Verificación de piezas a usar

Project: Grupo 3 2018
Status: Resolved
Start date: 08/13/2018
Due date: 08/21/2018
Assignee: Esteban Ovando
Priority: Normal
Grupo 4 2018 - Feature #421: Instalación de Adaptador WIFI Feature #421: Instalación de Adaptador WIFI

Project: Grupo 4 2018
Status: New
Start date: 08/21/2018
Due date: 08/21/2018
Assignee:
Priority: Normal
Grupo 1 2018 - Feature #212: Armado del Robot EV3 Feature #212: Armado del Robot EV3

Project: Grupo 1 2018
Status: New
Start date: 08/21/2018
Due date: 08/30/2018
Assignee: Diego Berrios
Priority: Normal
Grupo 1 2018 - Feature #213: Instalación del Sistema Ope... Feature #213: Instalación del Sistema Operativo ev3dev

Project: Grupo 1 2018
Status: New
Start date: 08/21/2018
Due date: 08/23/2018
Assignee: Miguel Rivero
Priority: Normal
Grupo 2 2018 - Feature #207: Proyecto: Parte 1 Feature #207: Proyecto: Parte 1

Project: Grupo 2 2018
Status: Resolved
Start date: 08/21/2018
Due date: 08/23/2018
Assignee: Matias Sandoval
Priority: Normal
Grupo 2 2018 - Feature #209: Armar Robot Feature #209: Armar Robot

Project: Grupo 2 2018
Status: Resolved
Start date: 08/21/2018
Due date: 08/23/2018
Assignee: José Ignacio Le Blanc
Priority: Normal
Grupo 2 2018 - Feature #210: Instalar S.O en la SD. Feature #210: Instalar S.O en la SD.

Project: Grupo 2 2018
Status: Resolved
Start date: 08/21/2018
Due date: 08/23/2018
Assignee: Nicolas Jorquera
Priority: Normal
Grupo 3 2018 - Feature #402: Ensamblaje del Robot. Feature #402: Ensamblaje del Robot.

Project: Grupo 3 2018
Status: Resolved
Start date: 08/21/2018
Due date: 08/30/2018
Assignee:
Priority: Normal
Grupo 4 2018 - Feature #419: Construcción Robot EV3 Feature #419: Construcción Robot EV3

Project: Grupo 4 2018
Status: New
Start date: 08/21/2018
Due date: 08/30/2018
Assignee: Cristian Baustista
Priority: High
Grupo 4 2018 - Feature #420: Instalación del Sistema Ope... Feature #420: Instalación del Sistema Operativo EV3DEV

Project: Grupo 4 2018
Status: New
Start date: 08/21/2018
Due date: 08/23/2018
Assignee: Christian Caceres
Priority: Normal
Grupo 5 2018 - Feature #217: Planteamiento del Problema Feature #217: Planteamiento del Problema

Project: Grupo 5 2018
Status: New
Start date: 08/21/2018
Due date: 08/23/2018
Assignee:
Priority: Normal
Grupo 5 2018 - Feature #218: Documentacion del Proyecto Feature #218: Documentacion del Proyecto

Project: Grupo 5 2018
Status: New
Start date: 08/21/2018
Due date: 12/06/2018
Assignee:
Priority: Normal
Grupo 5 2018 - Support #219: Bitacoras semanales Support #219: Bitacoras semanales

Project: Grupo 5 2018
Status: New
Start date: 08/21/2018
Due date: 12/06/2018
Assignee:
Priority: Normal
Grupo 5 2018 - Feature #222: Ensamblado del Robot Feature #222: Ensamblado del Robot

Project: Grupo 5 2018
Status: New
Start date: 08/21/2018
Due date: 08/30/2018
Assignee: Jeremy Gaete
Priority: Normal
Grupo 5 2018 - Support #223: Adquirir las piezas del Robot Support #223: Adquirir las piezas del Robot

Project: Grupo 5 2018
Status: New
Start date: 08/21/2018
Due date: 08/28/2018
Assignee: Jonathan Bravo
Priority: Normal
Grupo 6 2018 - Feature #211: Armar Robot Feature #211: Armar Robot

Project: Grupo 6 2018
Status: New
Start date: 08/21/2018
Due date: 09/06/2018
Assignee: Nicolas Vargas
Priority: High

22

Grupo 5 2018 - Support #225: Trabajo de Codigo Support #225: Trabajo de Codigo

Project: Grupo 5 2018
Status: New
Start date: 08/22/2018
Due date: 10/25/2018
Assignee:
Priority: Normal
Grupo 5 2018 - Support #227: Estudiar Lenguaje de Progra... Support #227: Estudiar Lenguaje de Programación Python

Project: Grupo 5 2018
Status: New
Start date: 08/22/2018
Due date: 10/18/2018
Assignee: Jonathan Bravo
Priority: Normal

23

Grupo 1 2018 - Feature #213: Instalación del Sistema Ope... Feature #213: Instalación del Sistema Operativo ev3dev

Project: Grupo 1 2018
Status: New
Start date: 08/21/2018
Due date: 08/23/2018
Assignee: Miguel Rivero
Priority: Normal
Grupo 2 2018 - Feature #207: Proyecto: Parte 1 Feature #207: Proyecto: Parte 1

Project: Grupo 2 2018
Status: Resolved
Start date: 08/21/2018
Due date: 08/23/2018
Assignee: Matias Sandoval
Priority: Normal
Grupo 2 2018 - Feature #209: Armar Robot Feature #209: Armar Robot

Project: Grupo 2 2018
Status: Resolved
Start date: 08/21/2018
Due date: 08/23/2018
Assignee: José Ignacio Le Blanc
Priority: Normal
Grupo 2 2018 - Feature #210: Instalar S.O en la SD. Feature #210: Instalar S.O en la SD.

Project: Grupo 2 2018
Status: Resolved
Start date: 08/21/2018
Due date: 08/23/2018
Assignee: Nicolas Jorquera
Priority: Normal
Grupo 4 2018 - Feature #420: Instalación del Sistema Ope... Feature #420: Instalación del Sistema Operativo EV3DEV

Project: Grupo 4 2018
Status: New
Start date: 08/21/2018
Due date: 08/23/2018
Assignee: Christian Caceres
Priority: Normal
Grupo 5 2018 - Feature #217: Planteamiento del Problema Feature #217: Planteamiento del Problema

Project: Grupo 5 2018
Status: New
Start date: 08/21/2018
Due date: 08/23/2018
Assignee:
Priority: Normal
Grupo 1 2018 - Feature #244: Estudio de la Librería ev3d... Feature #244: Estudio de la Librería ev3devlang-python

Project: Grupo 1 2018
Status: New
Start date: 08/23/2018
Due date: 08/28/2018
Assignee: Miguel Rivero
Priority: Normal
Grupo 1 2018 - Bug #331: Estudio del Lenguaje de Pro... Bug #331: Estudio del Lenguaje de Programación Python

Project: Grupo 1 2018
Status: New
Start date: 08/23/2018
Due date: 09/04/2018
Assignee: Miguel Rivero
Priority: Normal
Grupo 2 2018 - Feature #238: Proyecto: Parte 2 Feature #238: Proyecto: Parte 2

Project: Grupo 2 2018
Status: In Progress
Start date: 08/23/2018
Due date: 09/06/2018
Assignee: Matias Sandoval
Priority: Normal
Grupo 2 2018 - Feature #239: Estudiar Algoritmos Cubo Feature #239: Estudiar Algoritmos Cubo

Project: Grupo 2 2018
Status: In Progress
Start date: 08/23/2018
Due date: 09/04/2018
Assignee: Matias Sandoval
Priority: Normal
Grupo 2 2018 - Feature #240: Pruebas Estructura Robot Feature #240: Pruebas Estructura Robot

Project: Grupo 2 2018
Status: In Progress
Start date: 08/23/2018
Due date: 09/04/2018
Assignee: Nicolas Jorquera
Priority: Normal
Grupo 2 2018 - Feature #241: Ampliar Conocimiento Python Feature #241: Ampliar Conocimiento Python

Project: Grupo 2 2018
Status: In Progress
Start date: 08/23/2018
Due date: 09/06/2018
Assignee: José Ignacio Le Blanc
Priority: Normal
Grupo 2 2018 - Feature #242: Ideas Previas Aplicación Feature #242: Ideas Previas Aplicación

Project: Grupo 2 2018
Status: In Progress
Start date: 08/23/2018
Due date: 09/06/2018
Assignee: Luis Soto
Priority: Normal
Grupo 2 2018 - Feature #256: Proyecto: Parte 3 Feature #256: Proyecto: Parte 3

Project: Grupo 2 2018
Status: In Progress
Start date: 08/23/2018
Due date: 09/11/2018
Assignee: Matias Sandoval
Priority: Normal
Grupo 2 2018 - Feature #267: Formulación de Proyecto Feature #267: Formulación de Proyecto

Project: Grupo 2 2018
Status: In Progress
Start date: 08/23/2018
Due date: 09/03/2018
Assignee: Matias Sandoval
Priority: Normal
Grupo 5 2018 - Feature #224: Armar el Robot Feature #224: Armar el Robot

Project: Grupo 5 2018
Status: New
Start date: 08/23/2018
Due date: 08/30/2018
Assignee: Jeremy Gaete
Priority: Normal
Grupo 5 2018 - Support #226: Comprensión y adaptación de... Support #226: Comprensión y adaptación del codigo de Mind Cuber

Project: Grupo 5 2018
Status: New
Start date: 08/23/2018
Due date: 10/18/2018
Assignee: Jonathan Bravo
Priority: Normal

24

25

35

26

27

28

Grupo 1 2018 - Feature #244: Estudio de la Librería ev3d... Feature #244: Estudio de la Librería ev3devlang-python

Project: Grupo 1 2018
Status: New
Start date: 08/23/2018
Due date: 08/28/2018
Assignee: Miguel Rivero
Priority: Normal
Grupo 4 2018 - Feature #428: Informe Plan de Proyecto Feature #428: Informe Plan de Proyecto

Project: Grupo 4 2018
Status: New
Start date: 08/16/2018
Due date: 08/28/2018
Assignee:
Priority: Normal
Grupo 5 2018 - Support #223: Adquirir las piezas del Robot Support #223: Adquirir las piezas del Robot

Project: Grupo 5 2018
Status: New
Start date: 08/21/2018
Due date: 08/28/2018
Assignee: Jonathan Bravo
Priority: Normal
Grupo 5 2018 - Support #229: Instalacion del S.O ev3dev Support #229: Instalacion del S.O ev3dev

Project: Grupo 5 2018
Status: New
Start date: 08/28/2018
Due date: 08/30/2018
Assignee:
Priority: Normal
Grupo 6 2018 - Feature #251: Informe 1 Feature #251: Informe 1

Project: Grupo 6 2018
Status: New
Start date: 08/28/2018
Due date: 09/06/2018
Assignee: Nicolas Vargas
Priority: High
Grupo 6 2018 - Support #252: Aprender Python Support #252: Aprender Python

Project: Grupo 6 2018
Status: New
Start date: 08/28/2018
Due date: 09/13/2018
Assignee:
Priority: Normal

29

30

Grupo 1 2018 - Feature #212: Armado del Robot EV3 Feature #212: Armado del Robot EV3

Project: Grupo 1 2018
Status: New
Start date: 08/21/2018
Due date: 08/30/2018
Assignee: Diego Berrios
Priority: Normal
Grupo 3 2018 - Feature #399: Construcción del Robot EV3 Feature #399: Construcción del Robot EV3

Project: Grupo 3 2018
Status: Resolved
Start date: 08/09/2018
Due date: 08/30/2018
Assignee: Esteban Ovando
Priority: Normal
Grupo 3 2018 - Feature #402: Ensamblaje del Robot. Feature #402: Ensamblaje del Robot.

Project: Grupo 3 2018
Status: Resolved
Start date: 08/21/2018
Due date: 08/30/2018
Assignee:
Priority: Normal
Grupo 4 2018 - Feature #419: Construcción Robot EV3 Feature #419: Construcción Robot EV3

Project: Grupo 4 2018
Status: New
Start date: 08/21/2018
Due date: 08/30/2018
Assignee: Cristian Baustista
Priority: High
Grupo 4 2018 - Feature #433: Gestión de Riesgos Feature #433: Gestión de Riesgos

Project: Grupo 4 2018
Status: New
Start date: 08/14/2018
Due date: 08/30/2018
Assignee:
Priority: Normal
Grupo 5 2018 - Feature #222: Ensamblado del Robot Feature #222: Ensamblado del Robot

Project: Grupo 5 2018
Status: New
Start date: 08/21/2018
Due date: 08/30/2018
Assignee: Jeremy Gaete
Priority: Normal
Grupo 5 2018 - Feature #224: Armar el Robot Feature #224: Armar el Robot

Project: Grupo 5 2018
Status: New
Start date: 08/23/2018
Due date: 08/30/2018
Assignee: Jeremy Gaete
Priority: Normal
Grupo 5 2018 - Support #229: Instalacion del S.O ev3dev Support #229: Instalacion del S.O ev3dev

Project: Grupo 5 2018
Status: New
Start date: 08/28/2018
Due date: 08/30/2018
Assignee:
Priority: Normal
Grupo 1 2018 - Feature #264: Presentación I Feature #264: Presentación I

Project: Grupo 1 2018
Status: New
Start date: 08/30/2018
Due date: 09/06/2018
Assignee: Scarlett Oswald
Priority: Normal
Grupo 1 2018 - Bug #312: Pruebas Bug #312: Pruebas

Project: Grupo 1 2018
Status: New
Start date: 08/30/2018
Due date: 11/27/2018
Assignee: Diego Berrios
Priority: Normal
Grupo 1 2018 - Feature #313: Prueba 1 Feature #313: Prueba 1

Project: Grupo 1 2018
Status: New
Start date: 08/30/2018
Due date: 09/06/2018
Assignee: Diego Berrios
Priority: Normal
Grupo 2 2018 - Feature #262: Realizar Presentación Feature #262: Realizar Presentación

Project: Grupo 2 2018
Status: New
Start date: 08/30/2018
Due date: 09/06/2018
Assignee: Matias Sandoval
Priority: Normal
Grupo 3 2018 - Support #379: Desarrollo de la wiki Support #379: Desarrollo de la wiki

Project: Grupo 3 2018
Status: In Progress
Start date: 08/30/2018
Due date: 11/15/2018
Assignee: Pedro Araya
Priority: Normal
Grupo 3 2018 - Feature #381: Carta Gantt Feature #381: Carta Gantt

Project: Grupo 3 2018
Status: Resolved
Start date: 08/30/2018
Due date: 09/11/2018
Assignee: Gabriel Echeverria
Priority: Normal
Grupo 3 2018 - Feature #391: Programación del Brick Ev3 Feature #391: Programación del Brick Ev3

Project: Grupo 3 2018
Status: In Progress
Start date: 08/30/2018
Due date: 11/22/2018
Assignee: Nicolas Colque
Priority: Normal
Grupo 3 2018 - Feature #392: Instalación del sistema ope... Feature #392: Instalación del sistema operativo

Project: Grupo 3 2018
Status: Resolved
Start date: 08/30/2018
Due date: 09/04/2018
Assignee: Nicolas Colque
Priority: Normal
Grupo 6 2018 - Feature #375: Realizar Wiki Feature #375: Realizar Wiki

Project: Grupo 6 2018
Status: New
Start date: 08/30/2018
Due date: 11/22/2018
Assignee: David Orellana
Priority: Normal
Grupo 6 2018 - Feature #376: Aprender html Feature #376: Aprender html

Project: Grupo 6 2018
Status: New
Start date: 08/30/2018
Due date: 09/06/2018
Assignee: David Orellana
Priority: Normal
Grupo 6 2018 - Support #385: Programación del Robot Support #385: Programación del Robot

Project: Grupo 6 2018
Status: New
Start date: 08/30/2018
Due date: 10/25/2018
Assignee: Nicolas Vargas
Priority: High
Grupo 6 2018 - Bug #388: Conexión Computador Robot Bug #388: Conexión Computador Robot

Project: Grupo 6 2018
Status: New
Start date: 08/30/2018
Due date: 09/06/2018
Assignee: Nicolas Vargas
Priority: High

31

1

issue beginning this day issue ending this day issue beginning and ending this day