Feature #5701

Fase 2: Desarrollo

Added by martin castillo 30 days ago. Updated 11 days ago.

Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
10/21/2025
Due date:
11/25/2025
% Done:

100%


Subtasks

Feature #5702: Iniciar raspberry pi 4 BNew

Feature #5895: Instalación de librerías necesariasNew

Feature #5896: Redacción del informe 2New

Feature #5897: Creación de modelos de procesoNew

Feature #5898: Creación de la presentación 2New

History

#1 Updated by martin castillo 30 days ago

  • Tracker changed from Bug to Feature

#2 Updated by martin castillo 30 days ago

  • Due date set to 11/27/2025
  • Start date changed from 11/06/2025 to 10/21/2025
  • % Done changed from 0 to 10

#3 Updated by martin castillo 30 days ago

  • Status changed from New to In Progress
  • % Done changed from 10 to 30