Project

General

Profile

Calendar

Filters

« October | December »

Apply Clear

SundayMondayTuesdayWednesdayThursdayFridaySaturday
44

26

27

28

29

30

Feature #5967: Entrega de entregables Feature #5967: Entrega de entregables

Project: GRUPO 7
Status: New
Start date: 10/30/2025
Due date: 12/29/2025
Assignee:
Priority: Normal

31

Feature #5945: PLANIFICACIÓN Y DISEÑO INICIAL Feature #5945: PLANIFICACIÓN Y DISEÑO INICIAL

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date: 10/31/2025
Assignee:
Priority: Normal
Feature #5947: Investigación del kit Lego ... Feature #5947: Investigación del kit Lego Spike Prime

Project: GRUPO 7
Status: New
Start date: 10/02/2025
Due date: 10/31/2025
Assignee:
Priority: Normal
Feature #5957: Programación de movimientos... Feature #5957: Programación de movimientos básicos y giros

Project: GRUPO 7
Status: New
Start date: 10/23/2025
Due date: 10/31/2025
Assignee:
Priority: Normal

1

45

2

3

4

5

6

7

8

46

9

10

11

12

13

14

15

47

16

17

18

19

20

Feature #5949: DISEÑO DE PISTA DE OBSTÁCULOS Feature #5949: DISEÑO DE PISTA DE OBSTÁCULOS

Project: GRUPO 7
Status: New
Start date: 11/20/2025
Due date: 12/26/2025
Assignee:
Priority: Normal
Feature #5966: Preparación de presentación Feature #5966: Preparación de presentación

Project: GRUPO 7
Status: New
Start date: 11/20/2025
Due date: 12/30/2025
Assignee:
Priority: Normal
Feature #5999: Imprimir diseños de los obs... Feature #5999: Imprimir diseños de los obstáculos

Project: GRUPO 7
Status: New
Start date: 11/20/2025
Due date: 12/19/2025
Assignee:
Priority: Normal

21

22

48

23

24

25

26

27

Feature #6014: Diseño de pista de Obstaculos Feature #6014: Diseño de pista de Obstaculos

Project: GRUPO 7
Status: New
Start date: 11/27/2025
Due date: 11/28/2025
Assignee: Brandon Quispe
Priority: Normal

28

Feature #6014: Diseño de pista de Obstaculos Feature #6014: Diseño de pista de Obstaculos

Project: GRUPO 7
Status: New
Start date: 11/27/2025
Due date: 11/28/2025
Assignee: Brandon Quispe
Priority: Normal

29

49

30

1

2

3

4

Feature #6015: Crear los materiales de la ... Feature #6015: Crear los materiales de la pista de obstáculos.

Project: GRUPO 7
Status: New
Start date: 12/04/2025
Due date: 12/19/2025
Assignee: Brandon Quispe
Priority: Normal

5

Feature #5997: Conexion del Hub a Interfaz Feature #5997: Conexion del Hub a Interfaz

Project: GRUPO 7
Status: New
Start date: 10/24/2025
Due date: 12/05/2025
Assignee:
Priority: Normal
Feature #6006: Funcionamiento de la interfaz Feature #6006: Funcionamiento de la interfaz

Project: GRUPO 7
Status: New
Start date: 12/05/2025
Due date: 12/25/2025
Assignee:
Priority: Normal
Feature #6007: Establecimiento de funcion... Feature #6007: Establecimiento de funciones de movimiento faltantes

Project: GRUPO 7
Status: New
Start date: 12/05/2025
Due date: 12/18/2025
Assignee:
Priority: Normal
Feature #6009: Implementación de sistema d... Feature #6009: Implementación de sistema de instrucciones mediante socket stream

Project: GRUPO 7
Status: New
Start date: 12/05/2025
Due date: 12/20/2025
Assignee:
Priority: Normal

6

issue beginning this day issue ending this day issue beginning and ending this day