Support #5759: Sistemas de prueba

Support #5448: Prueba sistema 1

Prueba del sistema con grafana

Added by Scarlet Gavia Mondaca about 2 months ago. Updated 24 days ago.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
11/10/2025
Due date:
11/24/2025
% Done:

80%


Description

Se realiza las instalaciones debidas para dejar el dashboard funcional.


Subtasks

Feature #5458: Vistas de los datos generadosNew

History

#1 Updated by Scarlet Gavia Mondaca about 2 months ago

  • Start date changed from 10/15/2025 to 10/17/2025

#2 Updated by Scarlet Gavia Mondaca about 2 months ago

  • Due date changed from 10/22/2025 to 11/07/2025
  • Start date changed from 10/17/2025 to 10/24/2025

#3 Updated by Scarlet Gavia Mondaca about 2 months ago

  • Start date changed from 10/24/2025 to 10/29/2025

#4 Updated by Scarlet Gavia Mondaca about 2 months ago

  • Due date changed from 11/07/2025 to 11/14/2025
  • Start date changed from 10/29/2025 to 11/05/2025

#5 Updated by Scarlet Gavia Mondaca about 2 months ago

  • Subject changed from Instalación de dashboard to Pruebas final del sistema
  • Due date changed from 11/14/2025 to 11/17/2025
  • Start date changed from 11/05/2025 to 11/10/2025

#6 Updated by Scarlet Gavia Mondaca 24 days ago

  • Parent task set to #5448

#7 Updated by Scarlet Gavia Mondaca 24 days ago

  • Subject changed from Pruebas final del sistema to Prueba del sistema con grafana