Feature #54: Planteamiento del Problema Feature #54: Planteamiento del Problema

Project: Grupo 4
Status: New
Start date: 08/15/2017
Due date: 08/17/2017
Assignee: Jose Vasquez
Priority: High
Feature #66: Documentación del Proyecto Feature #66: Documentación del Proyecto

Project: Grupo 4
Status: New
Start date: 08/15/2017
Due date: 11/30/2017
Assignee: Gonzalo Vega
Priority: Normal
Support #114: Bitácoras semanales Support #114: Bitácoras semanales

Project: Grupo 4
Status: New
Start date: 08/15/2017
Due date: 11/30/2017
Assignee: Gonzalo Vega
Priority: Normal

16

17

Feature #54: Planteamiento del Problema Feature #54: Planteamiento del Problema

Project: Grupo 4
Status: New
Start date: 08/15/2017
Due date: 08/17/2017
Assignee: Jose Vasquez
Priority: High
Support #57: Adquirir las Piezas del Robot Support #57: Adquirir las Piezas del Robot

Project: Grupo 4
Status: New
Start date: 08/17/2017
Due date: 08/31/2017
Assignee: Matías Aguayo
Priority: Normal
Feature #59: Ensamblado del Robot Feature #59: Ensamblado del Robot

Project: Grupo 4
Status: New
Start date: 08/17/2017
Due date: 09/07/2017
Assignee: Matías Aguayo
Priority: Normal

18

19

34

20

21

22

23

24

Feature #98: Armar el robot básico Feature #98: Armar el robot básico

Project: Grupo 4
Status: New
Start date: 08/24/2017
Due date: 09/07/2017
Assignee: Matías Aguayo
Priority: Normal

25

26

35

27

28

29

30

31

Support #57: Adquirir las Piezas del Robot Support #57: Adquirir las Piezas del Robot

Project: Grupo 4
Status: New
Start date: 08/17/2017
Due date: 08/31/2017
Assignee: Matías Aguayo