Project

General

Profile

Calendar

Filters

« March | May »

Apply Clear

SundayMondayTuesdayWednesdayThursdayFridaySaturday
14

31

1

2

3

4

Feature #3539: Investigacion y coordinacion Feature #3539: Investigacion y coordinacion

Project: GRUPO P4-1 PUERTO
Status: In Progress
Start date: 04/04/2024
Due date: 04/29/2024
Assignee: Ignacio Córdova
Priority: High
Feature #3542: Reunion Feature #3542: Reunion

Project: GRUPO P4-1 PUERTO
Status: Resolved
Start date: 04/04/2024
Due date: 04/12/2024
Assignee: Ignacio Córdova
Priority: High

5

6

15

7

8

9

10

11

12

Feature #3542: Reunion Feature #3542: Reunion

Project: GRUPO P4-1 PUERTO
Status: Resolved
Start date: 04/04/2024
Due date: 04/12/2024
Assignee: Ignacio Córdova
Priority: High

13

Feature #3543: Elaboracion acta de acuerdo... Feature #3543: Elaboracion acta de acuerdo formal

Project: GRUPO P4-1 PUERTO
Status: Resolved
Start date: 04/13/2024
Due date: 04/19/2024
Assignee: Ignacio Córdova
Priority: Normal
16

14

15

16

17

18

19

Feature #3543: Elaboracion acta de acuerdo... Feature #3543: Elaboracion acta de acuerdo formal

Project: GRUPO P4-1 PUERTO
Status: Resolved
Start date: 04/13/2024
Due date: 04/19/2024
Assignee: Ignacio Córdova
Priority: Normal

20

17

21

22

23

24

25

26

Feature #3577: Diseño del proyecto Feature #3577: Diseño del proyecto

Project: GRUPO P4-1 PUERTO
Status: New
Start date: 04/26/2024
Due date: 04/29/2024
Assignee: Ignacio Córdova
Priority: Normal

27

18

28

29

Feature #3539: Investigacion y coordinacion Feature #3539: Investigacion y coordinacion

Project: GRUPO P4-1 PUERTO
Status: In Progress
Start date: 04/04/2024
Due date: 04/29/2024
Assignee: Ignacio Córdova
Priority: High
Feature #3577: Diseño del proyecto Feature #3577: Diseño del proyecto

Project: GRUPO P4-1 PUERTO
Status: New
Start date: 04/26/2024
Due date: 04/29/2024
Assignee: Ignacio Córdova
Priority: Normal

30

Feature #3540: Desarrollo Feature #3540: Desarrollo

Project: GRUPO P4-1 PUERTO
Status: New
Start date: 04/30/2024
Due date: 06/08/2024
Assignee:
Priority: Normal
Feature #3559: Desarrollo backend Feature #3559: Desarrollo backend

Project: GRUPO P4-1 PUERTO
Status: New
Start date: 04/30/2024
Due date: 05/12/2024
Assignee:
Priority: Normal
Feature #3651: Conectar las bases de datos Feature #3651: Conectar las bases de datos

Project: GRUPO P4-1 PUERTO
Status: New
Start date: 04/30/2024
Due date: 05/07/2024
Assignee: Ignacio Córdova
Priority: Normal

1

2

3

4

issue beginning this day issue ending this day issue beginning and ending this day