  Feature #3560: Desarrollo de frontend
  Feature #3560: Desarrollo de frontend Project: GRUPO P4-1 PUERTO Status: New Start date: 05/13/2024 Due date: 05/26/2024 Assignee: Priority: Normal | 27 
  
  Feature #3561: Realizar conexion y testear...
  Feature #3561: Realizar conexion y testear base de datos Project: GRUPO P4-1 PUERTO Status: New Start date: 05/27/2024 Due date: 05/31/2024 Assignee: Priority: Normal | 28 | 29 | 30 | 31 
  
  Feature #3561: Realizar conexion y testear...
  Feature #3561: Realizar conexion y testear base de datos Project: GRUPO P4-1 PUERTO Status: New Start date: 05/27/2024 Due date: 05/31/2024 Assignee: Priority: Normal | 1 
  
  Feature #3578: Desarrollo de reportes pers...
  Feature #3578: Desarrollo de reportes personalizados Project: GRUPO P4-1 PUERTO Status: New Start date: 06/01/2024 Due date: 06/08/2024 Assignee: Priority: Normal | 
| 23 | 2 | 3 | 4 | 5 | 6 | 7 | 8 
  
  Feature #3540: Desarrollo
  Feature #3540: Desarrollo Project: GRUPO P4-1 PUERTO Status: New Start date: 04/30/2024 Due date: 06/08/2024 Assignee: Priority: Normal 
  
  Feature #3578: Desarrollo de reportes pers...
  Feature #3578: Desarrollo de reportes personalizados Project: GRUPO P4-1 PUERTO Status: New Start date: 06/01/2024 Due date: 06/08/2024 Assignee: Priority: Normal | 
| 24 | 9 
  
  Feature #3541: Finalizacion del proyecto
  Feature #3541: Finalizacion del proyecto Project: GRUPO P4-1 PUERTO Status: New Start date: 06/09/2024 Due date: 06/30/2024 Assignee: Priority: Normal 
  
  Feature #3558: Finalizar producto y Elabor...
  Feature #3558: Finalizar producto y Elaborar informe Project: GRUPO P4-1 PUERTO Status: New Start date: 06/09/2024 Due date: 06/11/2024 Assignee: Priority: Normal | 10 | 11 
  
  Feature #3558: Finalizar producto y Elabor...
  Feature #3558: Finalizar producto y Elaborar informe Project: GRUPO P4-1 PUERTO Status: New Start date: 06/09/2024 Due date: 06/11/2024 Assignee: Priority: Normal | 12 
  
  Feature #3557: Manual de usuario
  Feature #3557: Manual de usuario Project: GRUPO P4-1 PUERTO Status: New Start date: 06/12/2024 Due date: 06/26/2024 Assignee: Priority: Normal | 13 | 14 | 15 | 
| 25 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 
| 26 | 23 | 24 | 25 | 26 
  
  Feature #3557: Manual de usuario
  Feature #3557: Manual de usuario Project: GRUPO P4-1 PUERTO Status: New Start date: 06/12/2024 Due date: 06/26/2024 Assignee: Priority: Normal | 27 
  
  Feature #3556: Elaboracion de Poster
  Feature #3556: Elaboracion de Poster Project: GRUPO P4-1 PUERTO Status: New Start date: 06/27/2024 Due date: 06/30/2024 Assignee: Priority: Normal | 28 | 29 | 
| 27 | 30 
  
  Feature #3541: Finalizacion del proyecto
  Feature #3541: Finalizacion del proyecto Project: GRUPO P4-1 PUERTO Status: New Start date: 06/09/2024 Due date: 06/30/2024 Assignee: Priority: Normal 
  
  Feature #3556: Elaboracion de Poster
  Feature #3556: Elaboracion de Poster Project: GRUPO P4-1 PUERTO Status: New Start date: 06/27/2024 Due date: 06/30/2024 Assignee: Priority: Normal | 1 | 2 | 3 | 4 | 5 | 6 | 