Feature #3581

Feature #3538: Documentación del Plan de Proyecto (Avance 3)

Implementar Back-End

Added by Diego Baltazar 9 months ago. Updated 7 months ago.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
05/07/2024
Due date:
06/10/2024
% Done:

100%


Description

Llevar a cabo la implementación inicial del Back-End del Sistema.

History

#1 Updated by Diego Baltazar 9 months ago

  • Subject changed from Llevar a cabo la implementación inicial del Back-End del Sistema. to Implementar Back-End

#2 Updated by Diego Baltazar 8 months ago

  • % Done changed from 0 to 20

#3 Updated by Diego Baltazar 7 months ago

  • % Done changed from 20 to 80

#4 Updated by Diego Baltazar 7 months ago

  • Due date changed from 05/07/2024 to 06/10/2024
  • Start date changed from 04/30/2024 to 05/07/2024

#5 Updated by Diego Baltazar 7 months ago

  • % Done changed from 80 to 100

Also available in: Atom PDF