36

1

Feature #4250: Desarrollo modelado 3D Feature #4250: Desarrollo modelado 3D

Project: Grupo 3B-2024
Status: New
Start date: 08/26/2024
Due date: 09/01/2024
Assignee:
Priority: Normal

2

Feature #4249: Presentación I - Solución d... Feature #4249: Presentación I - Solución del problema

Project: Grupo 3B-2024
Status: New
Start date: 09/02/2024
Due date: 09/08/2024
Assignee:
Priority: Normal

3

4

5

6

7

37

8

Feature #4249: Presentación I - Solución d... Feature #4249: Presentación I - Solución del problema

Project: Grupo 3B-2024
Status: New
Start date: 09/02/2024
Due date: 09/08/2024
Assignee:
Priority: Normal

9

Feature #4251: Desarrollo Informe I Feature #4251: Desarrollo Informe I

Project: Grupo 3B-2024
Status: New
Start date: 09/09/2024
Due date: 10/01/2024
Assignee:
Priority: Normal

10

11

12

13

14

38

15

16

17

18

19

20

21

39

22

23

24

Feature #4430: Desarrollo Presentación Inf... Feature #4430: Desarrollo Presentación Informe I

Project: Grupo 3B-2024
Status: New
Start date: 09/24/2024
Due date: 10/01/2024
Assignee:
Priority: Normal

25

26

27

28

40

29

30

1

Feature #4247: Fase I - Planificación del ... Feature #4247: Fase I - Planificación del Proyecto

Project: Grupo 3B-2024
Status: New
Start date: 08/12/2024
Due date: 10/01/2024
Assignee:
Priority: Normal
Feature #4251: Desarrollo Informe I Feature #4251: Desarrollo Informe I

Project: Grupo 3B-2024
Status: New
Start date: 09/09/2024
Due date: 10/01/2024
Assignee:
Priority: Normal
Feature #4430: Desarrollo Presentación Inf... Feature #4430: Desarrollo Presentación Informe I

Project: Grupo 3B-2024
Status: New
Start date: 09/24/2024
Due date: 10/01/2024