Calendar
Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday | |
---|---|---|---|---|---|---|---|
31 |
30 |
31 |
1 |
2 |
3 |
4 |
5 |
32 |
6 |
7 |
8 |
9 |
10
Feature #2392: Documentación
Feature #2392: Documentación
Project: GRUPO 5 B 2023 Status: In Progress Start date: 08/10/2023 Due date: 12/29/2023 Assignee: Alvaro Guarachi Priority: Normal
Support #2747: Fotos y videos
Support #2747: Fotos y videos
Project: GRUPO 5 B 2023 Status: New Start date: 08/10/2023 Due date: 12/29/2023 Assignee: Alvaro Guarachi Priority: Normal
Support #3465: Bitácoras
Support #3465: Bitácoras
Project: GRUPO 5 B 2023 Status: New Start date: 08/10/2023 Due date: 12/29/2023 Assignee: Matias Suazo Priority: Normal |
11
Support #2481: Designación de roles
Support #2481: Designación de roles
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/11/2023 Due date: 08/11/2023 Assignee: Alvaro Guarachi Priority: Normal
Feature #2480: Organización y estatus
Feature #2480: Organización y estatus
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/11/2023 Due date: 08/18/2023 Assignee: Alvaro Guarachi Priority: Normal
Feature #2496: Fase 1
Feature #2496: Fase 1
Project: GRUPO 5 B 2023 Status: In Progress Start date: 08/11/2023 Due date: 09/15/2023 Assignee: Priority: Normal
Support #2749: Wiki
Support #2749: Wiki
Project: GRUPO 5 B 2023 Status: New Start date: 08/11/2023 Due date: 12/29/2023 Assignee: Cristofer Pinto Priority: Normal |
12 |
33 |
13 |
14 |
15 |
16 |
17
Support #2750: Carta Gantt
Support #2750: Carta Gantt
Project: GRUPO 5 B 2023 Status: New Start date: 08/17/2023 Due date: 08/31/2023 Assignee: Alvaro Guarachi Priority: Normal |
18
Feature #2480: Organización y estatus
Feature #2480: Organización y estatus
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/11/2023 Due date: 08/18/2023 Assignee: Alvaro Guarachi Priority: Normal
Support #2746: Nombre del proyecto
Support #2746: Nombre del proyecto
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/18/2023 Due date: 08/18/2023 Assignee: Priority: Normal
Feature #2482: Diseño de robot
Feature #2482: Diseño de robot
Project: GRUPO 5 B 2023 Status: In Progress Start date: 08/18/2023 Due date: 08/31/2023 Assignee: Cristofer Pinto Priority: Normal
Support #2489: Diseño base
Support #2489: Diseño base
Project: GRUPO 5 B 2023 Status: New Start date: 08/18/2023 Due date: 08/25/2023 Assignee: Cristofer Pinto Priority: Normal |
19 |
34 |
20 |
21 |
22
Support #2491: Designación de memoria
Support #2491: Designación de memoria
Project: GRUPO 5 B 2023 Status: New Start date: 08/22/2023 Due date: 08/22/2023 Assignee: Nelson Ramirez Priority: Normal
Support #2492: Instalación de Sistema Oper...
Support #2492: Instalación de Sistema Operativo
Project: GRUPO 5 B 2023 Status: New Start date: 08/22/2023 Due date: 08/22/2023 Assignee: Nelson Ramirez Priority: Normal
Feature #2483: Armado del robot
Feature #2483: Armado del robot
Project: GRUPO 5 B 2023 Status: In Progress Start date: 08/22/2023 Due date: 08/31/2023 Assignee: Jose Escalante Priority: Normal
Support #2485: Chequeo de piezas
Support #2485: Chequeo de piezas
Project: GRUPO 5 B 2023 Status: New Start date: 08/22/2023 Due date: 08/24/2023 Assignee: Matias Suazo Priority: Normal |
23 |
24
Support #2485: Chequeo de piezas
Support #2485: Chequeo de piezas
Project: GRUPO 5 B 2023 Status: New Start date: 08/22/2023 Due date: 08/24/2023 Assignee: Matias Suazo Priority: Normal |
25
Support #2486: Armado de prueba
Support #2486: Armado de prueba
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/25/2023 Due date: 08/25/2023 Assignee: Jose Escalante Priority: Normal
Support #2489: Diseño base
Support #2489: Diseño base
Project: GRUPO 5 B 2023 Status: New Start date: 08/18/2023 Due date: 08/25/2023 Assignee: Cristofer Pinto Priority: Normal
Support #2487: Construcción Final
Support #2487: Construcción Final
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/25/2023 Due date: 08/31/2023 Assignee: Priority: Normal
Support #2490: Diseño definitivo
Support #2490: Diseño definitivo
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/25/2023 Due date: 08/31/2023 Assignee: Alvaro Guarachi Priority: Normal |
26 |
35 |
27 |
28 |
29 |
30 |
31
Feature #2482: Diseño de robot
Feature #2482: Diseño de robot
Project: GRUPO 5 B 2023 Status: In Progress Start date: 08/18/2023 Due date: 08/31/2023 Assignee: Cristofer Pinto Priority: Normal
Feature #2483: Armado del robot
Feature #2483: Armado del robot
Project: GRUPO 5 B 2023 Status: In Progress Start date: 08/22/2023 Due date: 08/31/2023 Assignee: Jose Escalante Priority: Normal
Support #2487: Construcción Final
Support #2487: Construcción Final
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/25/2023 Due date: 08/31/2023 Assignee: Priority: Normal
Feature #2488: Diseño de logo
Feature #2488: Diseño de logo
Project: GRUPO 5 B 2023 Status: New Start date: 08/31/2023 Due date: 08/31/2023 Assignee: Matias Suazo Priority: Normal
Support #2490: Diseño definitivo
Support #2490: Diseño definitivo
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/25/2023 Due date: 08/31/2023 Assignee: Alvaro Guarachi Priority: Normal
Support #2750: Carta Gantt
Support #2750: Carta Gantt
Project: GRUPO 5 B 2023 Status: New Start date: 08/17/2023 Due date: 08/31/2023 Assignee: Alvaro Guarachi Priority: Normal |
1
Support #2744: Informe I
Support #2744: Informe I
Project: GRUPO 5 B 2023 Status: New Start date: 09/01/2023 Due date: 09/15/2023 Assignee: Priority: Normal
Support #2745: Presentación 1
Support #2745: Presentación 1
Project: GRUPO 5 B 2023 Status: New Start date: 09/01/2023 Due date: 09/15/2023 Assignee: Priority: Normal |