Feature #2428: Definir proyecto Feature #2428: Definir proyecto

Project: Grupo P2-2
Status: Resolved
Start date: 08/22/2023
Due date: 08/22/2023
Assignee:
Priority: Normal
Bug #2577: Entrega y presentación de I... Bug #2577: Entrega y presentación de Informe

Project: Grupo P2-2
Status: New
Start date: 08/22/2023
Due date: 09/20/2023
Assignee:
Priority: Normal

23

Bug #2578: Definir escenario y problem... Bug #2578: Definir escenario y problema a solucionar

Project: Grupo P2-2
Status: New
Start date: 08/23/2023
Due date: 08/30/2023
Assignee:
Priority: Normal

24

25

26

35

27

28

Bug #2433: Comprar / Adquirir materiales Bug #2433: Comprar / Adquirir materiales

Project: Grupo P2-2
Status: New
Start date: 08/28/2023
Due date: 09/01/2023
Assignee:
Priority: Normal

29

30

Bug #2578: Definir escenario y problem... Bug #2578: Definir escenario y problema a solucionar

Project: Grupo P2-2
Status: New
Start date: 08/23/2023
Due date: 08/30/2023
Assignee:
Priority: Normal
Bug #2576: Confección y presentación d... Bug #2576: Confección y presentación de maqueta

Project: Grupo P2-2
Status: New
Start date: 08/30/2023
Due date: 09/06/2023
Assignee:
Priority: Normal

31

Bug #2867: Elaboración de Bitácoras Bug #2867: Elaboración de Bitácoras

Project: Grupo P2-2
Status: New
Start date: 08/31/2023
Due date: 12/20/2023
Assignee:
Priority: Normal

1

Bug #2433: Comprar / Adquirir materiales Bug #2433: Comprar / Adquirir materiales

Project: Grupo P2-2
Status: New
Start date: 08/28/2023
Due date: 09/01/2023
Assignee:
Priority: Normal