36

1

2

3

Feature #649: Formulacion del Plan de pro... Feature #649: Formulacion del Plan de proyecto

Project: Grupo I
Status: New
Start date: 08/20/2019
Due date: 09/03/2019
Assignee: Rodrigo González
Priority: Normal
Feature #651: Levantamiento de requerimiento Feature #651: Levantamiento de requerimiento

Project: Grupo I
Status: New
Start date: 08/27/2019
Due date: 09/03/2019
Assignee: Javier Rojas Butrón
Priority: Normal
Feature #857: Diseño de la maqueta (model... Feature #857: Diseño de la maqueta (modelo fisico)

Project: Grupo I
Status: New
Start date: 08/27/2019
Due date: 09/03/2019
Assignee: Llosect Moscoso
Priority: Normal
Feature #858: Analisis tratamiento de los... Feature #858: Analisis tratamiento de los riesgos

Project: Grupo I
Status: New
Start date: 08/20/2019
Due date: 09/03/2019
Assignee: Rodrigo González
Priority: Normal
Feature #861: Realización del informe 1 (... Feature #861: Realización del informe 1 (estructura de la maqueta)

Project: Grupo I
Status: New
Start date: 09/03/2019
Due date: 09/10/2019
Assignee: Llosect Moscoso
Priority: Normal

4

5

6

7

37

8

9

10

Feature #861: Realización del informe 1 (... Feature #861: Realización del informe 1 (estructura de la maqueta)

Project: Grupo I
Status: New
Start date: 09/03/2019
Due date: 09/10/2019
Assignee: Llosect Moscoso
Priority: Normal
Feature #859: Induccion sobre la hidroponia Feature #859: Induccion sobre la hidroponia

Project: Grupo I
Status: Resolved
Start date: 09/10/2019
Due date: 09/24/2019
Assignee:
Priority: Normal

11

12

13

14

38

15

16

17

18

19

20

21

39

22

23

24

Feature #859: Induccion sobre la hidroponia Feature #859: Induccion sobre la hidroponia

Project: Grupo I
Status: Resolved
Start date: 09/10/2019
Due date: 09/24/2019
Assignee:
Priority: Normal

25

26

27

28

40

29

30

1

Feature #656: Implementacion(programación... Feature #656: Implementacion(programación) del sistema hidroponico

Project: Grupo I
Status: New
Start date: 10/01/2019
Due date: 10/29/2019
Assignee: Rodrigo González
Priority: Normal
Feature #860: Induccion sobre el Controla... Feature #860: Induccion sobre el Controlador(Rasberry pi)

Project: Grupo I
Status: New
Start date: 10/01/2019
Due date: 10/15/2019
Assignee:
Priority: Normal