49

1

2

3

Feature #630: Mostrar Programación del si... Feature #630: Mostrar Programación del sistema

Project: Grupo II
Status: New
Start date: 11/19/2019
Due date: 12/03/2019
Assignee: Huber Ticona
Priority: Normal
Feature #631: Pruebas experimentales y en... Feature #631: Pruebas experimentales y entrega Informe final del proyecto

Project: Grupo II
Status: New
Start date: 12/03/2019
Due date: 12/10/2019
Assignee: Camilo Mamani
Priority: High

4

5

6

7

50

8

9

Feature #603: Documentacion del proyecto Feature #603: Documentacion del proyecto

Project: Grupo II
Status: New
Start date: 08/13/2019
Due date: 12/09/2019
Assignee: Huber Ticona
Priority: Normal
Feature #605: Bitácoras semanales Feature #605: Bitácoras semanales

Project: Grupo II
Status: New
Start date: 08/13/2019
Due date: 12/09/2019
Assignee: Huber Ticona
Priority: Normal

10

Feature #631: Pruebas experimentales y en... Feature #631: Pruebas experimentales y entrega Informe final del proyecto

Project: Grupo II
Status: New
Start date: 12/03/2019
Due date: 12/10/2019
Assignee: Camilo Mamani
Priority: High

11

12

13

14

51

15

16

17

18

19

20

21

52

22

23

24

25

26

27

28

1

29

30

31

1

2

3

4

issue beginning this day issue ending this day issue beginning and ending this day