36

1

2

Feature #4359: Definición de Problema y So... Feature #4359: Definición de Problema y Solución del Proyecto

Project: FacOdon-2
Status: Resolved
Start date: 08/19/2024
Due date: 09/02/2024
Assignee: Jack Torres
Priority: Normal
Feature #4360: Definición de Requerimiento... Feature #4360: Definición de Requerimientos del Sistema

Project: FacOdon-2
Status: Resolved
Start date: 08/26/2024
Due date: 09/02/2024
Assignee: Jack Torres
Priority: Normal
Feature #4366: Diseñar Modelo de Contexto Feature #4366: Diseñar Modelo de Contexto

Project: FacOdon-2
Status: Resolved
Start date: 09/02/2024
Due date: 09/16/2024
Assignee: Jack Torres
Priority: Normal

3

4

5

6

7

37

8

9

Feature #4367: Diseñar Diagrama de Caso de... Feature #4367: Diseñar Diagrama de Caso de Uso

Project: FacOdon-2
Status: Resolved
Start date: 09/09/2024
Due date: 09/30/2024
Assignee: Jack Torres
Priority: Normal

10

11

12

13

14

38

15

16

Feature #4366: Diseñar Modelo de Contexto Feature #4366: Diseñar Modelo de Contexto

Project: FacOdon-2
Status: Resolved
Start date: 09/02/2024
Due date: 09/16/2024
Assignee: Jack Torres
Priority: Normal

17

18

19

20

21

39

22

23

Feature #4369: Seleccionar Herramientas Feature #4369: Seleccionar Herramientas

Project: FacOdon-2
Status: Resolved
Start date: 09/23/2024
Due date: 09/30/2024
Assignee: Jack Torres
Priority: Normal

24

25

26

27

28

40

29

Feature #4371: Desarrollar BPMN de los pro... Feature #4371: Desarrollar BPMN de los procesos

Project: FacOdon-2
Status: Resolved
Start date: 09/29/2024
Due date: 09/30/2024
Assignee: Jack Torres
Priority: Normal

30

Feature #4367: Diseñar Diagrama de Caso de... Feature #4367: Diseñar Diagrama de Caso de Uso

Project: FacOdon-2
Status: Resolved
Start date: 09/09/2024
Due date: 09/30/2024
Assignee: Jack Torres
Priority: Normal
Feature #4369: Seleccionar Herramientas Feature #4369: Seleccionar Herramientas

Project: FacOdon-2
Status: Resolved
Start date: 09/23/2024
Due date: 09/30/2024
Assignee: Jack Torres
Priority: Normal
Feature #4371: Desarrollar BPMN de los pro... Feature #4371: Desarrollar BPMN de los procesos

Project: FacOdon-2
Status: Resolved
Start date: 09/29/2024
Due date: 09/30/2024
Assignee: Jack Torres
Priority: Normal
Feature #4377: Informe de Avance 1 Feature #4377: Informe de Avance 1

Project: FacOdon-2
Status: Resolved
Start date: 08/19/2024
Due date: 09/30/2024
Assignee: Jack Torres
Priority: Normal
Feature #4370: Desarrollar Prototipos Feature #4370: Desarrollar Prototipos

Project: FacOdon-2
Status: Resolved
Start date: 09/30/2024
Due date: 10/07/2024
Assignee: Jack Torres
Priority: Normal
Feature #4378: Informe de Avance 2 Feature #4378: Informe de Avance 2

Project: FacOdon-2
Status: Resolved
Start date: 09/30/2024
Due date: 10/13/2024
Assignee: Jack Torres