35 |
27
GRUPO 2 B 2023 -
Bug #2725: Estudio de librerias
Bug #2725: Estudio de librerias
Project: GRUPO 2 B 2023 Status: New Start date: 08/14/2023 Due date: 08/27/2023 Assignee: Mario Villalobos Priority: Normal
Grupo P2-4 -
Feature #2427: Primeras ideas de Diseño
Feature #2427: Primeras ideas de Diseño
Project: Grupo P2-4 Status: New Start date: 08/21/2023 Due date: 08/27/2023 Assignee: Priority: Normal
GRUPO 1 A 2023 -
Feature #2851: Tareas
Feature #2851: Tareas
Project: GRUPO 1 A 2023 Status: New Start date: 08/16/2023 Due date: 08/27/2023 Assignee: Melisa Laura Priority: High
GRUPO 1 A 2023 -
Feature #2859: Replantear diseño y estruct...
Feature #2859: Replantear diseño y estructura de robot
Project: GRUPO 1 A 2023 Status: New Start date: 08/21/2023 Due date: 08/27/2023 Assignee: Melisa Laura Priority: High
GRUPO 1 A 2023 -
Feature #2866: Logo
Feature #2866: Logo
Project: GRUPO 1 A 2023 Status: New Start date: 08/21/2023 Due date: 08/27/2023 Assignee: Liliana Galvez Priority: Normal
GRUPO 1 A 2023 -
Feature #2877: Estudio de libreria EV3 y s...
Feature #2877: Estudio de libreria EV3 y sus funciones
Project: GRUPO 1 A 2023 Status: New Start date: 08/25/2023 Due date: 08/27/2023 Assignee: Cristian Huanca Priority: Normal
GRUPO 2 B 2023 -
Bug #2734: movimientos base
Bug #2734: movimientos base
Project: GRUPO 2 B 2023 Status: New Start date: 08/27/2023 Due date: 09/03/2023 Assignee: Sebastian Caceres Priority: Normal
GRUPO 2 B 2023 -
Bug #2738: Funciones por separado
Bug #2738: Funciones por separado
Project: GRUPO 2 B 2023 Status: New Start date: 08/27/2023 Due date: 09/10/2023 Assignee: Sebastian Caceres Priority: Normal
GRUPO 2 B 2023 -
Bug #2741: Wiki
Bug #2741: Wiki
Project: GRUPO 2 B 2023 Status: New Start date: 08/27/2023 Due date: 09/17/2023 Assignee: Kary Tudela Priority: Normal
GRUPO 2 B 2023 -
Bug #2742: Informe Uno
Bug #2742: Informe Uno
Project: GRUPO 2 B 2023 Status: New Start date: 08/27/2023 Due date: 09/10/2023 Assignee: Ruben Salas Priority: Normal
GRUPO 2 B 2023 -
Bug #2743: Presentación Uno
Bug #2743: Presentación Uno
Project: GRUPO 2 B 2023 Status: New Start date: 08/27/2023 Due date: 09/17/2023 Assignee: Ruben Salas Priority: Normal |
28
GRUPO 4 A 2023 -
Feature #3045: Estimacion de costo
Feature #3045: Estimacion de costo
Project: GRUPO 4 A 2023 Status: New Start date: 08/24/2023 Due date: 08/28/2023 Assignee: Sergio Rabanal Priority: Normal
Grupo P2-2 -
Bug #2433: Comprar / Adquirir materiales
Bug #2433: Comprar / Adquirir materiales
Project: Grupo P2-2 Status: New Start date: 08/28/2023 Due date: 09/01/2023 Assignee: Priority: Normal
Grupo P2-4 -
Feature #2429: Revisar el material y plani...
Feature #2429: Revisar el material y planificar una maqueta.
Project: Grupo P2-4 Status: New Start date: 08/28/2023 Due date: 09/03/2023 Assignee: Priority: Normal
Grupo P2-6 -
Feature #3067: Formulación y construcción ...
Feature #3067: Formulación y construcción de la maqueta del proyecto.
Project: Grupo P2-6 Status: New Start date: 08/28/2023 Due date: 09/05/2023 Assignee: Priority: Normal
GRUPO 1 A 2023 -
Feature #2875: Programación de funciones d...
Feature #2875: Programación de funciones del Robot (Prueba)
Project: GRUPO 1 A 2023 Status: New Start date: 08/28/2023 Due date: 09/01/2023 Assignee: byron santibanez Priority: Normal
GRUPO 3 A 2023 -
Feature #2542: Bitácora 3
Feature #2542: Bitácora 3
Project: GRUPO 3 A 2023 Status: New Start date: 08/28/2023 Due date: 09/03/2023 Assignee: Fabian Diaz Priority: Normal
GRUPO 3 A 2023 -
Feature #2832: Wiki
Feature #2832: Wiki
Project: GRUPO 3 A 2023 Status: New Start date: 08/28/2023 Due date: 12/29/2023 Assignee: Andrea Navia Priority: Normal |
29
GRUPO 1 B 2023 -
Feature #3302: Construcción del robot
Feature #3302: Construcción del robot
Project: GRUPO 1 B 2023 Status: New Start date: 08/22/2023 Due date: 08/29/2023 Assignee: Jorge Caceres Priority: Normal
GRUPO 3 B 2023 -
Feature #3033: Informe I
Feature #3033: Informe I
Project: GRUPO 3 B 2023 Status: New Start date: 08/29/2023 Due date: 09/14/2023 Assignee: denis condori Priority: Normal
GRUPO 4 B 2023 -
Feature #2420: Semana 4
Feature #2420: Semana 4
Project: GRUPO 4 B 2023 Status: New Start date: 08/29/2023 Due date: 09/01/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2531: Codificacion movimientos robot
Feature #2531: Codificacion movimientos robot
Project: GRUPO 4 B 2023 Status: New Start date: 08/29/2023 Due date: 09/01/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2572: Interfaz grafica robot
Feature #2572: Interfaz grafica robot
Project: GRUPO 4 B 2023 Status: New Start date: 08/29/2023 Due date: 09/01/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2573: mejorar wiki
Feature #2573: mejorar wiki
Project: GRUPO 4 B 2023 Status: New Start date: 08/29/2023 Due date: 09/01/2023 Assignee: Priority: Normal
Grupo P2-3 -
Feature #2825: seleccion de proyecto
Feature #2825: seleccion de proyecto
Project: Grupo P2-3 Status: New Start date: 08/29/2023 Due date: 08/30/2023 Assignee: Priority: Normal
Grupo P2-5 -
Feature #2452: Diseñar maqueta
Feature #2452: Diseñar maqueta
Project: Grupo P2-5 Status: New Start date: 08/29/2023 Due date: 08/31/2023 Assignee: luciano vera Priority: Normal |
30
Grupo P2-2 -
Bug #2578: Definir escenario y problem...
Bug #2578: Definir escenario y problema a solucionar
Project: Grupo P2-2 Status: New Start date: 08/23/2023 Due date: 08/30/2023 Assignee: Priority: Normal
Grupo P2-3 -
Feature #2825: seleccion de proyecto
Feature #2825: seleccion de proyecto
Project: Grupo P2-3 Status: New Start date: 08/29/2023 Due date: 08/30/2023 Assignee: Priority: Normal
Grupo P2-3 -
Feature #2826: presentación del proyecto a...
Feature #2826: presentación del proyecto al curso
Project: Grupo P2-3 Status: New Start date: 08/30/2023 Due date: 08/30/2023 Assignee: Priority: Normal
Grupo P2-2 -
Bug #2576: Confección y presentación d...
Bug #2576: Confección y presentación de maqueta
Project: Grupo P2-2 Status: New Start date: 08/30/2023 Due date: 09/06/2023 Assignee: Priority: Normal
GRUPO 1 A 2023 -
Feature #2878: Presentación 1
Feature #2878: Presentación 1
Project: GRUPO 1 A 2023 Status: New Start date: 08/30/2023 Due date: 09/08/2023 Assignee: Melisa Laura Priority: Normal
GRUPO 1 A 2023 -
Feature #2879: Asignación de partes de la ...
Feature #2879: Asignación de partes de la primera presentación
Project: GRUPO 1 A 2023 Status: New Start date: 08/30/2023 Due date: 09/01/2023 Assignee: Melisa Laura Priority: Normal |
31
GRUPO 5 B 2023 -
Feature #2482: Diseño de robot
Feature #2482: Diseño de robot
Project: GRUPO 5 B 2023 Status: In Progress Start date: 08/18/2023 Due date: 08/31/2023 Assignee: Cristofer Pinto Priority: Normal
GRUPO 5 B 2023 -
Feature #2483: Armado del robot
Feature #2483: Armado del robot
Project: GRUPO 5 B 2023 Status: In Progress Start date: 08/22/2023 Due date: 08/31/2023 Assignee: Jose Escalante Priority: Normal
GRUPO 5 B 2023 -
Feature #2488: Diseño de logo
Feature #2488: Diseño de logo
Project: GRUPO 5 B 2023 Status: New Start date: 08/31/2023 Due date: 08/31/2023 Assignee: Matias Suazo Priority: Normal
Grupo P2-5 -
Feature #2452: Diseñar maqueta
Feature #2452: Diseñar maqueta
Project: Grupo P2-5 Status: New Start date: 08/29/2023 Due date: 08/31/2023 Assignee: luciano vera Priority: Normal
GRUPO 5 B 2023 -
Support #2487: Construcción Final
Support #2487: Construcción Final
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/25/2023 Due date: 08/31/2023 Assignee: Priority: Normal
GRUPO 5 B 2023 -
Support #2490: Diseño definitivo
Support #2490: Diseño definitivo
Project: GRUPO 5 B 2023 Status: Resolved Start date: 08/25/2023 Due date: 08/31/2023 Assignee: Alvaro Guarachi Priority: Normal
GRUPO 5 B 2023 -
Support #2750: Carta Gantt
Support #2750: Carta Gantt
Project: GRUPO 5 B 2023 Status: New Start date: 08/17/2023 Due date: 08/31/2023 Assignee: Alvaro Guarachi Priority: Normal
Grupo P2-2 -
Bug #2867: Elaboración de Bitácoras
Bug #2867: Elaboración de Bitácoras
Project: Grupo P2-2 Status: New Start date: 08/31/2023 Due date: 12/20/2023 Assignee: Priority: Normal
Grupo P2-3 -
Feature #2827: Confección de maqueta
Feature #2827: Confección de maqueta
Project: Grupo P2-3 Status: New Start date: 08/31/2023 Due date: 09/03/2023 Assignee: Priority: Normal |
1
Grupo P2-2 -
Bug #2433: Comprar / Adquirir materiales
Bug #2433: Comprar / Adquirir materiales
Project: Grupo P2-2 Status: New Start date: 08/28/2023 Due date: 09/01/2023 Assignee: Priority: Normal
GRUPO 3 B 2023 -
Feature #3373: Estimacion de Costos
Feature #3373: Estimacion de Costos
Project: GRUPO 3 B 2023 Status: New Start date: 09/01/2023 Due date: 09/01/2023 Assignee: Ignacio Gallardo Priority: Normal
GRUPO 4 B 2023 -
Feature #2420: Semana 4
Feature #2420: Semana 4
Project: GRUPO 4 B 2023 Status: New Start date: 08/29/2023 Due date: 09/01/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2531: Codificacion movimientos robot
Feature #2531: Codificacion movimientos robot
Project: GRUPO 4 B 2023 Status: New Start date: 08/29/2023 Due date: 09/01/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2572: Interfaz grafica robot
Feature #2572: Interfaz grafica robot
Project: GRUPO 4 B 2023 Status: New Start date: 08/29/2023 Due date: 09/01/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2573: mejorar wiki
Feature #2573: mejorar wiki
Project: GRUPO 4 B 2023 Status: New Start date: 08/29/2023 Due date: 09/01/2023 Assignee: Priority: Normal
GRUPO 1 A 2023 -
Feature #2873: Codificación
Feature #2873: Codificación
Project: GRUPO 1 A 2023 Status: New Start date: 08/22/2023 Due date: 09/01/2023 Assignee: byron santibanez Priority: Normal
GRUPO 1 A 2023 -
Feature #2875: Programación de funciones d...
Feature #2875: Programación de funciones del Robot (Prueba)
Project: GRUPO 1 A 2023 Status: New Start date: 08/28/2023 Due date: 09/01/2023 Assignee: byron santibanez Priority: Normal
GRUPO 1 A 2023 -
Feature #2879: Asignación de partes de la ...
Feature #2879: Asignación de partes de la primera presentación
Project: GRUPO 1 A 2023 Status: New Start date: 08/30/2023 Due date: 09/01/2023 Assignee: Melisa Laura Priority: Normal
GRUPO 2 A 2023 -
Feature #3123: Armado del Robot
Feature #3123: Armado del Robot
Project: GRUPO 2 A 2023 Status: Resolved Start date: 08/18/2023 Due date: 09/01/2023 Assignee: karen mamani Priority: Normal
GRUPO 3 A 2023 -
Feature #2998: Estudio del sistema operativo
Feature #2998: Estudio del sistema operativo
Project: GRUPO 3 A 2023 Status: New Start date: 08/25/2023 Due date: 09/01/2023 Assignee: Fabian Diaz Priority: Normal
GRUPO 4 A 2023 -
Feature #3062: Construcción del robot
Feature #3062: Construcción del robot
Project: GRUPO 4 A 2023 Status: New Start date: 08/16/2023 Due date: 09/01/2023 Assignee: Valentina Alvarez Priority: High
GRUPO 1 B 2023 -
Feature #3304: Informe I
Feature #3304: Informe I
Project: GRUPO 1 B 2023 Status: New Start date: 09/01/2023 Due date: 09/08/2023 Assignee: Katalina Oviedo Priority: Normal
Grupo P2-5 -
Feature #2453: Construir maqueta
Feature #2453: Construir maqueta
Project: Grupo P2-5 Status: New Start date: 09/01/2023 Due date: 09/05/2023 Assignee: luciano vera Priority: Normal
GRUPO 2 A 2023 -
Feature #3228: Parte II
Feature #3228: Parte II
Project: GRUPO 2 A 2023 Status: New Start date: 09/01/2023 Due date: 12/01/2023 Assignee: Priority: High
GRUPO 3 A 2023 -
Feature #2986: Programación del robot
Feature #2986: Programación del robot
Project: GRUPO 3 A 2023 Status: New Start date: 09/01/2023 Due date: 12/05/2023 Assignee: Priority: Normal
GRUPO 3 A 2023 -
Feature #2987: Programar movimientos del r...
Feature #2987: Programar movimientos del robot
Project: GRUPO 3 A 2023 Status: New Start date: 09/01/2023 Due date: 12/05/2023 Assignee: Fabian Diaz Priority: Normal
GRUPO 4 A 2023 -
Feature #3047: Presentacion I
Feature #3047: Presentacion I
Project: GRUPO 4 A 2023 Status: New Start date: 09/01/2023 Due date: 09/15/2023 Assignee: Sergio Rabanal Priority: High
Grupo P2-7-2 -
Feature #3101: Definicion del Proyecto
Feature #3101: Definicion del Proyecto
Project: Grupo P2-7-2 Status: Resolved Start date: 09/01/2023 Due date: 09/12/2023 Assignee: Priority: Normal
Grupo P2-7-2 -
Feature #3102: Crear la presentacion y maq...
Feature #3102: Crear la presentacion y maqueta
Project: Grupo P2-7-2 Status: New Start date: 09/01/2023 Due date: 09/12/2023 Assignee: Priority: Normal
GRUPO 5 B 2023 -
Support #2744: Informe I
Support #2744: Informe I
Project: GRUPO 5 B 2023 Status: New Start date: 09/01/2023 Due date: 09/15/2023 Assignee: Priority: Normal
GRUPO 5 B 2023 -
Support #2745: Presentación 1
Support #2745: Presentación 1
Project: GRUPO 5 B 2023 Status: New Start date: 09/01/2023 Due date: 09/15/2023 Assignee: Priority: Normal
GRUPO 2 A 2023 -
Support #3232: Desarrollo del código
Support #3232: Desarrollo del código
Project: GRUPO 2 A 2023 Status: New Start date: 09/01/2023 Due date: 10/03/2023 Assignee: Brian Lopez Priority: Normal
GRUPO 2 A 2023 -
Support #3235: Programación del movimiento...
Support #3235: Programación del movimiento del robot
Project: GRUPO 2 A 2023 Status: New Start date: 09/01/2023 Due date: 10/03/2023 Assignee: Brian Lopez Priority: Normal |
2
GRUPO 3 B 2023 -
Feature #3014: Pruebas con librerias ev3dev2
Feature #3014: Pruebas con librerias ev3dev2
Project: GRUPO 3 B 2023 Status: New Start date: 08/24/2023 Due date: 09/02/2023 Assignee: Ignacio Gallardo Priority: Normal
GRUPO 5 A 2023 -
Feature #2611: Creación de informe I
Feature #2611: Creación de informe I
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/02/2023 Due date: 09/14/2023 Assignee: Diego Ferrada Priority: Normal
GRUPO 5 A 2023 -
Feature #3437: Panorama General
Feature #3437: Panorama General
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/02/2023 Due date: 09/14/2023 Assignee: Javier Huanca Priority: Normal
GRUPO 5 A 2023 -
Feature #3438: Organizacion del Personal
Feature #3438: Organizacion del Personal
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/02/2023 Due date: 09/14/2023 Assignee: Javier Huanca Priority: Normal
GRUPO 5 A 2023 -
Feature #3439: Planificacion del Proyecto
Feature #3439: Planificacion del Proyecto
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/02/2023 Due date: 09/14/2023 Assignee: Javier Huanca Priority: Normal
GRUPO 5 A 2023 -
Feature #3440: Planificacion de los Recursos
Feature #3440: Planificacion de los Recursos
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/02/2023 Due date: 09/14/2023 Assignee: Javier Huanca Priority: Normal
GRUPO 2 A 2023 -
Support #3126: Realizar la Wiki
Support #3126: Realizar la Wiki
Project: GRUPO 2 A 2023 Status: In Progress Start date: 09/02/2023 Due date: 09/13/2023 Assignee: Angie Martinez Priority: Normal |
36 |
3
GRUPO 2 B 2023 -
Bug #2734: movimientos base
Bug #2734: movimientos base
Project: GRUPO 2 B 2023 Status: New Start date: 08/27/2023 Due date: 09/03/2023 Assignee: Sebastian Caceres Priority: Normal
Grupo P2-3 -
Feature #2827: Confección de maqueta
Feature #2827: Confección de maqueta
Project: Grupo P2-3 Status: New Start date: 08/31/2023 Due date: 09/03/2023 Assignee: Priority: Normal
Grupo P2-4 -
Feature #2429: Revisar el material y plani...
Feature #2429: Revisar el material y planificar una maqueta.
Project: Grupo P2-4 Status: New Start date: 08/28/2023 Due date: 09/03/2023 Assignee: Priority: Normal
GRUPO 3 A 2023 -
Feature #2542: Bitácora 3
Feature #2542: Bitácora 3
Project: GRUPO 3 A 2023 Status: New Start date: 08/28/2023 Due date: 09/03/2023 Assignee: Fabian Diaz Priority: Normal
GRUPO 2 B 2023 -
Bug #2735: Prueba Motores
Bug #2735: Prueba Motores
Project: GRUPO 2 B 2023 Status: New Start date: 09/03/2023 Due date: 09/10/2023 Assignee: Sebastian Caceres Priority: Normal
GRUPO 2 B 2023 -
Bug #2736: Movimiento del palo golf
Bug #2736: Movimiento del palo golf
Project: GRUPO 2 B 2023 Status: New Start date: 09/03/2023 Due date: 09/10/2023 Assignee: Sebastian Caceres Priority: Normal
GRUPO 2 B 2023 -
Bug #2737: Traslado del robot
Bug #2737: Traslado del robot
Project: GRUPO 2 B 2023 Status: New Start date: 09/03/2023 Due date: 09/10/2023 Assignee: Sebastian Caceres Priority: Normal
GRUPO 1 A 2023 -
Feature #2869: Diseño de Wiki
Feature #2869: Diseño de Wiki
Project: GRUPO 1 A 2023 Status: New Start date: 09/03/2023 Due date: 09/08/2023 Assignee: Tihare Cabello Priority: High |
4
Grupo P2-4 -
Feature #2430: Justificación del diseño de...
Feature #2430: Justificación del diseño de la maqueta.
Project: Grupo P2-4 Status: New Start date: 09/04/2023 Due date: 09/10/2023 Assignee: Priority: Normal
GRUPO 1 A 2023 -
Feature #2880: Creación y diseño
Feature #2880: Creación y diseño
Project: GRUPO 1 A 2023 Status: New Start date: 09/04/2023 Due date: 09/08/2023 Assignee: Melisa Laura Priority: Normal
GRUPO 3 A 2023 -
Feature #3001: Informe 1
Feature #3001: Informe 1
Project: GRUPO 3 A 2023 Status: New Start date: 09/04/2023 Due date: 09/15/2023 Assignee: Fabian Diaz Priority: Normal |
5
Grupo P2-5 -
Feature #2453: Construir maqueta
Feature #2453: Construir maqueta
Project: Grupo P2-5 Status: New Start date: 09/01/2023 Due date: 09/05/2023 Assignee: luciano vera Priority: Normal
Grupo P2-5 -
Feature #2789: Presentación maqueta
Feature #2789: Presentación maqueta
Project: Grupo P2-5 Status: New Start date: 09/05/2023 Due date: 09/05/2023 Assignee: bastian vega Priority: Normal
Grupo P2-6 -
Feature #3067: Formulación y construcción ...
Feature #3067: Formulación y construcción de la maqueta del proyecto.
Project: Grupo P2-6 Status: New Start date: 08/28/2023 Due date: 09/05/2023 Assignee: Priority: Normal
GRUPO 3 B 2023 -
Feature #3023: Prueba de conexión del serv...
Feature #3023: Prueba de conexión del servidor y cliente.
Project: GRUPO 3 B 2023 Status: New Start date: 09/05/2023 Due date: 09/08/2023 Assignee: Ignacio Gallardo Priority: Normal
GRUPO 3 B 2023 -
Feature #3024: Desarrollo del codigo para ...
Feature #3024: Desarrollo del codigo para el control del robot
Project: GRUPO 3 B 2023 Status: New Start date: 09/05/2023 Due date: 09/08/2023 Assignee: Ignacio Gallardo Priority: Normal
GRUPO 3 B 2023 -
Feature #3034: Avance wiki
Feature #3034: Avance wiki
Project: GRUPO 3 B 2023 Status: New Start date: 09/05/2023 Due date: 09/09/2023 Assignee: Esteban Gutierrez Priority: Normal
GRUPO 3 B 2023 -
Feature #3402: Presentacion I
Feature #3402: Presentacion I
Project: GRUPO 3 B 2023 Status: New Start date: 09/05/2023 Due date: 09/14/2023 Assignee: denis condori Priority: Normal
GRUPO 4 B 2023 -
Feature #2499: Semana 5
Feature #2499: Semana 5
Project: GRUPO 4 B 2023 Status: New Start date: 09/05/2023 Due date: 09/08/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2534: trabajar informe 1
Feature #2534: trabajar informe 1
Project: GRUPO 4 B 2023 Status: New Start date: 09/05/2023 Due date: 09/08/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2610: Avance certero Codificacion...
Feature #2610: Avance certero Codificacion golpe pelota python
Project: GRUPO 4 B 2023 Status: New Start date: 09/05/2023 Due date: 09/08/2023 Assignee: Priority: Normal
Grupo P2-3 -
Feature #2829: primera presentación evaluada
Feature #2829: primera presentación evaluada
Project: Grupo P2-3 Status: New Start date: 09/05/2023 Due date: 09/06/2023 Assignee: Priority: Normal |
6
Grupo P2-2 -
Bug #2576: Confección y presentación d...
Bug #2576: Confección y presentación de maqueta
Project: Grupo P2-2 Status: New Start date: 08/30/2023 Due date: 09/06/2023 Assignee: Priority: Normal
Grupo P2-3 -
Feature #2829: primera presentación evaluada
Feature #2829: primera presentación evaluada
Project: Grupo P2-3 Status: New Start date: 09/05/2023 Due date: 09/06/2023 Assignee: Priority: Normal
Grupo P2-6 -
Feature #3068: Redacción del informe 1.
Feature #3068: Redacción del informe 1.
Project: Grupo P2-6 Status: New Start date: 09/06/2023 Due date: 09/25/2023 Assignee: Priority: Normal |
7
GRUPO 1 B 2023 -
Feature #3305: Presentación I
Feature #3305: Presentación I
Project: GRUPO 1 B 2023 Status: New Start date: 09/07/2023 Due date: 09/15/2023 Assignee: Katalina Oviedo Priority: Normal
Grupo P2-5 -
Feature #2450: Informe l
Feature #2450: Informe l
Project: Grupo P2-5 Status: New Start date: 09/07/2023 Due date: 09/21/2023 Assignee: Andrew Campos Priority: Normal |
8
GRUPO 1 B 2023 -
Feature #3304: Informe I
Feature #3304: Informe I
Project: GRUPO 1 B 2023 Status: New Start date: 09/01/2023 Due date: 09/08/2023 Assignee: Katalina Oviedo Priority: Normal
GRUPO 3 B 2023 -
Feature #2718: Armado del Robot
Feature #2718: Armado del Robot
Project: GRUPO 3 B 2023 Status: New Start date: 08/22/2023 Due date: 09/08/2023 Assignee: denis condori Priority: Normal
GRUPO 3 B 2023 -
Feature #3023: Prueba de conexión del serv...
Feature #3023: Prueba de conexión del servidor y cliente.
Project: GRUPO 3 B 2023 Status: New Start date: 09/05/2023 Due date: 09/08/2023 Assignee: Ignacio Gallardo Priority: Normal
GRUPO 3 B 2023 -
Feature #3024: Desarrollo del codigo para ...
Feature #3024: Desarrollo del codigo para el control del robot
Project: GRUPO 3 B 2023 Status: New Start date: 09/05/2023 Due date: 09/08/2023 Assignee: Ignacio Gallardo Priority: Normal
GRUPO 3 B 2023 -
Feature #3376: Codificacion
Feature #3376: Codificacion
Project: GRUPO 3 B 2023 Status: New Start date: 08/24/2023 Due date: 09/08/2023 Assignee: Ignacio Gallardo Priority: Normal
GRUPO 4 B 2023 -
Feature #2499: Semana 5
Feature #2499: Semana 5
Project: GRUPO 4 B 2023 Status: New Start date: 09/05/2023 Due date: 09/08/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2534: trabajar informe 1
Feature #2534: trabajar informe 1
Project: GRUPO 4 B 2023 Status: New Start date: 09/05/2023 Due date: 09/08/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2610: Avance certero Codificacion...
Feature #2610: Avance certero Codificacion golpe pelota python
Project: GRUPO 4 B 2023 Status: New Start date: 09/05/2023 Due date: 09/08/2023 Assignee: Priority: Normal
GRUPO 1 A 2023 -
Feature #2848: Bitácoras
Feature #2848: Bitácoras
Project: GRUPO 1 A 2023 Status: New Start date: 08/16/2023 Due date: 09/08/2023 Assignee: Tihare Cabello Priority: Normal
GRUPO 1 A 2023 -
Feature #2869: Diseño de Wiki
Feature #2869: Diseño de Wiki
Project: GRUPO 1 A 2023 Status: New Start date: 09/03/2023 Due date: 09/08/2023 Assignee: Tihare Cabello Priority: High
GRUPO 1 A 2023 -
Feature #2878: Presentación 1
Feature #2878: Presentación 1
Project: GRUPO 1 A 2023 Status: New Start date: 08/30/2023 Due date: 09/08/2023 Assignee: Melisa Laura Priority: Normal
GRUPO 1 A 2023 -
Feature #2880: Creación y diseño
Feature #2880: Creación y diseño
Project: GRUPO 1 A 2023 Status: New Start date: 09/04/2023 Due date: 09/08/2023 Assignee: Melisa Laura Priority: Normal
GRUPO 4 A 2023 -
Feature #3046: Informe I
Feature #3046: Informe I
Project: GRUPO 4 A 2023 Status: New Start date: 08/25/2023 Due date: 09/08/2023 Assignee: Sergio Rabanal Priority: High
GRUPO 2 B 2023 -
Bug #2724: prototipo 1
Bug #2724: prototipo 1
Project: GRUPO 2 B 2023 Status: New Start date: 09/08/2023 Due date: 09/10/2023 Assignee: Priority: Normal
GRUPO 1 A 2023 -
Feature #2870: Desarrollo del proyecto
Feature #2870: Desarrollo del proyecto
Project: GRUPO 1 A 2023 Status: New Start date: 09/08/2023 Due date: 09/12/2023 Assignee: Liliana Galvez Priority: Normal
GRUPO 3 A 2023 -
Feature #2707: Bitácora 4
Feature #2707: Bitácora 4
Project: GRUPO 3 A 2023 Status: New Start date: 09/08/2023 Due date: 09/09/2023 Assignee: Fabian Diaz Priority: Normal
GRUPO 5 A 2023 -
Feature #2612: Creación de presentación I
Feature #2612: Creación de presentación I
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/08/2023 Due date: 09/15/2023 Assignee: Fabian Quezada Priority: High |
9
GRUPO 3 B 2023 -
Feature #3034: Avance wiki
Feature #3034: Avance wiki
Project: GRUPO 3 B 2023 Status: New Start date: 09/05/2023 Due date: 09/09/2023 Assignee: Esteban Gutierrez Priority: Normal
GRUPO 3 A 2023 -
Feature #2707: Bitácora 4
Feature #2707: Bitácora 4
Project: GRUPO 3 A 2023 Status: New Start date: 09/08/2023 Due date: 09/09/2023 Assignee: Fabian Diaz Priority: Normal |
37 |
10
GRUPO 2 B 2023 -
Bug #2716: Construcción del robot
Bug #2716: Construcción del robot
Project: GRUPO 2 B 2023 Status: New Start date: 08/14/2023 Due date: 09/10/2023 Assignee: Mario Villalobos Priority: Normal
GRUPO 2 B 2023 -
Bug #2717: Programación del robot
Bug #2717: Programación del robot
Project: GRUPO 2 B 2023 Status: New Start date: 08/14/2023 Due date: 09/10/2023 Assignee: Sebastian Caceres Priority: Normal
GRUPO 2 B 2023 -
Bug #2724: prototipo 1
Bug #2724: prototipo 1
Project: GRUPO 2 B 2023 Status: New Start date: 09/08/2023 Due date: 09/10/2023 Assignee: Priority: Normal
GRUPO 2 B 2023 -
Bug #2735: Prueba Motores
Bug #2735: Prueba Motores
Project: GRUPO 2 B 2023 Status: New Start date: 09/03/2023 Due date: 09/10/2023 Assignee: Sebastian Caceres Priority: Normal
GRUPO 2 B 2023 -
Bug #2736: Movimiento del palo golf
Bug #2736: Movimiento del palo golf
Project: GRUPO 2 B 2023 Status: New Start date: 09/03/2023 Due date: 09/10/2023 Assignee: Sebastian Caceres Priority: Normal
GRUPO 2 B 2023 -
Bug #2737: Traslado del robot
Bug #2737: Traslado del robot
Project: GRUPO 2 B 2023 Status: New Start date: 09/03/2023 Due date: 09/10/2023 Assignee: Sebastian Caceres Priority: Normal
GRUPO 2 B 2023 -
Bug #2738: Funciones por separado
Bug #2738: Funciones por separado
Project: GRUPO 2 B 2023 Status: New Start date: 08/27/2023 Due date: 09/10/2023 Assignee: Sebastian Caceres Priority: Normal
GRUPO 2 B 2023 -
Bug #2742: Informe Uno
Bug #2742: Informe Uno
Project: GRUPO 2 B 2023 Status: New Start date: 08/27/2023 Due date: 09/10/2023 Assignee: Ruben Salas Priority: Normal
Grupo P2-4 -
Feature #2430: Justificación del diseño de...
Feature #2430: Justificación del diseño de la maqueta.
Project: Grupo P2-4 Status: New Start date: 09/04/2023 Due date: 09/10/2023 Assignee: Priority: Normal |
11
Grupo P2-4 -
Feature #2431: Construcción maqueta
Feature #2431: Construcción maqueta
Project: Grupo P2-4 Status: New Start date: 09/11/2023 Due date: 09/17/2023 Assignee: Priority: Normal
GRUPO 3 A 2023 -
Feature #2840: Bitácora 5
Feature #2840: Bitácora 5
Project: GRUPO 3 A 2023 Status: New Start date: 09/11/2023 Due date: 09/15/2023 Assignee: Fabian Diaz Priority: Normal
GRUPO 3 A 2023 -
Feature #3000: Estimación de costos
Feature #3000: Estimación de costos
Project: GRUPO 3 A 2023 Status: New Start date: 09/11/2023 Due date: 09/14/2023 Assignee: Oscar Rolack Priority: Normal
GRUPO 3 A 2023 -
Feature #3002: Presentación 1
Feature #3002: Presentación 1
Project: GRUPO 3 A 2023 Status: New Start date: 09/11/2023 Due date: 09/15/2023 Assignee: Priority: Normal |
12
GRUPO 1 A 2023 -
Feature #2865: Diseño Wiki
Feature #2865: Diseño Wiki
Project: GRUPO 1 A 2023 Status: New Start date: 08/21/2023 Due date: 09/12/2023 Assignee: Liliana Galvez Priority: High
GRUPO 1 A 2023 -
Feature #2870: Desarrollo del proyecto
Feature #2870: Desarrollo del proyecto
Project: GRUPO 1 A 2023 Status: New Start date: 09/08/2023 Due date: 09/12/2023 Assignee: Liliana Galvez Priority: Normal
Grupo P2-7-2 -
Feature #3101: Definicion del Proyecto
Feature #3101: Definicion del Proyecto
Project: Grupo P2-7-2 Status: Resolved Start date: 09/01/2023 Due date: 09/12/2023 Assignee: Priority: Normal
Grupo P2-7-2 -
Feature #3102: Crear la presentacion y maq...
Feature #3102: Crear la presentacion y maqueta
Project: Grupo P2-7-2 Status: New Start date: 09/01/2023 Due date: 09/12/2023 Assignee: Priority: Normal
Grupo P2-5 -
Feature #3104: Análisis de framework
Feature #3104: Análisis de framework
Project: Grupo P2-5 Status: New Start date: 09/12/2023 Due date: 09/16/2023 Assignee: bastian vega Priority: Normal
Grupo P2-7-2 -
Feature #3103: Presentar la maqueta y la p...
Feature #3103: Presentar la maqueta y la presentacion
Project: Grupo P2-7-2 Status: New Start date: 09/12/2023 Due date: 09/13/2023 Assignee: Priority: Normal
Grupo P2-7-2 -
Feature #3110: Redaccion del Informe 1
Feature #3110: Redaccion del Informe 1
Project: Grupo P2-7-2 Status: New Start date: 09/12/2023 Due date: 09/25/2023 Assignee: Priority: Normal |
13
GRUPO 3 A 2023 -
Feature #2997: Formulación del proyecto
Feature #2997: Formulación del proyecto
Project: GRUPO 3 A 2023 Status: New Start date: 08/18/2023 Due date: 09/13/2023 Assignee: Priority: Normal
GRUPO 3 A 2023 -
Feature #2999: Construcción del robot
Feature #2999: Construcción del robot
Project: GRUPO 3 A 2023 Status: New Start date: 08/18/2023 Due date: 09/13/2023 Assignee: Juan Casilla Priority: Normal
Grupo P2-7-2 -
Feature #3103: Presentar la maqueta y la p...
Feature #3103: Presentar la maqueta y la presentacion
Project: Grupo P2-7-2 Status: New Start date: 09/12/2023 Due date: 09/13/2023 Assignee: Priority: Normal
GRUPO 2 A 2023 -
Support #3126: Realizar la Wiki
Support #3126: Realizar la Wiki
Project: GRUPO 2 A 2023 Status: In Progress Start date: 09/02/2023 Due date: 09/13/2023 Assignee: Angie Martinez Priority: Normal
GRUPO 4 B 2023 -
Feature #2500: Semana 6
Feature #2500: Semana 6
Project: GRUPO 4 B 2023 Status: New Start date: 09/13/2023 Due date: 09/14/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2954: se prepara ppt presentacion...
Feature #2954: se prepara ppt presentacion informe 1
Project: GRUPO 4 B 2023 Status: New Start date: 09/13/2023 Due date: 09/14/2023 Assignee: Priority: Normal
Grupo P2-3 -
Feature #3085: Informe del proyecto fase 1
Feature #3085: Informe del proyecto fase 1
Project: Grupo P2-3 Status: New Start date: 09/13/2023 Due date: 09/26/2023 Assignee: Priority: Normal |
14
GRUPO 3 B 2023 -
Feature #2705: Fase 1
Feature #2705: Fase 1
Project: GRUPO 3 B 2023 Status: New Start date: 08/17/2023 Due date: 09/14/2023 Assignee: denis condori Priority: Normal
GRUPO 3 B 2023 -
Feature #3033: Informe I
Feature #3033: Informe I
Project: GRUPO 3 B 2023 Status: New Start date: 08/29/2023 Due date: 09/14/2023 Assignee: denis condori Priority: Normal
GRUPO 3 B 2023 -
Feature #3402: Presentacion I
Feature #3402: Presentacion I
Project: GRUPO 3 B 2023 Status: New Start date: 09/05/2023 Due date: 09/14/2023 Assignee: denis condori Priority: Normal
GRUPO 4 B 2023 -
Feature #2500: Semana 6
Feature #2500: Semana 6
Project: GRUPO 4 B 2023 Status: New Start date: 09/13/2023 Due date: 09/14/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2954: se prepara ppt presentacion...
Feature #2954: se prepara ppt presentacion informe 1
Project: GRUPO 4 B 2023 Status: New Start date: 09/13/2023 Due date: 09/14/2023 Assignee: Priority: Normal
GRUPO 1 A 2023 -
Feature #2844: Fase 1
Feature #2844: Fase 1
Project: GRUPO 1 A 2023 Status: New Start date: 08/16/2023 Due date: 09/14/2023 Assignee: Melisa Laura Priority: High
GRUPO 1 A 2023 -
Feature #2846: Documentación
Feature #2846: Documentación
Project: GRUPO 1 A 2023 Status: New Start date: 08/16/2023 Due date: 09/14/2023 Assignee: Tihare Cabello Priority: Normal
GRUPO 1 A 2023 -
Feature #2850: Informe 1
Feature #2850: Informe 1
Project: GRUPO 1 A 2023 Status: New Start date: 08/23/2023 Due date: 09/14/2023 Assignee: Melisa Laura Priority: Normal
GRUPO 3 A 2023 -
Feature #3000: Estimación de costos
Feature #3000: Estimación de costos
Project: GRUPO 3 A 2023 Status: New Start date: 09/11/2023 Due date: 09/14/2023 Assignee: Oscar Rolack Priority: Normal
GRUPO 5 A 2023 -
Feature #2611: Creación de informe I
Feature #2611: Creación de informe I
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/02/2023 Due date: 09/14/2023 Assignee: Diego Ferrada Priority: Normal
GRUPO 5 A 2023 -
Feature #3437: Panorama General
Feature #3437: Panorama General
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/02/2023 Due date: 09/14/2023 Assignee: Javier Huanca Priority: Normal
GRUPO 5 A 2023 -
Feature #3438: Organizacion del Personal
Feature #3438: Organizacion del Personal
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/02/2023 Due date: 09/14/2023 Assignee: Javier Huanca Priority: Normal
GRUPO 5 A 2023 -
Feature #3439: Planificacion del Proyecto
Feature #3439: Planificacion del Proyecto
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/02/2023 Due date: 09/14/2023 Assignee: Javier Huanca Priority: Normal
GRUPO 5 A 2023 -
Feature #3440: Planificacion de los Recursos
Feature #3440: Planificacion de los Recursos
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/02/2023 Due date: 09/14/2023 Assignee: Javier Huanca Priority: Normal
GRUPO 2 A 2023 -
Support #3129: Informe I
Support #3129: Informe I
Project: GRUPO 2 A 2023 Status: Resolved Start date: 09/14/2023 Due date: 09/25/2023 Assignee: Priority: High |
15
GRUPO 1 B 2023 -
Feature #3295: Etapa I
Feature #3295: Etapa I
Project: GRUPO 1 B 2023 Status: New Start date: 08/15/2023 Due date: 09/15/2023 Assignee: Priority: Normal
GRUPO 1 B 2023 -
Feature #3305: Presentación I
Feature #3305: Presentación I
Project: GRUPO 1 B 2023 Status: New Start date: 09/07/2023 Due date: 09/15/2023 Assignee: Katalina Oviedo Priority: Normal
GRUPO 5 B 2023 -
Feature #2496: Fase 1
Feature #2496: Fase 1
Project: GRUPO 5 B 2023 Status: In Progress Start date: 08/11/2023 Due date: 09/15/2023 Assignee: Priority: Normal
GRUPO 3 A 2023 -
Feature #2840: Bitácora 5
Feature #2840: Bitácora 5
Project: GRUPO 3 A 2023 Status: New Start date: 09/11/2023 Due date: 09/15/2023 Assignee: Fabian Diaz Priority: Normal
GRUPO 3 A 2023 -
Feature #2996: Etapa 1
Feature #2996: Etapa 1
Project: GRUPO 3 A 2023 Status: New Start date: 08/18/2023 Due date: 09/15/2023 Assignee: Priority: Normal
GRUPO 3 A 2023 -
Feature #3001: Informe 1
Feature #3001: Informe 1
Project: GRUPO 3 A 2023 Status: New Start date: 09/04/2023 Due date: 09/15/2023 Assignee: Fabian Diaz Priority: Normal
GRUPO 3 A 2023 -
Feature #3002: Presentación 1
Feature #3002: Presentación 1
Project: GRUPO 3 A 2023 Status: New Start date: 09/11/2023 Due date: 09/15/2023 Assignee: Priority: Normal
GRUPO 4 A 2023 -
Feature #3036: Etapa I
Feature #3036: Etapa I
Project: GRUPO 4 A 2023 Status: New Start date: 08/14/2023 Due date: 09/15/2023 Assignee: Cristian Sanchez Priority: Immediate
GRUPO 4 A 2023 -
Feature #3047: Presentacion I
Feature #3047: Presentacion I
Project: GRUPO 4 A 2023 Status: New Start date: 09/01/2023 Due date: 09/15/2023 Assignee: Sergio Rabanal Priority: High
GRUPO 5 A 2023 -
Feature #2612: Creación de presentación I
Feature #2612: Creación de presentación I
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/08/2023 Due date: 09/15/2023 Assignee: Fabian Quezada Priority: High
GRUPO 5 A 2023 -
Feature #3078: Fase I
Feature #3078: Fase I
Project: GRUPO 5 A 2023 Status: Resolved Start date: 08/14/2023 Due date: 09/15/2023 Assignee: Priority: High
GRUPO 5 B 2023 -
Support #2744: Informe I
Support #2744: Informe I
Project: GRUPO 5 B 2023 Status: New Start date: 09/01/2023 Due date: 09/15/2023 Assignee: Priority: Normal
GRUPO 5 B 2023 -
Support #2745: Presentación 1
Support #2745: Presentación 1
Project: GRUPO 5 B 2023 Status: New Start date: 09/01/2023 Due date: 09/15/2023 Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2608: entrega informe 1
Feature #2608: entrega informe 1
Project: GRUPO 4 B 2023 Status: New Start date: 09/15/2023 Due date: Assignee: Priority: Normal
GRUPO 4 B 2023 -
Feature #2609: presentacion avance proyecto
Feature #2609: presentacion avance proyecto
Project: GRUPO 4 B 2023 Status: New Start date: 09/15/2023 Due date: Assignee: Priority: Normal
GRUPO 4 A 2023 -
Feature #3037: Etapa II
Feature #3037: Etapa II
Project: GRUPO 4 A 2023 Status: New Start date: 09/15/2023 Due date: 12/06/2023 Assignee: Cristian Sanchez Priority: Immediate
GRUPO 4 A 2023 -
Feature #3048: Estudio de LINUX
Feature #3048: Estudio de LINUX
Project: GRUPO 4 A 2023 Status: New Start date: 09/15/2023 Due date: 09/18/2023 Assignee: Cristian Sanchez Priority: Normal
GRUPO 4 A 2023 -
Feature #3049: Programación
Feature #3049: Programación
Project: GRUPO 4 A 2023 Status: New Start date: 09/15/2023 Due date: 11/29/2023 Assignee: Cristian Sanchez Priority: Urgent
GRUPO 4 A 2023 -
Feature #3050: Estudio de librerias ev3dev
Feature #3050: Estudio de librerias ev3dev
Project: GRUPO 4 A 2023 Status: New Start date: 09/15/2023 Due date: 09/18/2023 Assignee: Cristian Sanchez Priority: High |
16
Grupo P2-5 -
Feature #3104: Análisis de framework
Feature #3104: Análisis de framework
Project: Grupo P2-5 Status: New Start date: 09/12/2023 Due date: 09/16/2023 Assignee: bastian vega Priority: Normal |
38 |
17
GRUPO 2 B 2023 -
Bug #2702: Entrega I
Bug #2702: Entrega I
Project: GRUPO 2 B 2023 Status: New Start date: 08/14/2023 Due date: 09/17/2023 Assignee: Kary Tudela Priority: Normal
GRUPO 2 B 2023 -
Bug #2739: Entregas
Bug #2739: Entregas
Project: GRUPO 2 B 2023 Status: New Start date: 08/14/2023 Due date: 09/17/2023 Assignee: Vaitheare Gomez Priority: Normal
GRUPO 2 B 2023 -
Bug #2740: Bitacoras Semanales
Bug #2740: Bitacoras Semanales
Project: GRUPO 2 B 2023 Status: New Start date: 08/14/2023 Due date: 09/17/2023 Assignee: Vaitheare Gomez Priority: Normal
GRUPO 2 B 2023 -
Bug #2741: Wiki
Bug #2741: Wiki
Project: GRUPO 2 B 2023 Status: New Start date: 08/27/2023 Due date: 09/17/2023 Assignee: Kary Tudela Priority: Normal
GRUPO 2 B 2023 -
Bug #2743: Presentación Uno
Bug #2743: Presentación Uno
Project: GRUPO 2 B 2023 Status: New Start date: 08/27/2023 Due date: 09/17/2023 Assignee: Ruben Salas Priority: Normal
Grupo P2-4 -
Feature #2431: Construcción maqueta
Feature #2431: Construcción maqueta
Project: Grupo P2-4 Status: New Start date: 09/11/2023 Due date: 09/17/2023 Assignee: Priority: Normal
Grupo P2-5 -
Feature #2449: Estimar costos
Feature #2449: Estimar costos
Project: Grupo P2-5 Status: New Start date: 09/17/2023 Due date: 09/20/2023 Assignee: bastian vega Priority: Normal |
18
GRUPO 4 A 2023 -
Feature #3048: Estudio de LINUX
Feature #3048: Estudio de LINUX
Project: GRUPO 4 A 2023 Status: New Start date: 09/15/2023 Due date: 09/18/2023 Assignee: Cristian Sanchez Priority: Normal
GRUPO 4 A 2023 -
Feature #3050: Estudio de librerias ev3dev
Feature #3050: Estudio de librerias ev3dev
Project: GRUPO 4 A 2023 Status: New Start date: 09/15/2023 Due date: 09/18/2023 Assignee: Cristian Sanchez Priority: High
GRUPO 4 A 2023 -
Feature #3052: Prueba de conexiones
Feature #3052: Prueba de conexiones
Project: GRUPO 4 A 2023 Status: New Start date: 09/18/2023 Due date: 09/18/2023 Assignee: Cristian Sanchez Priority: Immediate
GRUPO 1 B 2023 -
Feature #3296: Etapa II
Feature #3296: Etapa II
Project: GRUPO 1 B 2023 Status: New Start date: 09/18/2023 Due date: 12/07/2023 Assignee: Priority: Normal
GRUPO 1 B 2023 -
Feature #3306: Estudiar librerias EV3
Feature #3306: Estudiar librerias EV3
Project: GRUPO 1 B 2023 Status: New Start date: 09/18/2023 Due date: 09/21/2023 Assignee: Katalina Oviedo Priority: Normal
Grupo P2-4 -
Feature #2432: Entrega de Primer Informe d...
Feature #2432: Entrega de Primer Informe de Avance
Project: Grupo P2-4 Status: New Start date: 09/18/2023 Due date: 10/01/2023 Assignee: Priority: Normal
GRUPO 4 A 2023 -
Feature #3051: Conexion al EV3
Feature #3051: Conexion al EV3
Project: GRUPO 4 A 2023 Status: New Start date: 09/18/2023 Due date: 09/20/2023 Assignee: Cristian Sanchez Priority: Urgent
GRUPO 5 A 2023 -
Feature #3080: Creación de interfaz gráfica
Feature #3080: Creación de interfaz gráfica
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/18/2023 Due date: 10/27/2023 Assignee: Maykol Bravo Priority: High |
19 |
20
Grupo P2-2 -
Bug #2577: Entrega y presentación de I...
Bug #2577: Entrega y presentación de Informe
Project: Grupo P2-2 Status: New Start date: 08/22/2023 Due date: 09/20/2023 Assignee: Priority: Normal
Grupo P2-5 -
Feature #2449: Estimar costos
Feature #2449: Estimar costos
Project: Grupo P2-5 Status: New Start date: 09/17/2023 Due date: 09/20/2023 Assignee: bastian vega Priority: Normal
GRUPO 4 A 2023 -
Feature #3051: Conexion al EV3
Feature #3051: Conexion al EV3
Project: GRUPO 4 A 2023 Status: New Start date: 09/18/2023 Due date: 09/20/2023 Assignee: Cristian Sanchez Priority: Urgent
GRUPO 4 A 2023 -
Feature #3053: Pruebas de codificación
Feature #3053: Pruebas de codificación
Project: GRUPO 4 A 2023 Status: New Start date: 09/20/2023 Due date: 09/20/2023 Assignee: Jean-Pierre Huanca Priority: Normal
Grupo P2-7-2 -
Feature #3107: Redactar Gestion de Riesgos
Feature #3107: Redactar Gestion de Riesgos
Project: Grupo P2-7-2 Status: New Start date: 09/20/2023 Due date: 09/20/2023 Assignee: Priority: Normal |
21
GRUPO 1 B 2023 -
Feature #3306: Estudiar librerias EV3
Feature #3306: Estudiar librerias EV3
Project: GRUPO 1 B 2023 Status: New Start date: 09/18/2023 Due date: 09/21/2023 Assignee: Katalina Oviedo Priority: Normal
Grupo P2-5 -
Feature #2450: Informe l
Feature #2450: Informe l
Project: Grupo P2-5 Status: New Start date: 09/07/2023 Due date: 09/21/2023 Assignee: Andrew Campos Priority: Normal
Grupo P2-7-2 -
Feature #3111: Desarrollar punto 1 y 3 del...
Feature #3111: Desarrollar punto 1 y 3 del informe 1
Project: Grupo P2-7-2 Status: New Start date: 09/21/2023 Due date: 09/23/2023 Assignee: Priority: Normal |
22
GRUPO 1 B 2023 -
Feature #3308: Programación del robot
Feature #3308: Programación del robot
Project: GRUPO 1 B 2023 Status: New Start date: 09/22/2023 Due date: 11/06/2023 Assignee: Katalina Oviedo Priority: Normal
GRUPO 1 B 2023 -
Feature #3309: Programación de los movimie...
Feature #3309: Programación de los movimientos del robot.
Project: GRUPO 1 B 2023 Status: New Start date: 09/22/2023 Due date: 10/10/2023 Assignee: Katalina Oviedo Priority: Normal
Grupo P2-5 -
Feature #2451: Presentación l
Feature #2451: Presentación l
Project: Grupo P2-5 Status: New Start date: 09/22/2023 Due date: 09/25/2023 Assignee: luciano vera Priority: Normal
GRUPO 4 A 2023 -
Feature #3054: Creación de la GUI
Feature #3054: Creación de la GUI
Project: GRUPO 4 A 2023 Status: New Start date: 09/22/2023 Due date: 11/29/2023 Assignee: Cristian Sanchez Priority: Normal |
23
Grupo P2-7-2 -
Feature #3111: Desarrollar punto 1 y 3 del...
Feature #3111: Desarrollar punto 1 y 3 del informe 1
Project: Grupo P2-7-2 Status: New Start date: 09/21/2023 Due date: 09/23/2023 Assignee: Priority: Normal
Grupo P2-7-2 -
Feature #3112: Desarrollar punto 4 y compl...
Feature #3112: Desarrollar punto 4 y completar Informe 1
Project: Grupo P2-7-2 Status: New Start date: 09/23/2023 Due date: 09/23/2023 Assignee: Priority: Normal |
39 |
24 |
25
Grupo P2-5 -
Feature #2446: Parte l
Feature #2446: Parte l
Project: Grupo P2-5 Status: New Start date: 08/21/2023 Due date: 09/25/2023 Assignee: Vranika Santiago Priority: Normal
Grupo P2-5 -
Feature #2451: Presentación l
Feature #2451: Presentación l
Project: Grupo P2-5 Status: New Start date: 09/22/2023 Due date: 09/25/2023 Assignee: luciano vera Priority: Normal
Grupo P2-6 -
Feature #3068: Redacción del informe 1.
Feature #3068: Redacción del informe 1.
Project: Grupo P2-6 Status: New Start date: 09/06/2023 Due date: 09/25/2023 Assignee: Priority: Normal
GRUPO 2 A 2023 -
Feature #3128: Bitocara (primera etapa)
Feature #3128: Bitocara (primera etapa)
Project: GRUPO 2 A 2023 Status: Resolved Start date: 08/15/2023 Due date: 09/25/2023 Assignee: Polette Montt Priority: Normal
Grupo P2-7-2 -
Feature #3110: Redaccion del Informe 1
Feature #3110: Redaccion del Informe 1
Project: Grupo P2-7-2 Status: New Start date: 09/12/2023 Due date: 09/25/2023 Assignee: Priority: Normal
GRUPO 2 A 2023 -
Support #3121: Parte I
Support #3121: Parte I
Project: GRUPO 2 A 2023 Status: New Start date: 08/11/2023 Due date: 09/25/2023 Assignee: Priority: High
GRUPO 2 A 2023 -
Support #3129: Informe I
Support #3129: Informe I
Project: GRUPO 2 A 2023 Status: Resolved Start date: 09/14/2023 Due date: 09/25/2023 Assignee: Priority: High
Grupo P2-5 -
Feature #2454: Parte ll
Feature #2454: Parte ll
Project: Grupo P2-5 Status: New Start date: 09/25/2023 Due date: 11/28/2023 Assignee: Vranika Santiago Priority: Normal
Grupo P2-5 -
Feature #2839: Realizar Casos de Uso
Feature #2839: Realizar Casos de Uso
Project: Grupo P2-5 Status: New Start date: 09/25/2023 Due date: 11/03/2023 Assignee: Andrew Campos Priority: Normal
GRUPO 1 A 2023 -
Feature #3345: Fase 2
Feature #3345: Fase 2
Project: GRUPO 1 A 2023 Status: New Start date: 09/25/2023 Due date: 12/04/2023 Assignee: Cristian Huanca Priority: Urgent
GRUPO 1 A 2023 -
Feature #3347: Bitacoras
Feature #3347: Bitacoras
Project: GRUPO 1 A 2023 Status: New Start date: 09/25/2023 Due date: 12/01/2023 Assignee: Cristian Huanca Priority: Normal
GRUPO 3 A 2023 -
Feature #2988: Programación de interfaz
Feature #2988: Programación de interfaz
Project: GRUPO 3 A 2023 Status: New Start date: 09/25/2023 Due date: 12/05/2023 Assignee: Andrea Navia Priority: Normal
GRUPO 3 A 2023 -
Feature #3181: Bitácora 6
Feature #3181: Bitácora 6
Project: GRUPO 3 A 2023 Status: New Start date: 09/25/2023 Due date: 09/30/2023 Assignee: Fabian Diaz Priority: Normal
GRUPO 5 A 2023 -
Feature #3084: Estudiar Ev3dev
Feature #3084: Estudiar Ev3dev
Project: GRUPO 5 A 2023 Status: Resolved Start date: 09/25/2023 Due date: 10/02/2023 Assignee: Diego Ferrada Priority: High
Grupo P2-7-2 -
Feature #3113: Estudio de carascteristicas...
Feature #3113: Estudio de carascteristicas raspberry
Project: Grupo P2-7-2 Status: New Start date: 09/25/2023 Due date: 10/04/2023 Assignee: Priority: Normal |
26
Grupo P2-3 -
Feature #2821: Primera fase del proyecto
Feature #2821: Primera fase del proyecto
Project: Grupo P2-3 Status: New Start date: 08/23/2023 Due date: 09/26/2023 Assignee: alexis yucra Priority: Normal
Grupo P2-3 -
Feature #3085: Informe del proyecto fase 1
Feature #3085: Informe del proyecto fase 1
Project: Grupo P2-3 Status: New Start date: 09/13/2023 Due date: 09/26/2023 Assignee: Priority: Normal
Grupo P2-6 -
Feature #3086: Entrega informe 1 y demostr...
Feature #3086: Entrega informe 1 y demostración
Project: Grupo P2-6 Status: New Start date: 09/26/2023 Due date: 09/26/2023 Assignee: Priority: Immediate
GRUPO 4 B 2023 -
Bug #3160: Semana 7
Bug #3160: Semana 7
Project: GRUPO 4 B 2023 Status: New Start date: 09/26/2023 Due date: Assignee: Priority: Normal
GRUPO 4 B 2023 -
Bug #3161: Cambio de Roles
Bug #3161: Cambio de Roles
Project: GRUPO 4 B 2023 Status: New Start date: 09/26/2023 Due date: Assignee: Priority: Normal
GRUPO 5 B 2023 -
Feature #2484: Fase 2
Feature #2484: Fase 2
Project: GRUPO 5 B 2023 Status: In Progress Start date: 09/26/2023 Due date: 12/07/2023 Assignee: Nelson Ramirez Priority: High
GRUPO 5 B 2023 -
Feature #2493: Estudio
Feature #2493: Estudio
Project: GRUPO 5 B 2023 Status: New Start date: 09/26/2023 Due date: 10/17/2023 Assignee: Priority: Normal
GRUPO 5 B 2023 -
Support #2494: Investigar sobre EV3
Support #2494: Investigar sobre EV3
Project: GRUPO 5 B 2023 Status: New Start date: 09/26/2023 Due date: 10/03/2023 Assignee: Nelson Ramirez Priority: Normal |
27 |
28 |
29
GRUPO 1 B 2023 -
Feature #3310: Creación interfaz gráfica
Feature #3310: Creación interfaz gráfica
Project: GRUPO 1 B 2023 Status: New Start date: 09/29/2023 Due date: 11/06/2023 Assignee: Jorge Caceres Priority: Normal
GRUPO 5 B 2023 -
Feature #2764: Programación
Feature #2764: Programación
Project: GRUPO 5 B 2023 Status: New Start date: 09/29/2023 Due date: 11/24/2023 Assignee: Priority: Normal
GRUPO 5 B 2023 -
Support #2495: Estudiar librerias Python
Support #2495: Estudiar librerias Python
Project: GRUPO 5 B 2023 Status: New Start date: 09/29/2023 Due date: 10/17/2023 Assignee: Jose Escalante Priority: Normal
GRUPO 5 B 2023 -
Support #2765: Programación en python
Support #2765: Programación en python
Project: GRUPO 5 B 2023 Status: New Start date: 09/29/2023 Due date: 10/06/2023 Assignee: Jose Escalante Priority: Normal |
30
GRUPO 3 A 2023 -
Feature #3181: Bitácora 6
Feature #3181: Bitácora 6
Project: GRUPO 3 A 2023 Status: New Start date: 09/25/2023 Due date: 09/30/2023 Assignee: Fabian Diaz Priority: Normal |