Feature #697: 4.1 Programación de la pinza. Feature #697: 4.1 Programación de la pinza.

Project: Grupo 5 2019
Status: Resolved
Start date: 08/27/2019
Due date: 09/03/2019
Assignee: Patricio Gutierrez
Priority: Normal
Feature #821: 4.2 Unión de movimientos Feature #821: 4.2 Unión de movimientos

Project: Grupo 5 2019
Status: Resolved
Start date: 08/29/2019
Due date: 09/03/2019
Assignee: Marco Chayo
Priority: Normal
Feature #824: 2.2 Carta Gantt Feature #824: 2.2 Carta Gantt

Project: Grupo 5 2019
Status: Resolved
Start date: 08/27/2019
Due date: 09/03/2019
Assignee: Sebastian Torres
Priority: Normal
Feature #695: 3.4 Probar movimientos bási... Feature #695: 3.4 Probar movimientos básicos.

Project: Grupo 5 2019
Status: Resolved
Start date: 09/03/2019
Due date: 09/05/2019
Assignee: Adolfo Navea
Priority: Normal

4

Feature #829: 2.4 Power Point de formulac... Feature #829: 2.4 Power Point de formulación de proyecto

Project: Grupo 5 2019
Status: Resolved
Start date: 08/29/2019
Due date: 09/04/2019
Assignee: Sebastian Torres
Priority: Normal

5

Feature #685: 3. Programar e implementar ... Feature #685: 3. Programar e implementar movimientos básicos.

Project: Grupo 5 2019
Status: Resolved
Start date: 08/27/2019
Due date: 09/05/2019
Assignee: Marco Chayo
Priority: Normal
Feature #693: 3.3 Código base. Feature #693: 3.3 Código base.

Project: Grupo 5 2019
Status: Resolved
Start date: 08/29/2019
Due date: 09/05/2019
Assignee: Patricio Gutierrez
Priority: Normal
Feature #695: 3.4 Probar movimientos bási... Feature #695: 3.4 Probar movimientos básicos.

Project: Grupo 5 2019
Status: Resolved
Start date: 09/03/2019
Due date: 09/05/2019
Assignee: Adolfo Navea
Priority: Normal
Feature #825: 2.3 Informe de formulación ... Feature #825: 2.3 Informe de formulación de proyecto

Project: Grupo 5 2019
Status: Resolved
Start date: 08/27/2019
Due date: 09/05/2019
Assignee: Katia Layi
Priority: Normal

6

7

37

8

9

10

11

12

Feature #823: 4.3 Prueba de todos los mov... Feature #823: 4.3 Prueba de todos los movimientos.

Project: Grupo 5 2019
Status: Resolved
Start date: 08/29/2019
Due date: 09/12/2019
Assignee: Patricio Gutierrez
Priority: Normal

13

14

38

15

16

17

Feature #828: 2.5 Informe de avance Feature #828: 2.5 Informe de avance

Project: Grupo 5 2019
Status: Resolved
Start date: 09/17/2019
Due date: 10/17/2019
Assignee: Katia Layi
Priority: Normal
Feature #862: 2.6 Presentación de avance ... Feature #862: 2.6 Presentación de avance del proyecto

Project: Grupo 5 2019
Status: Resolved
Start date: 09/17/2019
Due date: 10/17/2019
Assignee: Sebastian Torres
Priority: Normal

18

19

20

21

39

22

23

24

Feature #867: 4.4 Interfaz gráfica Feature #867: 4.4 Interfaz gráfica

Project: Grupo 5 2019
Status: In Progress
Start date: 09/24/2019
Due date: 10/17/2019
Assignee: Marco Chayo
Priority: Normal

25

26

27

28

40

29

30

1

2

3

4

5

issue beginning this day issue ending this day issue beginning and ending this day