Calendar
Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday | |
---|---|---|---|---|---|---|---|
39 |
25 |
26 |
27
Feature #2096: Informe N°2
Feature #2096: Informe N°2
Project: Grupo 3 B 2022 Status: New Start date: 09/27/2022 Due date: 10/13/2022 Assignee: felipe guzman Priority: Normal |
28 |
29 |
30 |
1 |
40 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
41 |
9 |
10 |
11 |
12 |
13
Feature #2096: Informe N°2
Feature #2096: Informe N°2
Project: Grupo 3 B 2022 Status: New Start date: 09/27/2022 Due date: 10/13/2022 Assignee: felipe guzman Priority: Normal
Feature #2243: Diseño Interfaz EV3
Feature #2243: Diseño Interfaz EV3
Project: Grupo 3 B 2022 Status: New Start date: 10/13/2022 Due date: 11/03/2022 Assignee: felipe guzman Priority: Normal |
14 |
15 |
42 |
16 |
17 |
18
Feature #2245: Programación del Robot
Feature #2245: Programación del Robot
Project: Grupo 3 B 2022 Status: New Start date: 10/18/2022 Due date: 10/25/2022 Assignee: felipe guzman Priority: Normal
Feature #2246: Conexión del Robot EV3
Feature #2246: Conexión del Robot EV3
Project: Grupo 3 B 2022 Status: New Start date: 10/18/2022 Due date: 10/25/2022 Assignee: felipe guzman Priority: Normal |
19 |
20 |
21 |
22 |
43 |
23 |
24 |
25
Feature #2245: Programación del Robot
Feature #2245: Programación del Robot
Project: Grupo 3 B 2022 Status: New Start date: 10/18/2022 Due date: 10/25/2022 Assignee: felipe guzman Priority: Normal
Feature #2246: Conexión del Robot EV3
Feature #2246: Conexión del Robot EV3
Project: Grupo 3 B 2022 Status: New Start date: 10/18/2022 Due date: 10/25/2022 Assignee: felipe guzman Priority: Normal
Feature #2248: Pruebas de conexión
Feature #2248: Pruebas de conexión
Project: Grupo 3 B 2022 Status: New Start date: 10/25/2022 Due date: 10/25/2022 Assignee: felipe guzman Priority: Normal
Feature #2242: Wiki
Feature #2242: Wiki
Project: Grupo 3 B 2022 Status: New Start date: 10/25/2022 Due date: 11/01/2022 Assignee: felipe guzman Priority: Normal |
26 |
27 |
28 |
29 |
44 |
30 |
31 |
1
Feature #2242: Wiki
Feature #2242: Wiki
Project: Grupo 3 B 2022 Status: New Start date: 10/25/2022 Due date: 11/01/2022 Assignee: felipe guzman Priority: Normal |
2 |
3
Feature #2243: Diseño Interfaz EV3
Feature #2243: Diseño Interfaz EV3
Project: Grupo 3 B 2022 Status: New Start date: 10/13/2022 Due date: 11/03/2022 Assignee: felipe guzman Priority: Normal
Support #2244: Presentación N°2
Support #2244: Presentación N°2
Project: Grupo 3 B 2022 Status: New Start date: 11/03/2022 Due date: 11/03/2022 Assignee: Priority: Normal |
4 |
5 |
issue beginning this day issue ending this day issue beginning and ending this day