Project

General

Profile

Calendar

Filters

« September | November »

Apply Clear

SundayMondayTuesdayWednesdayThursdayFridaySaturday
40

28

29

30

1

2

3

4

41

5

6

Feature #4861: Presentación Maqueta Feature #4861: Presentación Maqueta

Project: Grupo 3A 2025
Status: New
Start date: 10/06/2025
Due date: 10/08/2025
Assignee: Guillermo Pino
Priority: Normal

7

Feature #4785: Maqueta Feature #4785: Maqueta

Project: Grupo 3A 2025
Status: New
Start date: 09/24/2025
Due date: 10/07/2025
Assignee: Iván Collao
Priority: Normal

8

Feature #4861: Presentación Maqueta Feature #4861: Presentación Maqueta

Project: Grupo 3A 2025
Status: New
Start date: 10/06/2025
Due date: 10/08/2025
Assignee: Guillermo Pino
Priority: Normal
Feature #4888: Informe 1 Feature #4888: Informe 1

Project: Grupo 3A 2025
Status: New
Start date: 10/08/2025
Due date: 10/28/2025
Assignee: giorgio rojas
Priority: High

9

10

11

42

12

13

14

15

16

17

18

43

19

20

21

22

23

24

25

44

26

27

28

Feature #4784: Fase 1 Feature #4784: Fase 1

Project: Grupo 3A 2025
Status: New
Start date: 09/24/2025
Due date: 10/28/2025
Assignee: Guillermo Pino
Priority: High
Feature #4888: Informe 1 Feature #4888: Informe 1

Project: Grupo 3A 2025
Status: New
Start date: 10/08/2025
Due date: 10/28/2025
Assignee: giorgio rojas
Priority: High

29

30

31

1

issue beginning this day issue ending this day issue beginning and ending this day