Feature #206: Organización Proyecto
Feature #206: Organización Proyecto
Project: Grupo 2 2018 Status: Resolved Start date: 08/16/2018 Due date: 08/16/2018 Assignee: Matias Sandoval Priority: Normal
Feature #205: Desarrollo Del Proyecto
Feature #205: Desarrollo Del Proyecto
Project: Grupo 2 2018 Status: In Progress Start date: 08/16/2018 Due date: 12/07/2018 Assignee: Matias Sandoval Priority: Normal |
17 |
18 |
34 |
19 |
20 |
21
Feature #208: Contabilizar Piezas Del Robot
Feature #208: Contabilizar Piezas Del Robot
Project: Grupo 2 2018 Status: Resolved Start date: 08/21/2018 Due date: 08/21/2018 Assignee: Luis Soto Priority: Normal
Feature #207: Proyecto: Parte 1
Feature #207: Proyecto: Parte 1
Project: Grupo 2 2018 Status: Resolved Start date: 08/21/2018 Due date: 08/23/2018 Assignee: Matias Sandoval Priority: Normal
Feature #209: Armar Robot
Feature #209: Armar Robot
Project: Grupo 2 2018 Status: Resolved Start date: 08/21/2018 Due date: 08/23/2018 Assignee: José Ignacio Le Blanc Priority: Normal
Feature #210: Instalar S.O en la SD.
Feature #210: Instalar S.O en la SD.
Project: Grupo 2 2018 Status: Resolved Start date: 08/21/2018 Due date: 08/23/2018 Assignee: Nicolas Jorquera Priority: Normal |
22 |
23
Feature #207: Proyecto: Parte 1
Feature #207: Proyecto: Parte 1
Project: Grupo 2 2018 Status: Resolved Start date: 08/21/2018 Due date: 08/23/2018 Assignee: Matias Sandoval Priority: Normal
Feature #209: Armar Robot
Feature #209: Armar Robot
Project: Grupo 2 2018 Status: Resolved Start date: 08/21/2018 Due date: 08/23/2018 Assignee: José Ignacio Le Blanc Priority: Normal
Feature #210: Instalar S.O en la SD.
Feature #210: Instalar S.O en la SD.
Project: Grupo 2 2018 Status: Resolved Start date: 08/21/2018 Due date: 08/23/2018 Assignee: Nicolas Jorquera Priority: Normal
Feature #238: Proyecto: Parte 2
Feature #238: Proyecto: Parte 2
Project: Grupo 2 2018 Status: In Progress Start date: 08/23/2018 Due date: 09/06/2018 Assignee: Matias Sandoval Priority: Normal
Feature #239: Estudiar Algoritmos Cubo
Feature #239: Estudiar Algoritmos Cubo
Project: Grupo 2 2018 Status: In Progress Start date: 08/23/2018 Due date: 09/04/2018 Assignee: Matias Sandoval Priority: Normal
Feature #240: Pruebas Estructura Robot
Feature #240: Pruebas Estructura Robot
Project: Grupo 2 2018 Status: In Progress Start date: 08/23/2018 Due date: 09/04/2018 Assignee: Nicolas Jorquera Priority: Normal
Feature #241: Ampliar Conocimiento Python
Feature #241: Ampliar Conocimiento Python
Project: Grupo 2 2018 Status: In Progress Start date: 08/23/2018 Due date: 09/06/2018 Assignee: José Ignacio Le Blanc Priority: Normal
Feature #242: Ideas Previas Aplicación
Feature #242: Ideas Previas Aplicación
Project: Grupo 2 2018 Status: In Progress Start date: 08/23/2018 Due date: 09/06/2018 Assignee: Luis Soto Priority: Normal
Feature #256: Proyecto: Parte 3
Feature #256: Proyecto: Parte 3
Project: Grupo 2 2018 Status: In Progress Start date: 08/23/2018 Due date: 09/11/2018 Assignee: Matias Sandoval Priority: Normal
Feature #267: Formulación de Proyecto
Feature #267: Formulación de Proyecto
Project: Grupo 2 2018 Status: In Progress Start date: 08/23/2018 Due date: 09/03/2018 Assignee: Matias Sandoval Priority: Normal |
24 |
25 |
35 |
26 |
27 |
28 |
29 |
30
Feature #262: Realizar Presentación
Feature #262: Realizar Presentación
Project: Grupo 2 2018 Status: New Start date: 08/30/2018 Due date: 09/06/2018 Assignee: Matias Sandoval Priority: Normal |