Feature #5316: Fase de pruebas Feature #5316: Fase de pruebas

Project: Tiro-Arco
Status: New
Start date: 12/01/2025
Due date: 12/21/2025
Assignee:
Priority: Normal

2

3

4

5

Feature #5320: FASE III Reunion con el cli... Feature #5320: FASE III Reunion con el cliente

Project: Tiro-Arco
Status: New
Start date: 12/05/2025
Due date: 12/05/2025
Assignee:
Priority: Normal

6

50

7

8

9

10

11

12

13

51

14

15

Feature #5317: Fase de Análisis Feature #5317: Fase de Análisis

Project: Tiro-Arco
Status: New
Start date: 12/15/2025
Due date: 12/31/2025
Assignee:
Priority: Normal

16

17

18

19

20

52

21

Feature #5316: Fase de pruebas Feature #5316: Fase de pruebas

Project: Tiro-Arco
Status: New
Start date: 12/01/2025
Due date: 12/21/2025
Assignee:
Priority: Normal

22

23

24

25

26

27

1

28

29

Feature #5318: Realización de manual de us... Feature #5318: Realización de manual de usuario

Project: Tiro-Arco
Status: New
Start date: 12/29/2025
Due date: 12/31/2025
Assignee:
Priority: Normal

30

31

Support #5106: Desarrollo del Software Support #5106: Desarrollo del Software

Project: Tiro-Arco
Status: New
Start date: 11/03/2025
Due date: 12/31/2025
Assignee:
Priority: Normal
Feature #5317: Fase de Análisis Feature #5317: Fase de Análisis

Project: Tiro-Arco
Status: New
Start date: 12/15/2025
Due date: 12/31/2025
Assignee:
Priority: Normal
Feature #5318: Realización de manual de us... Feature #5318: Realización de manual de usuario

Project: Tiro-Arco