44

28

29

30

Feature #554: investigar e implementar mé... Feature #554: investigar e implementar métodos de armado para el cubo de Rubik.

Project: Grupo 3 2018
Status: New
Start date: 10/30/2018
Due date: 11/22/2018
Assignee:
Priority: Normal

31

1

2

3

45

4

5

6

Feature #545: Investigar plataforma para ... Feature #545: Investigar plataforma para el envió de comandos al brick EV3.

Project: Grupo 3 2018
Status: New
Start date: 10/18/2018
Due date: 11/06/2018
Assignee: Nicolas Colque
Priority: Normal
Feature #547: Programación de la interfaz... Feature #547: Programación de la interfaz de usuario.

Project: Grupo 3 2018
Status: New
Start date: 11/06/2018
Due date: 11/27/2018
Assignee: Pedro Araya
Priority: Normal

7

8

9

10

46

11

12

13

14

15

Support #379: Desarrollo de la wiki Support #379: Desarrollo de la wiki

Project: Grupo 3 2018
Status: In Progress
Start date: 08/30/2018
Due date: 11/15/2018
Assignee: Pedro Araya
Priority: Normal

16

17

47

18

19

20

Feature #550: Estudiar los patrones de mo... Feature #550: Estudiar los patrones de movimientos de Cubo Rubik.

Project: Grupo 3 2018
Status: New
Start date: 10/09/2018
Due date: 11/20/2018
Assignee:
Priority: Normal

21

22

Feature #383: Avance 1 + Corrección Feature #383: Avance 1 + Corrección

Project: Grupo 3 2018
Status: New
Start date: 09/27/2018
Due date: 11/22/2018
Assignee: Gabriel Echeverria
Priority: Normal
Feature #391: Programación del Brick Ev3 Feature #391: Programación del Brick Ev3

Project: Grupo 3 2018
Status: In Progress
Start date: 08/30/2018
Due date: 11/22/2018
Assignee: Nicolas Colque
Priority: Normal
Feature #554: investigar e implementar mé... Feature #554: investigar e implementar métodos de armado para el cubo de Rubik.

Project: Grupo 3 2018
Status: New
Start date: 10/30/2018
Due date: 11/22/2018
Assignee:
Priority: Normal
Support #404: Informe Final Support #404: Informe Final

Project: Grupo 3 2018
Status: New
Start date: 11/22/2018
Due date: 12/06/2018
Assignee:
Priority: Normal

23

24

48

25

26

27

Feature #396: Programación de la interfa... Feature #396: Programación de la interfaz de usuario.

Project: Grupo 3 2018
Status: New
Start date: 10/09/2018
Due date: 11/27/2018
Assignee: Pedro Araya
Priority: Normal
Feature #547: Programación de la interfaz... Feature #547: Programación de la interfaz de usuario.

Project: Grupo 3 2018
Status: New
Start date: 11/06/2018
Due date: 11/27/2018
Assignee: Pedro Araya
Priority: Normal

28

29

Feature #380: Bitácora (semanal) Feature #380: Bitácora (semanal)

Project: Grupo 3 2018
Status: In Progress
Start date: 08/16/2018
Due date: 11/29/2018
Assignee: Gabriel Echeverria
Priority: Normal

30

1