Project

General

Profile

Calendar

Filters

« May | July »

Apply Clear

SundayMondayTuesdayWednesdayThursdayFridaySaturday
22

26

Feature #3602: Desarrollo de Aspectos Inic... Feature #3602: Desarrollo de Aspectos Iniciales

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 05/13/2024
Due date: 05/26/2024
Assignee:
Priority: Normal
Feature #3603: Subir proyecto a Github Feature #3603: Subir proyecto a Github

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 05/20/2024
Due date: 05/26/2024
Assignee:
Priority: Normal

27

Feature #3591: Avance 3 Feature #3591: Avance 3

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 05/27/2024
Due date: 06/23/2024
Assignee:
Priority: High
Feature #3605: Implementación del proyecto Feature #3605: Implementación del proyecto

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 05/27/2024
Due date: 06/23/2024
Assignee:
Priority: High

28

29

30

31

1

23

2

Feature #3590: Avance 2 Feature #3590: Avance 2

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 05/06/2024
Due date: 06/02/2024
Assignee:
Priority: Normal
Feature #3604: Informe plan de proyecto Feature #3604: Informe plan de proyecto

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 06/02/2024
Due date: 06/02/2024
Assignee:
Priority: Normal

3

4

5

6

7

8

24

9

10

11

12

13

14

15

25

16

Feature #3606: Informe de Avance 3 Feature #3606: Informe de Avance 3

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 06/16/2024
Due date: 06/16/2024
Assignee:
Priority: Normal

17

18

19

20

21

22

26

23

Feature #3591: Avance 3 Feature #3591: Avance 3

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 05/27/2024
Due date: 06/23/2024
Assignee:
Priority: High
Feature #3605: Implementación del proyecto Feature #3605: Implementación del proyecto

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 05/27/2024
Due date: 06/23/2024
Assignee:
Priority: High

24

Feature #3592: Fase final Feature #3592: Fase final

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 06/24/2024
Due date: 07/08/2024
Assignee:
Priority: High
Feature #3607: Pruebas Feature #3607: Pruebas

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 06/24/2024
Due date: 06/30/2024
Assignee:
Priority: Normal
Feature #3608: Presentacion de producto a ... Feature #3608: Presentacion de producto a Cliente

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 06/24/2024
Due date: 06/30/2024
Assignee:
Priority: Normal

25

26

27

28

29

27

30

Feature #3607: Pruebas Feature #3607: Pruebas

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 06/24/2024
Due date: 06/30/2024
Assignee:
Priority: Normal
Feature #3608: Presentacion de producto a ... Feature #3608: Presentacion de producto a Cliente

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 06/24/2024
Due date: 06/30/2024
Assignee:
Priority: Normal
Feature #3609: Carta de aprobación Feature #3609: Carta de aprobación

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 06/30/2024
Due date: 06/30/2024
Assignee:
Priority: Normal

1

Feature #3610: Entrega de Producto Feature #3610: Entrega de Producto

Project: GRUPO P4-1 NEWENCHE
Status: Resolved
Start date: 07/01/2024
Due date: 07/08/2024
Assignee:
Priority: High

2

3

4

5

6

issue beginning this day issue ending this day issue beginning and ending this day