Project

General

Profile

Calendar

Filters

« August | October »

Apply Clear

SundayMondayTuesdayWednesdayThursdayFridaySaturday
35

27

28

29

Feature #2452: Diseñar maqueta Feature #2452: Diseñar maqueta

Project: Grupo P2-5
Status: New
Start date: 08/29/2023
Due date: 08/31/2023
Assignee: luciano vera
Priority: Normal

30

31

Feature #2452: Diseñar maqueta Feature #2452: Diseñar maqueta

Project: Grupo P2-5
Status: New
Start date: 08/29/2023
Due date: 08/31/2023
Assignee: luciano vera
Priority: Normal

1

Feature #2453: Construir maqueta Feature #2453: Construir maqueta

Project: Grupo P2-5
Status: New
Start date: 09/01/2023
Due date: 09/05/2023
Assignee: luciano vera
Priority: Normal

2

36

3

4

5

Feature #2453: Construir maqueta Feature #2453: Construir maqueta

Project: Grupo P2-5
Status: New
Start date: 09/01/2023
Due date: 09/05/2023
Assignee: luciano vera
Priority: Normal
Feature #2789: Presentación maqueta Feature #2789: Presentación maqueta

Project: Grupo P2-5
Status: New
Start date: 09/05/2023
Due date: 09/05/2023
Assignee: bastian vega
Priority: Normal

6

7

Feature #2450: Informe l Feature #2450: Informe l

Project: Grupo P2-5
Status: New
Start date: 09/07/2023
Due date: 09/21/2023
Assignee: Andrew Campos
Priority: Normal

8

9

37

10

11

12

Feature #3104: Análisis de framework Feature #3104: Análisis de framework

Project: Grupo P2-5
Status: New
Start date: 09/12/2023
Due date: 09/16/2023
Assignee: bastian vega
Priority: Normal

13

14

15

16

Feature #3104: Análisis de framework Feature #3104: Análisis de framework

Project: Grupo P2-5
Status: New
Start date: 09/12/2023
Due date: 09/16/2023
Assignee: bastian vega
Priority: Normal
38

17

Feature #2449: Estimar costos Feature #2449: Estimar costos

Project: Grupo P2-5
Status: New
Start date: 09/17/2023
Due date: 09/20/2023
Assignee: bastian vega
Priority: Normal

18

19

20

Feature #2449: Estimar costos Feature #2449: Estimar costos

Project: Grupo P2-5
Status: New
Start date: 09/17/2023
Due date: 09/20/2023
Assignee: bastian vega
Priority: Normal

21

Feature #2450: Informe l Feature #2450: Informe l

Project: Grupo P2-5
Status: New
Start date: 09/07/2023
Due date: 09/21/2023
Assignee: Andrew Campos
Priority: Normal

22

Feature #2451: Presentación l Feature #2451: Presentación l

Project: Grupo P2-5
Status: New
Start date: 09/22/2023
Due date: 09/25/2023
Assignee: luciano vera
Priority: Normal

23

39

24

25

Feature #2446: Parte l Feature #2446: Parte l

Project: Grupo P2-5
Status: New
Start date: 08/21/2023
Due date: 09/25/2023
Assignee: Vranika Santiago
Priority: Normal
Feature #2451: Presentación l Feature #2451: Presentación l

Project: Grupo P2-5
Status: New
Start date: 09/22/2023
Due date: 09/25/2023
Assignee: luciano vera
Priority: Normal
Feature #2454: Parte ll Feature #2454: Parte ll

Project: Grupo P2-5
Status: New
Start date: 09/25/2023
Due date: 11/28/2023
Assignee: Vranika Santiago
Priority: Normal
Feature #2839: Realizar Casos de Uso Feature #2839: Realizar Casos de Uso

Project: Grupo P2-5
Status: New
Start date: 09/25/2023
Due date: 11/03/2023
Assignee: Andrew Campos
Priority: Normal

26

27

28

29

30

issue beginning this day issue ending this day issue beginning and ending this day